Optimal job scheduling explained
Optimal job scheduling is a class of optimization problems related to scheduling. The inputs to such problems are a list of jobs (also called processes or tasks) and a list of machines (also called processors or workers). The required output is a schedule – an assignment of jobs to machines. The schedule should optimize a certain objective function. In the literature, problems of optimal job scheduling are often called machine scheduling, processor scheduling, multiprocessor scheduling, or just scheduling.
There are many different problems of optimal job scheduling, different in the nature of jobs, the nature of machines, the restrictions on the schedule, and the objective function. A convenient notation for optimal scheduling problems was introduced by Ronald Graham, Eugene Lawler, Jan Karel Lenstra and Alexander Rinnooy Kan. It consists of three fields: α, β and γ. Each field may be a comma separated list of words. The α field describes the machine environment, β the job characteristics and constraints, and γ the objective function.[1] Since its introduction in the late 1970s the notation has been constantly extended, sometimes inconsistently. As a result, today there are some problems that appear with distinct notations in several papers.
Single-stage jobs vs. multi-stage jobs
In the simpler optimal job scheduling problems, each job j consists of a single execution phase, with a given processing time pj. In more complex variants, each job consists of several execution phases, which may be executed in sequence or in parallel.
Machine environments
In single-stage job scheduling problems, there are four main categories of machine environments:
parallel machines, and they are identical. Job
takes time
on any machine it is scheduled to.
parallel machines, and they have different given speeds. Job
on machine
takes time
.
parallel machines, and they are unrelated – Job
on machine
takes time
.
These letters might be followed by the number of machines, which is then fixed. For example, P2 indicates that there are two parallel identical machines. Pm indicates that there are m parallel identical machines, where m is a fixed parameter. In contrast, P indicates that there are m parallel identical machines, but m is not fixed (it is part of the input).
In multi-stage job scheduling problems, there are other options for the machine environments:
consists of
operations
for
. The operations can be scheduled in
any order. Operation
must be processed for
units on machine
.
consists of
operations
for
, to be scheduled in
the given order. Operation
must be processed for
units on machine
.
consists of
operations
for
, to be scheduled in that order. Operation
must be processed for
units on a
dedicated machine
with
for
.
Job characteristics
All processing times are assumed to be integers. In some older research papers however they are assumed to be rationals.
, or
: the processing time is equal for all jobs.
, or
: the processing time is equal to 1 time-unit for all jobs.
for each job a release time is given before which it cannot be scheduled, default is 0.
: an online problem. Jobs are revealed at their release times. In this context the performance of an algorithm is measured by its
competitive ratio.
: for each job a due date is given. The idea is that every job should complete before its due date and there is some penalty for jobs that complete late. This penalty is denoted in the objective value. The presence of the job characteristic
is implicitly assumed and not denoted in the problem name, unless there are some restrictions as for example
, assuming that all due dates are equal to some given date.
: for each job a strict deadline is given. Every job must complete before its deadline.
- pmtn: Jobs can be preempted and resumed possibly on another machine. Sometimes also denoted by 'prmp'.
: Each job comes with a number of machines on which it must be scheduled at the same time. The default is 1. This is an important parameter in the variant called
parallel task scheduling.
Precedence relations
Each pair of two jobs may or may not have a precedence relation. A precedence relation between two jobs means that one job must be finished before the other job. For example, if job i is a predecessor of job j in that order, job j can only start once job i is completed.
- prec: There are no restrictions placed on the precedence relations.
- chains: Each job is the predecessor of at most one other job and is preceded by at most one other job.
- tree: The precedence relations must satisfy one of the two restrictions.
- intree: Each node is the predecessor of at most one other job.
- outtree: Each node is preceded by at most one other job.
- opposing forest: If the graph of precedence relations is split into connected components, then each connected component is either an intree or outtree.
- sp-graph: The graph of precedence relations is a series parallel graph.
- bounded height: The length of the longest directed path is capped at a fixed value. (A directed path is a sequence of jobs where each job except the last is a predecessor of the next job in the sequence.)
- level order: Each job has a level, which is the length of the longest directed path starting from that job. Each job with level
is a predecessor of every job with level
.
has an interval and job
is a predecessor of
if and only if the end of the interval of
is strictly less than the start of the interval for
.=
In the presence of a precedence relation one might in addition assume time lags. The time lag between two jobs is the amount of time that must be waited after the first job is complete before the second job to begin. Formally, if job i precedes job j, then
must be true. If no time lag
is specified then it is assumed to be zero. Time lags can also be negative. A negative time lag means that the second job can begin a fixed time before the first job finishes.
- ℓ: The time lag is the same for each pair of jobs.
: Different pairs of jobs can have different time lags.
Transportation delays
: Between the completion of operation
of job
on machine
and the start of operation
of job
on machine
, there is a transportation delay of at least
units.
: Between the completion of operation
of job
on machine
and the start of operation
of job
on machine
, there is a transportation delay of at least
units.
: Machine dependent transportation delay. Between the completion of operation
of job
on machine
and the start of operation
of job
on machine
, there is a transportation delay of at least
units.
: Machine pair dependent transportation delay. Between the completion of operation
of job
on machine
and the start of operation
of job
on machine
, there is a transportation delay of at least
units.
: Job dependent transportation delay. Between the completion of operation
of job
on machine
and the start of operation
of job
on machine
, there is a transportation delay of at least
units.
Various constraints
- rcrc: Also known as Recirculation or flexible job shop. The promise on
is lifted and for some pairs
we might have
. In other words, it is possible for different operations of the same job to be assigned to the same machine.
must start exactly when operation
completes. In other words, once one operation of a job finishes, the next operation must begin immediately. Sometimes also denoted as
'nwt'.
- no-idle: No machine may ever be idle between the start of its first execution to the end of its last execution.
: Multiprocessor tasks on identical parallel machines. The execution of job
is done simultaneously on
parallel machines.
: Multiprocessor tasks. Every job
is given with a set of machines
fixj\subseteq\{1,\ldots,m\}
, and needs simultaneously all these machines for execution. Sometimes also denoted by 'MPT'.
: Multipurpose machines. Every job
needs to be scheduled on one machine out of a given set
Mj\subseteq\{1,\ldots,m\}
. Sometimes also denoted by
Mj.
Objective functions
Usually the goal is to minimize some objective value. One difference is the notation
where the goal is to maximize the number of jobs that complete before their deadline. This is also called the
throughput. The objective value can be sum, possibly weighted by some given priority weights
per job.
- -: The absence of an objective value is denoted by a single dash. This means that the problem consists simply in producing a feasible scheduling, satisfying all given constraints.
: the
completion time of job
.
is the maximum completion time; also known as the
makespan. Sometimes we are interested in the
mean completion time (the average of
over all
j), which is sometimes denoted by mft (mean finish time).
[2]
: The
flow time of a job is the difference between its completion time and its release time, i.e.
.
:
Lateness. Every job
is given a due date
. The lateness of job
is defined as
. Sometimes
is used to denote feasibility for a problem with deadlines. Indeed using binary search, the complexity of the feasibility version is equivalent to the minimization of
.
:
Throughput. Every job is given a due date
. There is a unit profit for jobs that complete on time, i.e.
if
and
otherwise. Sometimes the meaning of
is inverted in the literature, which is equivalent when considering the decision version of the problem, but which makes a huge difference for approximations.
:
Tardiness. Every job
is given a due date
. The tardiness of job
is defined as
.
:
Earliness. Every job
is given a due date
. The earliness of job
is defined as
. This objective is important for
just-in-time scheduling.There are also variants with
multiple objectives, but they are much less studied.
[3] Examples
Here are some examples for problems defined using the above notation.[4]
– assigning each of
given jobs to one of the two identical machines so to minimize the maximum total processing time over the machines. This is an optimization version of the partition problem
– assigning to a single machine, processes with general precedence constraint, minimizing maximum lateness.
– assigning tasks to a variable number of unrelated parallel machines, allowing preemption, minimizing total completion time.
– a 3-machine job shop problem with unit processing times, where the goal is to minimize the maximum completion time.
– assigning jobs to
parallel identical machines, where each job comes with a number of machines on which it must be scheduled at the same time, minimizing maximum completion time. See
parallel task scheduling.
Other variants
- All variants surveyed above are deterministic in that all data is known to the planner. There are also stochastic variants, in which the data is not known in advance, or can perturb randomly.
- In a load balancing game, each job belongs to a strategic agent, who can decide where to schedule his job. The Nash equilibrium in this game may not be optimal. Aumann and Dombb[5] assess the inefficiency of equilibrium in several load-balancing games.
See also
External links
- Scheduling zoo (by Christoph Dürr, Sigrid Knust, Damien Prot, Óscar C. Vásquez): an online tool for searching an optimal scheduling problem using the notation.
- Complexity results for scheduling problems (by Peter Brucker, Sigrid Knust): a classification of optimal scheduling problems by what is known on their runtime complexity.
Notes and References
- B. Chen, C.N. Potts and G.J. Woeginger. "A review of machine scheduling: Complexity, algorithms and approximability". Handbook of Combinatorial Optimization (Volume 3) (Editors: D.-Z. Du and P. Pardalos), 1998, Kluwer Academic Publishers. 21-169. (HB) 0-7923-5019-7 (Set)
- Horowitz. Ellis. Sahni. Sartaj. 1976-04-01. Exact and Approximate Algorithms for Scheduling Nonidentical Processors. Journal of the ACM. 23. 2. 317–327. 10.1145/321941.321951. 18693114 . 0004-5411. free.
- Eugene L. Lawler, Jan Karel Lenstra, Alexander H. G. Rinnooy Kan, David B. Shmoys. 1993-01-01. Chapter 9 Sequencing and scheduling: Algorithms and complexity. Handbooks in Operations Research and Management Science. en. 4. 445–522. 10.1016/S0927-0507(05)80189-6. 9780444874726 . 0927-0507.
- Graham . R. L. . Lawler . E. L. . Lenstra . J.K. . Rinnooy Kan . A.H.G. . Optimization and Approximation in Deterministic Sequencing and Scheduling: a Survey . Proceedings of the Advanced Research Institute on Discrete Optimization and Systems Applications of the Systems Science Panel of NATO and of the Discrete Optimization Symposium . Elsevier . 1979 . (5) 287–326 .
- Aumann . Yonatan . Dombb . Yair . 2010 . Kontogiannis . Spyros . Koutsoupias . Elias . Spirakis . Paul G. . Pareto Efficiency and Approximate Pareto Efficiency in Routing and Load Balancing Games . Algorithmic Game Theory . Lecture Notes in Computer Science . en . Berlin, Heidelberg . Springer . 66–77 . 10.1007/978-3-642-16170-4_7 . 978-3-642-16170-4.