Level Crossing Removal Project Explained

Agency Name:Level Crossing Removal Project
Type:project
Picture Caption:Elevated rail near the rebuilt Preston station.
Formed:March 2015
Jurisdiction:Melbourne
Headquarters:Melbourne
Employees: 382
Minister1 Name:Danny Pearson
Minister1 Pfo:Minister for Transport and Infrastructure
Chief1 Name:Matt Thorpe[1]
Chief1 Position:Acting CEO
Agency Type:Project team
Logo Alt:The logo of the Level Crossing Removal Project, showing multiple small red circles and black text for the project name.
Image Alt:The newly elevated Reservoir railway station showing the project's elevated designs with a road in the foreground.
Parent Agency Type:authority
Parent Agency:Major Transport Infrastructure Authority
Parent Department:Department of Transport and Planning

The Level Crossing Removal Project (LXRP) is an infrastructure upgrade program by the Government of Victoria, Australia, to remove and grade-separate 110 level crossings and to rebuild 51 railway stations on the metropolitan and regional rail network of the state capital Melbourne. The project aims to improve network efficiency, rail safety, and reduce traffic congestion.

After pledging the removal of 50 level crossings at the 2014 Victorian state election, the Andrews Government committed $2.4 billion in the 2015–2016 budget to remove the first 20 crossings by 2018. The next 30 crossings were notionally funded through the hypothecation of the sale proceeds from the privatisation of the Port of Melbourne.[2] Prior to the 2018 state election, the government committed to remove a further 25 level crossings, using a new prioritisation framework. In 2021, the government announced a further ten level crossing removals and four level crossing closures would occur by 2025, bringing the total planned level crossing removals to 85 by 2025.[3] [4] In 2022, the Andrews government announced the removal of an additional 25 level crossings by 2030, bringing the total to 110.

Previously its own administrative agency, in 2019 the LXRP became a project within the Major Transport Infrastructure Authority, an office of the Victorian Department of Transport and Planning.[5] As of August 2024, 84 crossings have been removed and 48 train stations have been built or rebuilt as part of the project.[6]

Background

When Melbourne's rail network was built, many road-railway crossings were via level crossing rather than bridges or underpasses due to the city's flat topography and sparse population. As traffic levels increased, these became bottlenecks for road and rail traffic, limiting the speed and frequency of train services. In 1954, the State Government established a committee to look at the removal of level crossings at Clifton Hill, Elsternwick, Footscray, Moorabbin, and Newport.[7] [8] These projects were completed by 1960.[9]

In 1983, the level crossing at Station Street, Box Hill, was removed. Other level crossing removals include Dorset Road, Boronia, in 1998 and Middleborough Road, Laburnum, in 2007.[10] In the early 2010s, level crossings were removed at Nunawading (2010), Springvale (2014), Sunshine (2014) and Mitcham (2014).[11] [12] [13] As of 2014, there were 176 level crossings left on metropolitan Melbourne's rail network (5 of which were light rail level crossings) and 228 places where railways had been separated from roads;[14] by the end of the Level Crossing Removal Project (LXRP), 66 level crossings will remain.[15] Over two-thirds of these grade separations were constructed between 1863 and 1918, with fewer than one level crossing removal per year between 1918 and 2015. The commitment by the government to remove 110 level crossings over sixteen years, by 2030, represents the fastest rate of crossing removals in Melbourne's history.[16]

History

2014 election commitments

In June 2014, five months prior to the Victorian state election, VicRoads compiled a report of the most dangerous level crossings in Victoria and handed it to the Napthine Liberal-Nationals government.[17] In its 2014 state election manifesto, the then Labor opposition announced that, if elected, it would remove 50 level crossings by grade separation, with 20 to be removed by 2018. Although the majority of crossings announced by Opposition Leader Daniel Andrews were included in the priority list, ten of the crossings highlighted by VicRoads were not on the opposition's list.[18] The sites of all 50 level crossing removals were progressively announced over the following two years after the election of the Andrews government in November 2014.[19]

In September 2016, the Port of Melbourne lease concluded, providing $9.7 billion for infrastructure, including funding for the remaining 30 level crossing removals to be completed by mid-2022.[20]

2018 election commitments

In October 2018, the LXRP surpassed the State Government's 2014 election commitment of removing 20 level crossings by 2018, having officially removed 29 crossings.[21] In the lead up to the 2018 state election, Victorian Premier Daniel Andrews pledged to remove a further 25 level crossings across Melbourne at a cost of $6.6 billion by 2025. The locations of the additional removals were announced progressively over the course of 2018 through a new prioritisation framework based on safety, congestion, and proximity to emergency services.[22]

2021 additional commitments

In July 2021, the State Government announced the removal of an additional ten level crossings and four closures by the end of 2025 at a cost of $2.5 billion. These removals will include the reconstruction of five stations across the network, with stations to be rebuilt at Croydon, Keon Park, Narre Warren, Parkdale, and Ringwood East. At the conclusion of these additional 35 removals, the Pakenham, Cranbourne, and Lilydale lines will have no road level crossings for their entire length, with these announcements pushing the number of crossing removals to 85 by 2025.[23]

2022 election commitments

In the lead up to the 2022 state election, the Andrews government announced a further 25 level crossing removals, bringing the total number of removals to 110 by 2030. Many of these removals will be delivered together and include a number of closures. In September 2022, the premier announced eight crossings would be removed in Brunswick on the Upfield line.[24] [25] The eight crossings would be removed by 2027 and would include the rebuilding of Jewell, Brunswick, and Anstey stations. The government announced elevated rail would be built along the corridor from Royal Park to Moreland Road, meeting the elevated rail built as part of the 2022 level crossing removal works, and would include an upgrade of the Upfield Bike Path.[24]

In October 2022, the government committed to removing an extra four level crossings on the Ballarat line between Caroline Springs and Melton stations by 2028. Proposed removal methods for the level crossings at Exford Road and Coburns Road is by constructing a rail trench (since revised to a rail bridge) and lowering Melton station, while the roads will be elevated over tracks to get rid of the Hopkins Road and Ferris Road level crossings.[26] Seven more crossing removals and two closures were announced in October 2022 for the Frankston line.[27] These level crossings would be removed by 2029 and would make the line level crossing free for its entire length. Four stations will be rebuilt as part of the removals at Highett, Mordialloc, Aspendale and Seaford.[28]

On 21 and 25 October 2022, the Andrews government announced an additional two level crossing removals for the Sunbury line and one on the Hurstbridge line. These crossings are located at Old Calder Highway and Watsons Road, Diggers Rest, and Ruthven St, Macleod. These crossings will be removed by 2026 via the construction of a road bridge for the Sunbury line removals and a rail bridge for the Hurstbridge line. At the conclusion of these removals, the Sunbury line will be fully level crossing free.[29]

The government announced an additional three removals and two closures on the Werribee line on 27 October 2022.[30] [31] Along with the four already removed on the Werribee line, these removals would make the line level crossing free by 2030, and allow for additional services and the construction of the Geelong Fast Rail project. The crossings at Hudsons Road, Spotswood, Maddox Road, Newport, and Maidstone Street, Altona. These crossings will be removed with a combination of rail over and road over, and will include a newly elevated Spotswood station.[32] The crossings at Anderson Street, Yarraville, and Champion Road, Newport will be closed during the project. Pedestrian links will still remain with a plan to upgrade local roads to accommodate the closure of these crossings.

Governance

The Level Crossing Removal Authority (LXRA) was formed in May 2015 as an administrative office of the then-new Department of Economic Development, Jobs, Transport and Resources to deliver the project.[33] [34] [35]

Later, the LXRA led delivery of other rail projects, including extension of the South Morang line to Mernda, upgrades of the Hurstbridge and Cranbourne lines, as well as a rebuilt Frankston station. The authority also delivered a new stabling facility north of Wyndham Vale station and train storage at Kananook.[36] [37]

The LXRA was abolished as an independent administrative office following the 2018 state election, and its functions were absorbed into the newly formed Major Transport Infrastructure Authority at the Department of Transport.[38]

Architecture and urban design

The LXRP has used several different design approaches to removing level crossings, tailoring designs to different urban settings around Melbourne.[39] Most projects, particularly those in the denser inner- and middle-suburbs, have involved lowering the rail line into a trench or elevating the rail line above the road. Some projects in outer suburbs, such as Gap Road near Sunbury station or Station Street near Beaconsfield station, have involved lowering or raising the road without altering the existing rail corridor. This is enabled by the additional space surrounding the railway line.

As noted by University of Melbourne researchers in 2016, the scale of the project had significant urban renewal implications for the city:

Each crossing removal affects, on average, at least a kilometre of rail corridor and, within the urban area, this usually includes a station. In some instances, topography has required the removal of more than one crossing to meet rail engineering requirements as well as longer sections of corridor becoming part of the works. On the face of it, this means that the current seventy-five crossing removals could result in seventy-five kilometres of transformed rail corridors and fifty-seven new stations – more than a quarter of Melbourne’s total.
The researchers emphasised the urban benefits from new elevated rail over trenched rail, including the creation of new parkland and open space, arguing wider benefits could be achieved beyond reducing traffic congestion.[40] One study examined the local public health positive and negative impacts from the removal of level crossings on the Upfield line, including significant construction impacts.[41] The study found that by improving road connections the project could help induce more car usage, but that this could be offset by improving pedestrian and cycling connections.[42]

Awards

The LXRP has received numerous awards for their different projects in the categories of sustainability, architecture, and urban design. The Reservoir station project was presented the 'Special Prize Exterior' award in the Passenger Stations category at the World Architecture and Design Award at the 2021 Prix Versailles.[43] [44] The Toorak Road level crossing removal topped the infrastructure category of the Australian Institute of Landscape Architects awards due to the design of the new public parkland, cycling paths, and open space.[45] The elevated rail project from Moreland to Coburg stations saw landscape architects Tract win the Infrastructure Award of Excellence for their landscape and urban design work on the project, with the judging panel "particularly impressed with the urban renewal of the area".[46] The Bell to Moreland project was also awarded a score of 98 points from the Infrastructure Sustainability Council (ISC), the highest rating ever awarded in Australia.[47]

Elevated rail

Some of the most significant changes to Melbourne's urban structure from the LXRP have resulted from the construction of large sections of elevated rail, something that was relatively rare in Melbourne. In 2016, the government announced that of elevated rail would be built in Melbourne's south-eastern suburbs to remove nine level crossings on the Pakenham and Cranbourne rail corridor and build five new elevated stations at Carnegie, Murrumbeena, Hughesdale, Clayton and Noble Park.[48]

Dubbed "sky rail" by opponents and some media outlets, the LXRP spurred significant local opposition due to concerns over visual and noise impacts, and lack of consultation.[49] [50] The project became a political issue in the 2018 state election, although one opinion poll commissioned by The Age newspaper found 60% of Victorians supported the use of elevated rail to remove level crossings, and the government was returned at the election with an increased majority.[51] [52] Prior to the election, the government announced more sections of elevated rail on the Pakenham line.[53]

Some experts argued elevated rail offered a better urban outcome than trenched rail, providing opportunities for more open space, economic development, better local connections and less disruption from construction.[54] The Caulfield to Dandenong level crossing removals created a large new section of open parkland, dubbed a "linear park". This included 22.5ha of new open space, sports courts, playgrounds, new walking and cycling trails, and expanded station forecourts.[55] [56] As part of the project, the Djerring Trail was created, a 17km (11miles) shared-use path along the rail corridor. In the year after the elevated rail opened in 2018, the media reported that many residents, including some who were opposed to the project, were happy with the outcome and utilised the new open space.[57] [58]

Tree removal

The removal of mature trees for level crossing removal works has been a source of controversy with some local residents and project critics.[59] [60] Due to the nature of the LXRP, trees need to be cut down or relocated from the site to allow for construction works. This is a particular issue for projects where the rail line is lowered into a trench, such as the planned level crossing removals near Glen Huntly station, which have required significant mature tree removal along the planned 11NaN1 rail trench.[61] [62] An elevated rail design was chosen to remove the level crossings near Rosanna station in part to minimise the loss of native trees, as a proposed rail trench would have required the removal of hundreds of mature river red gum trees along the corridor.[63] [64]

According to a newspaper report, more than 10,000 trees have been cut down since 2014 to allow for the construction of Victorian infrastructure projects—including hundreds of trees for the LXRP. During the level crossing removal at Moreland Road, a campaign against the removal of 100 mature trees was unsuccessful, with a local councillor claiming only three or four trees remained at the conclusion of the project. In response, the government has stated more trees were planted than were there originally, as part of expanded parkland at the site. The state opposition has highlighted and campaigned on tree loss due to major infrastructure projects.

Railway heritage

The loss of heritage railways stations and the impact on heritage architecture has been a source of controversy and a key design consideration for the project. During the removal of a level crossing or rebuild of a railway station, heritage station buildings or existing railway infrastructure may be impacted. Some heritage buildings have been demolished, while others have been retained, moved or adapted for other uses, such as at Clayton and Mentone stations.[65] [66]

At the Warrigal Road level crossing removal, Kingston Council have called for heritage protection for the heritage Parkdale railway station buildings.[67] This request has been denied by the Department of Environment, Land, Water and Planning as well as Heritage Victoria on grounds that the structure is "not of state-level cultural heritage significance".[68] Nonetheless, in response to the local campaign to preserve the original heritage station building, the LXRP announced it would retain and repurpose the building within the precinct, although the extent of the retention is not clear.[69] [70]

Other crossing removals have had their heritage structures restored for reuse. At Moreland station, the original heritage station building that opened in 1884 was restored and turned into additional station facilities.[71] Heritage restorations are common across the removals, with other examples including the signals box at Gardiner railway station turning into bike parking, and the station building at North Williamstown railway station being restored into community and station facilities.[72] [73]

Crossing closures

The use of road closures to remove level crossings has been a source of controversy. The government has used crossing closures in select cases where there are nearby crossing removal projects or existing grade-separated major roads. For example, the crossings at Anderson Street, Yarraville, and Champion Road, Newport will be closed at the same time as the rail line will be elevated above Hudsons Road in nearby Spotswood and at Maddox Road in Newport with new grade-separated pedestrian and cycling crossings also built. According to the government, this solution is required is due to the constrained site, significant heritage impacts that would arise from grade separation, and the relatively low level of car traffic on the roads. Some local residents, however, have objected to the road closures, arguing there would be significant impacts to local car journeys.[74] Similar objections were raised during the 2022 state election by the state opposition over the closure of Latrobe Street in Cheltenham, which similarly is located close to two other grade separated crossings completed in 2020.

New and amalgamated stations

Due to a large portion of level crossings also having adjacently located stations, many stations have been rebuilt as part of the project. Rebuilt stations have subsequently delivered improve facilities for passengers, including new toilet facilities, drinking fountains, increased levels of accessibility, better integration with surrounding transport connections, and higher quality architectural designs, amongst other benefits.[75]

Whilst the majority of stations demolished as part of the project have been rebuilt and reopened, a few projects have resulted in the amalgamation of stations. Whilst controversial, these instances have usually only occurred due to the close proximity between existing stations, reducing the negative impact on users. Amalgamated stations have allowed for improved station locations, faster journey times, and higher quality facilities.[76] One amalgamation has included Mont Albert and Surrey Hills stations on the Belgrave and Lilydale lines. In 2023, these two stations were closed and amalgamated into the new Union station located in-between the two former locations as part of the removals of Mont Albert and Union roads project.[77] This amalgamation has received criticism, with opponents highlighting how the increased distances from the two shopping centres on Union Road and Hamilton Street will negatively impact local mobility.[78] Despite communicty critism, this project was completed in 2023 with the removal of two level crossings and the opening of the new Union station.

Reception

Political

The LXRP has generally been seen as a political success for the Andrews government. Journalist Benita Kolovos argued it was the quick rollout of the program and the visible, tangible benefits it delivered to communities that drove its electoral success.[79] She wrote: "It was promised at the 2014 election, construction began in the first year of the Andrews government’s term and several were completed before the 2018 election. Commuters benefited from more trains, drivers from less traffic." The government's messaging on the project has focused on these localised benefits, public safety, and the prevalence of level crossings within Melbourne. Minister for Transport Infrastructure Jacinta Allan said in 2021: "Every Victorian knows the dinging sound of boom gates coming down and the frustration that comes with it, that’s why we’re getting rid of them – saving lives, easing congestion and getting you home sooner."[80]

But controversy over design choices and the cost of the project has also prompted opposition. Liberal MP Brad Rowswell criticised the Andrews government for a lack of community consultation and local feedback on the project and claimed that the government was out of touch with the community.[81] Shadow Minister for Transport Infrastructure David Davis criticised the project for its cost, arguing that “without a comprehensive business case, there is simply no proper economic justification for the Level Crossing Removal Program".[82] The ongoing disruption of roadworks for the project was also an issue in some suburbs.[83]

Media

The Guardian Australia has called the program "transformational" and "suburb moulding" in comments about the Andrews government's infrastructure projects.[84] Other local newspapers, such as The Age and Herald Sun, have been critical of the project and have highlighted local opposition in their reporting.[85] [86] [87] [88]

Experts and lobby groups

The Public Transport Users Association has campaigned for level-crossing removals, and has welcome the LXRP and its benefits to the public transport system, with spokesman Daniel Bowen highlighting how the projects "bring a lot of pluses to the wider community, and [how] it’s good to finally see progress on them."[89] [90] The Royal Automobile Club of Victoria have also campaigned for level crossing removals, and have welcomed announcements of crossing removals.[91]

Academics Ian Woodcock and John Stone have highlighted the benefits from the LXRP, including its urban design opportunities and how it has contributed to the revitalisation of public transportation in Melbourne.[92] Other academics such as Monash University researcher Graham Currie have been critical of the project, arguing the travel time savings resulting from the project were low and did not justify the cost.

Auditor-General

A report released in December 2017 by the Victorian Auditor-General's Office in the LXRP's original fifty level crossing removals found that the speed and cost of the project carried significant risks.[93] The report criticised the Level Crossing Removal Authority for its haste in delivering the program, and found that the rapid pace of the project had contributed to a failure to properly assess the merits of each grade separation. In 2017, the project's cost was found to have increased to $8.3 billion, the project is more than 38% more expensive than its initial $5–6 billion estimated price tag.

The Auditor-General criticised the selection of crossings, stating that the value of the project was compromised by the apparent political motivation for some crossing removals at the expense of more dangerous or congested intersections.[94] In their report, the Auditor-General found that only 32 of the crossings chosen in the original 50 removals were featured in the top 50 of a 2008 list by the Department of Transport of the state's most dangerous level crossings. 28 of these were prioritised on a 2013 VicRoads removal list which was handed to the Napthine government.

Since these findings, the LXRP has developed and applied a transparent process to select sites for the additional level crossing removals. In a follow-up 2020 report, the Auditor-General stated the new process has improved the project’s cost-effectiveness because it uses delivery efficiency as one of the criteria for site selection.[95] The Auditor-General noted the Department and the Major Transport Infrastructure Authority had fully addressed seven of its recommendations, partially addressed one and was working to address two more, but warned that the project had not completed a business case for its second batch of crossing removals so the economic benefits were unclear.

Public

While the LXRP has been broadly popular, local opposition has attracted significant media attention. Elevated rail has been controversial among some local residents and businesses, with protests over the removal of crossings on the Upfield line calling for a rail trench to be used instead.[96] [97] At the same time, polling has found a majority of Victorians supported the use of elevated rail to remove level crossings. In other examples, such as the Caulfield to Dandenong elevated rail project, local media reported that many residents were supportive of the project's outcomes.

List of crossing removals

Original 50 crossing removals: 2014–2022

Prior to the 2014 state election, the then Labor opposition announced a plan to remove 50 level crossings by 2022, including 20 by 2018.[98] Park Road, Cheltenham, Mascot Avenue, Bonbeach, and Lochiel Avenue, Edithvale were added to the original 50 level crossing removals after further community consultations.[99] [100] [101] This pushed the number of level crossing removals to 53. These removals were completed on the Glen Waverley, Frankston, Sunbury, Belgrave, Lilydale, Upfield, Pakenham, Cranbourne, Werribee, Craigieburn, and Mernda lines by May 2022.[102]

Line(s)RoadNearest stationSolutionDate of completion
Glen WaverleyBurke RoadGardinerRail under[103]
Centre RoadBentleighRail under[104]
FrankstonMcKinnon RoadMcKinnonRail under[105]
FrankstonNorth RoadOrmondRail under[106]
SunburyFurlong RoadGiniferRail under[107]
SunburyMain RoadSt AlbansRail under[108]
Mountain HighwayBayswaterHybrid[109]
Scoresby RoadBayswaterRail under[110]
Belgrave, LilydaleBlackburn RoadBlackburnRail under[111]
Belgrave, LilydaleHeatherdale RoadHeatherdaleRail under[112]
UpfieldCamp RoadGowrieRail under[113]
SunburyMelton HighwayWatergardensRoad over[114]
Cranbourne, PakenhamChandler RoadNoble ParkRail over[115]
Cranbourne, PakenhamCorrigan RoadNoble ParkRail over[116]
Cranbourne, PakenhamHeatherton RoadNoble ParkRail over[117]
Cranbourne, PakenhamCentre RoadClaytonRail over[118]
Cranbourne, PakenhamClayton RoadClaytonRail over[119]
HurstbridgeGrange RoadAlphingtonRail under[120]
HurstbridgeLower Plenty RoadRosannaRail over[121]
Cranbourne, PakenhamGrange RoadCarnegieRail over[122]
Cranbourne, PakenhamKoornang RoadCarnegieRail over[123]
Cranbourne, PakenhamMurrumbeena RoadMurrumbeenaRail over[124]
Cranbourne, PakenhamPoath RoadHughesdaleRail over[125]
FrankstonSkye/Overton RoadKananookRail over[126]
CranbourneThompsons RoadMerinda ParkRoad over[127]
WerribeeKororoit Creek RoadSeaholmeRail over[128]
CranbourneAbbotts RoadDandenongRail over[129]
Buckley StreetEssendonRoad under[130]
FrankstonSeaford RoadSeafordHybrid[131]
WerribeeAviation RoadAircraftRoad over[132]
MerndaHigh StreetReservoirRail over[133]
FrankstonEel Race RoadCarrumClosed off[134]
FrankstonMascot AvenueBonbeachClosed off[135]
FrankstonStation StreetCarrumRail over[136]
Glen WaverleyToorak RoadToorongaRail over[137]
FrankstonBalcombe RoadMentoneRail under[138]
FrankstonCharman RoadCheltenhamRail under[139]
FrankstonPark RoadCheltenhamRail under
UpfieldBell StreetCoburgRail over[140]
UpfieldMoreland RoadMorelandRail over[141]
WerribeeWerribee StreetWerribeeRail over[142]
WerribeeCherry StreetWerribeeRoad over[143]
PakenhamSouth Gippsland HighwayDandenongRoad over[144]
FrankstonBondi RoadBonbeachRail under[145]
FrankstonEdithvale RoadEdithvaleRail under[146]
FrankstonLochiel AvenueEdithvaleClosed off[147]
LilydaleManchester RoadMooroolbarkRail over[148]
LilydaleMaroondah HighwayLilydaleRail over[149]
WilliamstownFerguson StreetNorth WilliamstownRail under[150]
PakenhamClyde RoadBerwickRoad under[151]
PakenhamHallam RoadHallamRail over[152]
MerndaBell StreetBellRail over[153]
Glenroy RoadGlenroyRail under[154]

Additional 25 crossing removals: 2022–2025

During the lead up to the 2018 state election, an extra 25 level crossing removals were announced. These removals will occur on the Cranbourne, Pakenham, Upfield, Frankston, Mernda, Ballarat, Geelong, Sunbury, Belgrave, Lilydale and Barinsdale lines. This announcement will result in the Cranbourne line being fully level crossing free, with these announcements pushing the number of level crossing removals to 75 by 2025.

Line(s)RoadNearest stationPreferred solution StatusDate of Completion
CranbourneEvans RoadMerinda ParkRoad overCompleted[155]
UpfieldMunro StreetCoburgRail overCompleted[156]
UpfieldReynard StreetCoburgRail overCompleted[157]
PakenhamCardinia RoadCardinia RoadRoad overCompleted[158]
FrankstonArgyle AvenueChelseaRail underCompleted[159]
FrankstonChelsea RoadChelseaClosed offCompleted[160]
FrankstonSwanpool AvenueChelseaClosed offCompleted[161]
WerribeeOld Geelong RoadHoppers CrossingRoad overCompleted[162]
CranbourneGreens RoadDandenongRail overCompleted[163]
MerndaCramer StreetPrestonRail overCompleted[164]
MerndaMurray RoadPrestonRail overCompleted[165]
MerndaOakover RoadBellRail overCompleted[166]
Ballarat, GeelongFitzgerald RoadArdeerRoad overCompleted[167]
Ballarat, GeelongRobinsons RoadDeer ParkRoad underCompleted[168]
SunburyGap RoadSunburyRoad underCompleted[169]
Ballarat, GeelongMt Derrimut RoadDeer ParkRail overCompletedApril [170]
Belgrave, LilydaleUnion RoadSurrey HillsRail underCompletedMay [171]
Belgrave, LilydaleMont Albert RoadMont AlbertRail underCompletedMay [172]
FrankstonNeerim RoadGlen HuntlyRail underCompletedJune [173]
FrankstonGlen Huntly RoadGlen HuntlyRail underCompletedJuly [174]
CranbourneCamms RoadCranbourneRoad overCompletedNovember [175]
PakenhamMain StreetPakenhamRail overCompletedJune [176]
PakenhamMcGregor RoadPakenhamRail overCompletedJune [177]
GippslandRacecourse RoadPakenhamRail overCompletedJune [178]
Cranbourne, PakenhamWebster StreetDandenongClosed offPlanning[179]

Additional 10 crossing removals: 2023–2025

Boosting the number of removals, the Andrews Labor government announced in July 2021 an extra 10 level crossing removals and 4 closures. These removals will occur on the Pakenham, Frankston, Mernda, Sunbury, Belgrave and Lilydale lines. At the conclusion of these removals, the Pakenham and Lilydale lines will join the Cranbourne line in having no road level crossings for their entire length, with these announcements pushing the number of crossing removals to 85 by 2025.

Line(s)RoadNearest stationPreferred solutionStatusDate of Completion
PakenhamWebb StreetNarre WarrenRail overCompletedDecember [180]
LilydaleCave Hill RoadLilydaleClosed offCompletedJanuary [181]
BelgraveBedford RoadRingwoodRail underCompletedMarch [182]
PakenhamBrunt RoadBeaconsfieldRoad overCompletedApril [183]
MerndaKeon ParadeKeon ParkRail overCompletedMay [184]
PakenhamStation StreetOfficerClosed offCompletedMay [185]
LilydaleDublin RoadRingwood EastRail underCompletedJune [186]
LilydaleCoolstore RoadCroydonRail overCompletedJuly [187]
FrankstonWarrigal RoadParkdaleRail overCompletedAugust [188]
FrankstonParkers RoadParkdaleRail overCompletedAugust [189]
SunburyCalder Park DriveWatergardensRoad overUnder construction[190]
PakenhamProgress StreetDandenongClosed offUnder construction[191] [192]
PakenhamStation StreetBeaconsfieldRoad overUnder construction[193]
SunburyHolden RoadWatergardensClosed offPlanning[194]

Additional 25 crossing removals: 2025–2030

Prior to the 2022 state election, the State Government announced an extra 25 level crossing removals by 2030. These removals will occur on the Upfield, Ballarat, Sunbury, Hurstbridge, Frankston and Werribee/Williamstown lines. At the conclusion of these removals, the Frankston, Sunbury, and Werribee lines will have no road level crossings for their entire length, joining the Cranbourne, Pakenham and Lilydale lines, once projects on those lines are complete.[195] These series of announcements have pushed the number of crossing removals to 110.[24] [196] [197]

Line(s)RoadNearest stationPreferred solution StatusDate of Completion
SunburyOld Calder HighwayDiggers RestRoad overUnder construction2025[198] [199]
SunburyWatsons RoadDiggers RestRoad overUnder construction2025
FrankstonBear StreetMordiallocClosed offPlanning2026[200]
WerribeeChampion Road NewportClosed offPlanning2026[201]
BallaratCoburns RoadMeltonRail overPlanning2026[202]
BallaratExford RoadMeltonRail overPlanning2026
BallaratFerris RoadCobblebankRoad overPlanning2026
BallaratHopkins RoadCaroline SpringsRoad overPlanning2026
WerribeeMaddox Road NewportRail overPlanning2026
FrankstonMcDonald Street MordiallocRail overPlanning2026
FrankstonStation Street MordiallocRail overPlanning2026
WerribeeMaidstone Street LavertonRoad overPlanning2027[203]
HurstbridgeRuthven StreetMacleodRail overEarly planning2027[204]
Werribee, WilliamstownHudsons Road SpotswoodRail overEarly planning2028[205]
FrankstonArmstrongs Road SeafordRail overEarly planning2029[206]
FrankstonGroves Street AspendaleRail underEarly planning2029[207]
FrankstonHighett Road HighettRail overEarly planning2029
FrankstonLatrobe StreetMentoneClosed offEarly planning2029
FrankstonStation StreetSeafordRail overEarly planning2029
FrankstonWickham Road HighettRail overEarly planning2029
UpfieldAlbert StreetBrunswickRail overEarly planning2030[208]
UpfieldAlbion StreetAnsteyRail overEarly planning2030
Werribee, WilliamstownAnderson Street YarravilleClosed offEarly planning2030
UpfieldBrunswick RoadJewellRail overEarly planning2030
UpfieldDawson StreetJewellRail overEarly planning2030
UpfieldHope StreetAnsteyRail overEarly planning2030
UpfieldUnion StreetJewellRail overEarly planning2030
UpfieldVictoria StreetBrunswickRail overEarly planning2030
UpfieldPark StreetJewellRail overEarly planning2030

New and rebuilt stations

There will be 51 railway stations rebuilt as part of the LXRP. Four stations are being added to the metropolitan network as part of suburban rail extensions delivered by the LXRP. Three of these stations, Hawkstowe, Middle Gorge and Mernda were added as part of the Mernda rail extension, which extended the former South Morang line 8km (05miles) north to Mernda. The extension, announced by Labor at the 2014 state election, opened in 2018.[209] [210] As part of the level crossing removals along the Pakenham line, a new station was added at East Pakenham along with a short rail extension.[211] The LXRP also delivered a new infill station at Southland on the Frankston line.[212] In one case, the nearby Mont Albert and Surrey Hills railway stations on the Belgrave and Lilydale lines were merged and replaced with a brand new Union station located between them.[213] [214]

Line(s)StationImageStatusdata-sort-type="date" Completion date
Glen WaverleyGardinerOpenJanuary 2016[215]
FrankstonMcKinnonOpenAugust 2016[216]
FrankstonBentleighOpenAugust 2016[217]
FrankstonOrmondOpenAugust 2016[218]
SunburyGiniferOpenNovember 2016[219]
SunburySt AlbansOpenNovember 2016[220]
BelgraveBayswaterOpenDecember 2016[221]
Belgrave, LilydaleHeatherdaleOpenFebruary 2017[222]
FrankstonSouthland (new)OpenNovember 2017[223]
Cranbourne, PakenhamNoble ParkOpenFebruary 2018[224]
Cranbourne, PakenhamClaytonOpenApril 2018[225]
HurstbridgeRosannaOpenMay 2018[226]
Cranbourne, PakenhamCarnegieOpenJune 2018[227]
Frankston, Stony PointFrankstonOpenJune 2018[228]
Cranbourne, PakenhamMurrumbeenaOpenJune 2018[229]
Cranbourne, PakenhamHughesdaleOpenAugust 2018[230]
MerndaHawkstowe (new)OpenAugust 2018[231]
MerndaMernda (new)OpenAugust 2018
MerndaMiddle Gorge (new)OpenAugust 2018
MerndaReservoirOpenDecember 2019[232]
FrankstonCarrumOpenFebruary 2020[233]
FrankstonMentoneOpenJuly 2020[234]
FrankstonCheltenhamOpenAugust 2020[235]
UpfieldCoburgOpenDecember 2020[236]
UpfieldMorelandOpenDecember 2020[237]
LilydaleLilydaleOpenNovember 2021[238]
LilydaleMooroolbarkOpenNovember 2021[239]
FrankstonBonbeachOpenNovember 2021[240]
FrankstonChelseaOpenNovember 2021[241]
FrankstonEdithvaleOpenNovember 2021[242]
WilliamstownNorth WilliamstownOpenDecember 2021[243]
CranbourneMerinda ParkOpenFebruary 2022[244]
PakenhamHallamOpenMay 2022[245]
CraigieburnGlenroyOpenMay 2022[246]
MerndaBellOpenSeptember 2022[247]
MerndaPrestonOpenSeptember 2022
Ballarat, GeelongDeer ParkOpenApril 2023[248]
HurstbridgeGreensboroughOpenApril 2023[249]
HurstbridgeMontmorencyOpenApril 2023[250]
Belgrave, LilydaleUnion (new)OpenMay 2023[251]
FrankstonGlen HuntlyOpenJuly 2023[252]
PakenhamNarre WarrenOpenMarch 2024
PakenhamEast Pakenham (new)OpenJune 2024
PakenhamPakenhamOpenJune 2024
MerndaKeon ParkOpenJune 2024
LilydaleRingwood EastOpenJuly 2024
FrankstonParkdaleOpenAugust 2024
LilydaleCroydonOpenAugust 2024
BallaratMeltonPlanning2026
FrankstonMordiallocPlanning2026
Werribee, WilliamstownSpotswoodEarly planning2028
FrankstonAspendaleEarly planning2029
FrankstonHighettEarly planning2029
FrankstonSeafordEarly planning2029
UpfieldAnsteyEarly planning2030
UpfieldBrunswickEarly planning2030
UpfieldJewellEarly planning2030

See also

External links

Notes and References

  1. Web site: Melbourne residents angry over new train station metres from their balconies .
  2. Web site: About – Level Crossing Removal Project. Level Crossing Removal Authority. 7 January 2017. 12 December 2016. https://web.archive.org/web/20161212014205/http://levelcrossings.vic.gov.au/about. live.
  3. Web site: Ten More Level Crossings To Go By 2025 Premier of Victoria. 9 August 2021. www.premier.vic.gov.au. en. 29 July 2021. https://web.archive.org/web/20210729004027/https://www.premier.vic.gov.au/ten-more-level-crossings-go-2025. live.
  4. Web site: Fowler. Michael. 29 July 2021. Big Build swells: Andrews adds $2.5b, five new stations and 10 level crossing removals. 9 August 2021. The Age. en. 9 August 2021. https://web.archive.org/web/20210809033317/https://www.theage.com.au/politics/victoria/big-build-swells-andrews-adds-2-5b-five-new-stations-and-10-level-crossing-removals-20210729-p58e3b.html. live.
  5. Web site: Department of Transport. September 2019. Annual Report 2018-19. 9 November 2021. 9 November 2021. https://web.archive.org/web/20211109042413/https://transport.vic.gov.au/-/media/tfv-documents/dot-annual-report-1819.pdf?la=en&hash=B21A6EF6EF7406A3A9FA3F0699283FFD. live.
  6. Web site: 26 October 2022 . Level Crossing Removal Project . 6 December 2022 . Victoria’s Big Build . en . 21 September 2022 . https://web.archive.org/web/20220921194737/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project . live .
  7. "Abolition of Busy Level Crossings" Railway Gazette 13 August 1954 page 176
  8. "Abolishing Level Crossings in Victoria" Railway Gazette 30 December 1955 pages 769–771
  9. "Abolition of Level Crossings in Victoria" Railway Gazette 4 November 1960 pages 539–540
  10. Web site: 7 July 2013 . DVN61: Crossing The Line: Boronia's forgotten killer intersection . 6 December 2022 . DVN61 . 6 December 2022 . https://web.archive.org/web/20221206115700/https://dvn61.blogspot.com/2013/07/crossing-line-boronias-forgotten-killer.html . live .
  11. "Infrastructure" Railway Gazette International July 2009 page 14
  12. http://www.arup.com/projects/springvale_road_rail_grade_separation Springvale road and rail grade separation
  13. Web site: 2014 . Anderson rd level crossing in sunshine finally removed . 6 December 2022 . 6 December 2022 . https://web.archive.org/web/20221206121618/https://www.heraldsun.com.au/leader/west/anderson-rd-level-crossing-in-sunshine-finally-removed/news-story/14cccb860b04cf71f8998d9fc61fdbd6 . live .
  14. Web site: 2024-03-16 . Level crossings: Which are funded to be removed, which are promised? – Daniel Bowen . 2024-04-29 . https://web.archive.org/web/20240316085125/https://danielbowen.com/2014/09/24/level-crossing-list/ . 16 March 2024 .
  15. Web site: Melbourne Level Crossing Map . 2024-04-29 . Google My Maps.
  16. Woodcock . Ian . Stone . John . 2016 . The Benefits of Level Crossing Removal: lessons from Melbourne's historical experience . University of Melbourne/RMIT University . 13 . RMIT Researchbank . 6 December 2022 . 6 December 2022 . https://web.archive.org/web/20221206120308/https://researchrepository.rmit.edu.au/esploro/outputs/9921860675101341 . live .
  17. Web site: Strategic framework for the prioritisation of level crossings in metropolitan Melbourne . Parliament of Victoria . 12 September 2022 . https://web.archive.org/web/20170313075632/http://www.parliament.vic.gov.au/images/stories/committees/pomsc/Other_Docs/VicRoads_Report_05102015.pdf . 13 March 2017.
  18. Web site: Level crossings: VicRoads list of Melbourne's worst overlooked by Labor. Carey. Adam. 26 October 2015. The Age. 7 January 2017. 23 May 2017. https://web.archive.org/web/20170523011252/http://www.theage.com.au/victoria/level-crossings-vicroads-list-of-melbournes-worst-overlooked-by-labor-20151023-gkh3s1.html. live.
  19. Web site: Moorabbin Kingston Leader . 6 September 2016 . Level Crossing Removal Authority releases plans for Frankston line . 22 November 2022 . 2 January 2017 . https://web.archive.org/web/20170102150729/http://www.heraldsun.com.au/leader/inner-south/level-crossing-removal-authority-releases-plans-for-frankston-line/news-story/21d8af26190121d9c8343bedf66fb038 . live .
  20. http://www.premier.vic.gov.au/promise-delivered-port-of-melbourne-leased-to-remove-level-crossings-and-create-thousands-of-jobs/ Promise Delivered: Port Of Melbourne Leased To Remove Level Crossings And Create Thousands Of Jobs
  21. Web site: Another 25 rail level crossings to go under Labor pledge. Towell. Craig Butt, Noel. 21 October 2018. The Age. en. 28 October 2018. 22 October 2018. https://web.archive.org/web/20181022153453/https://www.theage.com.au/politics/victoria/25-more-rail-level-crossings-to-go-under-labor-pledge-20181021-p50b07.html. live.
  22. News: Andrews pledges 25 new level crossing removals in Melbourne. 21 October 2018. ABC News. 28 October 2018. en-AU. 31 October 2018. https://web.archive.org/web/20181031035950/https://www.abc.net.au/news/2018-10-21/new-melbourne-level-crossing-removals-to-include-sky-rail/10401896. live.
  23. Web site: 10 more level crossings to go by 2025 . 30 July 2021 . levelcrossings.vic.gov.au . 29 July 2021 . 30 July 2021 . https://web.archive.org/web/20210730004647/https://levelcrossings.vic.gov.au/media/news/10-more-level-crossings-to-go-by-2025 . live .
  24. Web site: Eight More Dangerous Level Crossings To Go By 2027 Premier of Victoria . 19 September 2022 . www.premier.vic.gov.au . en . 19 September 2022 . https://web.archive.org/web/20220919000058/https://www.premier.vic.gov.au/eight-more-dangerous-level-crossings-go-2027 . live .
  25. Web site: Eddie . Rachael Dexter, Rachel . 19 September 2022 . Eight level crossings to be removed in Melbourne's north . 19 September 2022 . The Age . en . 19 September 2022 . https://web.archive.org/web/20220919085427/https://www.theage.com.au/politics/victoria/eight-level-crossings-to-be-removed-in-melbourne-s-north-20220919-p5bj6c.html . live .
  26. Web site: 6 October 2022 . Making Melton level crossing-free . live . https://web.archive.org/web/20221006013408/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/making-melton-level-crossing-free . 6 October 2022 . 6 October 2022 . Victoria’s Big Build . en.
  27. News: 9 October 2022 . Victorian opposition pledges to cap public transport fares at $2 a day . en-AU . ABC News . 27 October 2022 . 9 October 2022 . https://web.archive.org/web/20221009231822/https://www.abc.net.au/news/2022-10-09/victorian-election-promises-2-dollar-public-transport/101516028 . live .
  28. Web site: Tribune . The National . 8 October 2022 . Making Frankston Line Level Crossing Free . live . https://web.archive.org/web/20221009012550/https://www.nationaltribune.com.au/making-frankston-line-level-crossing-free/?tt=1665272712 . 9 October 2022 . 9 October 2022 . The National Tribune . en-AU.
  29. Web site: 21 October 2022 . Making the Sunbury Line level crossing-free . 21 October 2022 . Victoria’s Big Build . en . 21 October 2022 . https://web.archive.org/web/20221021122353/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/making-the-sunbury-line-level-crossing-free . live .
  30. Web site: Chan . Ray . 26 October 2022 . All Werribee Line crossings set for removal . 27 October 2022 . Rail Express . en-AU . 27 October 2022 . https://web.archive.org/web/20221027233004/https://www.railexpress.com.au/all-werribee-line-crossings-set-for-removal/ . live .
  31. Web site: 26 October 2022 . Werribee Line level crossing removals . 27 October 2022 . Victoria’s Big Build . en . 27 October 2022 . https://web.archive.org/web/20221027233002/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/werribee . live .
  32. Web site: Making The Werribee Line Level Crossing Free Premier of Victoria . 26 October 2022 . www.premier.vic.gov.au . en . 25 October 2022 . https://web.archive.org/web/20221025232033/https://www.premier.vic.gov.au/making-werribee-line-level-crossing-free . live .
  33. Web site: Victoria Government Gazette – No. G 18 Thursday 7 May 2015. Victoria Government Gazette. 7 May 2015. 7 January 2017. 74. 23 October 2015. https://web.archive.org/web/20151023071726/http://www.gazette.vic.gov.au/gazette/Gazettes2015/GG2015G018.pdf. live.
  34. Web site: Melbourne level crossing removal plan to be fast-tracked, Government says. 15 February 2015. ABC News. 7 January 2017. 3 May 2017. https://web.archive.org/web/20170503083954/http://www.abc.net.au/news/2015-02-15/removal-of-50-level-crossings-to-be-fast-tracked-through-/6106696. live.
  35. Web site: About the authority. Level Crossing Removal Authority. 7 January 2017 . https://web.archive.org/web/20161227173054/http://levelcrossings.vic.gov.au/about/about-the-authority . 27 December 2016.
  36. Web site: Wyndham Vale Train Stabling – Mcconnell Dowell . 12 December 2022 . www.mcconnelldowell.com . 12 December 2022 . https://web.archive.org/web/20221212110834/https://www.mcconnelldowell.com/projects/wyndham-vale-train-stabling . live .
  37. Web site: Bayside News . 18 May 2020 . Train stabling facility finished . 12 December 2022 . Bayside News . en-AU . 12 December 2022 . https://web.archive.org/web/20221212110834/https://baysidenews.com.au/2020/05/18/train-stabling-facility-finished/ . live .
  38. Web site: 28 April 2021 . About the Major Transport Infrastructure Authority . 31 October 2022 . Victoria’s Big Build . en . 31 October 2022 . https://web.archive.org/web/20221031060240/https://bigbuild.vic.gov.au/about/mtia . live .
  39. Web site: Woodcock . Ian . Jan 2020 . On track: Level Crossing Removal Project . 20 September 2022 . Architecture Australia . en . 22 December 2022 . https://web.archive.org/web/20221222223923/https://architectureau.com/articles/level-crossing-removal-project/ . live .
  40. Web site: Rothenbury . Camryn . 10 April 2018 . Level-crossing removals: learning from Melbourne's experience . 20 September 2022 . Melbourne School of Design . en . 20 September 2022 . https://web.archive.org/web/20220920173051/https://msd.unimelb.edu.au/research/projects/completed/level-crossing-removals-learning-from-melbournes-experience . live .
  41. Web site: Browne . Geoffrey . Lowe . Melanie . Level-crossing removals: a case study in why major projects must also be investments in health . 20 September 2022 . The Conversation . 22 January 2021 . en . 22 September 2022 . https://web.archive.org/web/20220922091757/https://theconversation.com/level-crossing-removals-a-case-study-in-why-major-projects-must-also-be-investments-in-health-149820 . live .
  42. Browne . Geoffrey R. . Lowe . Melanie . 1 March 2021 . Liveability as determinant of health: Testing a new approach for health impact assessment of major infrastructure . Environmental Impact Assessment Review . en . 87 . 106546 . 10.1016/j.eiar.2020.106546 . 2021EIARv..8706546B . 233784494 . 0195-9255.
  43. Web site: 2021 Passenger Stations . Prix Versailles . 13 December 2022 . 13 December 2022 . https://web.archive.org/web/20221213165508/https://www.prix-versailles.com/2021-passenger-stations . live .
  44. Web site: 31 December 2021 . Fantastique Reservoir – world architecture and rail sustainability winner . 31 October 2022 . Victoria’s Big Build . en . 31 October 2022 . https://web.archive.org/web/20221031110438/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/fantastique-reservoir-world-architecture-and-design-award . live .
  45. Web site: 19 July 2022 . Level crossings top landscape architecture awards . 31 October 2022 . Victoria’s Big Build . en . 30 October 2022 . https://web.archive.org/web/20221030111350/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/level-crossings-top-landscape-architecture-awards . live .
  46. Web site: 11 July 2022 . 2022 AILA Landscape Architecture Award Winners Ace Contractors Group Pty Ltd . 31 October 2022 . en-AU . 31 October 2022 . https://web.archive.org/web/20221031110430/https://www.acecon.com.au/2022-aila-landscape-architecture-award-winners/ . live .
  47. Web site: Chan . Ray . 13 June 2022 . Sustainability award for Bell-Moreland level crossing removal project . 31 October 2022 . Rail Express . en-AU . 31 October 2022 . https://web.archive.org/web/20221031110430/https://www.railexpress.com.au/sustainability-award-for-bell-moreland-level-crossing-removal-project/ . live .
  48. Web site: Carey . Adam . 8 February 2016 . Melbourne sky rail: Many questions remain about Andrews government plan . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920172354/https://www.theage.com.au/national/victoria/melbourne-sky-rail-many-questions-remain-about-andrews-government-plan-20160208-gmo67k.html . live .
  49. Web site: Woodcock . Ian . Stone . John . The 'sky rail' saga: can big new transport projects ever run smoothly? . 20 September 2022 . The Conversation . 22 February 2016 . en . 21 September 2022 . https://web.archive.org/web/20220921231511/https://theconversation.com/the-sky-rail-saga-can-big-new-transport-projects-ever-run-smoothly-54383 . live .
  50. Web site: Willingham . Richard . 16 February 2016 . Sky rail: Premier Andrews stands by consultation process in face of anger . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920173148/https://www.theage.com.au/national/victoria/skyrail-premier-andrews-stands-by-consultation-process-in-face-of-anger-20160216-gmv6ou.html . live .
  51. Web site: Willingham . Richard . 4 September 2016 . Sky rail gets strong backing from voters . 20 September 2022 . The Courier . en-AU . 4 December 2016 . https://web.archive.org/web/20161204084509/http://www.theage.com.au/victoria/sky-rail-gets-strong-backing-from-voters-20160904-gr89nx.html . live .
  52. Web site: Szego . Julie . 10 February 2016 . Sky rail more an eye opener than an eyesore . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920172255/https://www.theage.com.au/opinion/less-an-eyesore-than-an-eye-opener-sky-rail-would-open-more-melbourne-to-the-world-20160210-gmq1mi.html . live .
  53. Web site: Preiss . Benjamin . 1 November 2018 . Andrews targets key marginal with latest sky rail announcement . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920172931/https://www.theage.com.au/politics/victoria/andrews-targets-key-marginal-with-latest-sky-rail-announcement-20181101-p50dbv.html . live .
  54. Web site: Rail lines over roads can help with more than just traffic jams . 20 September 2022 . ArchitectureAU . en . 2 December 2021 . https://web.archive.org/web/20211202215709/https://architectureau.com/articles/rail-lines-over-roads-can-help-with-more-than-just-traffic-jams/ . live .
  55. Web site: Landezine International Landscape Award LILA . 2019 . Caulfield to Dandenong Level Crossing Removal Project . 20 September 2022 . en-US . 20 September 2022 . https://web.archive.org/web/20220920171839/https://landezine-award.com/caulfield-to-dandenong-level-crossing-removal-project-2/ . live .
  56. Web site: Jacks . Timna . 13 November 2017 . Life under the viaduct: Melbourne's south-east Skyrail will get a 'green up' . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920171415/https://www.theage.com.au/national/victoria/life-under-the-viaduct-melbournes-southeast-skyrail-will-get-a-green-up-20171113-gzk4dl.html . live .
  57. Web site: Sakkal . Paul . 12 May 2019 . More than a year on, has 'sky rail' turned suburbs into ghettos? . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920173211/https://www.theage.com.au/national/victoria/more-than-a-year-on-has-sky-rail-turned-suburbs-into-ghettos-20190509-p51lqm.html . live .
  58. Web site: Cowie . Tom . 16 April 2018 . New sky rail station opens – and residents are happy about it . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920173804/https://www.theage.com.au/national/victoria/new-sky-rail-station-opens-and-residents-are-happy-about-it-20180416-p4z9wx.html . live .
  59. Web site: Lucas . Clay . 3 January 2021 . Anger grows as thousands of trees axed in transport building blitz . 23 October 2022 . The Age . en . 23 October 2022 . https://web.archive.org/web/20221023093956/https://www.theage.com.au/national/victoria/anger-as-thousands-of-trees-axed-in-transport-building-blitz-20210101-p56r6j.html . live .
  60. News: 2 September 2021 . Why are trees dying at this Melbourne train station? . en-AU . ABC News . 23 October 2022 . 24 October 2022 . https://web.archive.org/web/20221024001412/https://www.abc.net.au/news/2021-09-02/dead-trees-at-moreland-station/100425132 . live .
  61. News: 8 February 2022 . Level crossing removals: 600 trees to go for Glen Huntly trench . Herald Sun . 24 October 2022 . 24 October 2022 . https://web.archive.org/web/20221024033745/https://www.heraldsun.com.au/leader/inner-south/iconic-plane-trees-paperbarks-along-frankston-line-glen-huntly-at-risk/news-story/1a2b70f3513c790e8e48606a436aae84 . live .
  62. Web site: 20 June 2022 . Works notice – vegetation removal in Glen Huntly . 24 October 2022 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024032241/https://bigbuild.vic.gov.au/library/level-crossing-removal-project/frankston/glen-huntly/works/works-notice-vegetation-removal-in-glen-huntly . live .
  63. Web site: Carey . Adam . 28 September 2016 . Hundreds of red gums at risk if trench is built at Rosanna rail crossing . 24 October 2022 . The Age . en . 24 October 2022 . https://web.archive.org/web/20221024032242/https://www.theage.com.au/national/victoria/hundreds-of-red-gums-at-risk-if-trench-is-built-at-rosanna-rail-crossing-20160928-grqiqs.html . live .
  64. News: Koenig . Rick . 7 February 2017 . Design finalised for Lower Plenty Rd level crossing removal . Herald Sun . 24 October 2022 . 24 October 2022 . https://web.archive.org/web/20221024032240/https://www.heraldsun.com.au/leader/east/design-finalised-for-lower-plenty-rd-level-crossing-removal/news-story/a6b24a801d60f9874de343fb4b055b2d . live .
  65. Web site: 2 February 2022 . Station serves up a slice of history . 24 October 2022 . Bayside News . en-AU . 24 October 2022 . https://web.archive.org/web/20221024021342/https://baysidenews.com.au/2022/02/02/station-serves-up-a-slice-of-history/ . live .
  66. Web site: 14 June 2022 . TAFE class assist with Clayton Station restoration . 24 October 2022 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024021354/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/station-restoration-in-clayton . live .
  67. Web site: 16 September 2022 . Council's call for Parkdale Train Station heritage protection refused . 24 October 2022 . Mirage News . en-AU . 24 January 2023 . https://web.archive.org/web/20230124094411/https://www.miragenews.com/councils-call-for-parkdale-train-station-856131/ . live .
  68. Web site: Cowburn . Brodie . 21 September 2022 . Heritage hopes for train station dashed . 24 October 2022 . Bayside News . en-AU . 24 October 2022 . https://web.archive.org/web/20221024104557/https://baysidenews.com.au/2022/09/21/heritage-hopes-for-train-station-dashed/ . live .
  69. Web site: 12 October 2022 . New design features old station building . 24 October 2022 . Bayside News . en-AU . 24 October 2022 . https://web.archive.org/web/20221024021347/https://baysidenews.com.au/2022/10/12/new-design-features-old-station-building/ . live .
  70. Web site: Victoria’s Big Build . 1 October 2022 . Updated designs released for Parkdale level crossings . 24 October 2022 . en . 24 October 2022 . https://web.archive.org/web/20221024104556/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/updated-designs-released-for-parkdale-level-crossings . live .
  71. Web site: 8 June 2022 . Bell to Moreland comes out on top! . 24 October 2022 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024104559/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/bell-to-moreland-comes-out-on-top . live .
  72. Web site: 21 June 2022 . Ferguson Street, Williamstown . 24 October 2022 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024104556/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/ferguson-street-williamstown . live .
  73. Web site: 22 June 2022 . Burke Road, Glen Iris . 24 October 2022 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024104557/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/burke-road-glen-iris . live .
  74. Web site: 27 October 2022 . 'It would divide our community': Newport locals slam level crossing removal . 12 November 2022 . ABC Melbourne . en-AU . 12 November 2022 . https://web.archive.org/web/20221112074959/https://www.abc.net.au/melbourne/programs/drive/newport-champion-road-level-crossing-removal/101586900 . live .
  75. Web site: Murrumbeena Rail Station LXRP . Mascot Engineering . 25 March 2024.
  76. Web site: Victoria’s Big Build . 2022-06-15 . Union Road, Surrey Hills and Mont Albert Road, Mont Albert – selecting the best design . 2024-04-13 . Victoria’s Big Build . en.
  77. Web site: Union Road, Surrey Hills and Mont Albert Road, Mont Albert . Engage Victoria . 25 March 2024 . en.
  78. Web site: Union Road, Surrey Hills and Mont Albert Road, Mont Albert level crossing removals Submission from Boroondara City Council . . 25 March 2024.
  79. Web site: Kolovos . Benita . 1 April 2022 . Analysis: Australia's busiest state government goes into hibernation . 12 November 2022 . the Guardian . en . 12 November 2022 . https://web.archive.org/web/20221112111822/https://www.theguardian.com/australia-news/2022/apr/02/australias-busiest-state-government-goes-into-hibernation-not-just-isolation . live .
  80. Web site: Andrews . Daniel . 29 July 2021 . Premier of Victoria: Ten More Level Crossings To Go By 2025 . 12 November 2022 . 24 October 2022 . https://web.archive.org/web/20221024063521/https://www.premier.vic.gov.au/ten-more-level-crossings-go-2025 . live .
  81. Web site: Staszewska . Ewa . 4 November 2022 . 'Dictate from their ivory tower': Andrews upsets marginal Melbourne seat . 6 November 2022 . Sky News . en . 6 November 2022 . https://web.archive.org/web/20221106103527/https://www.skynews.com.au/australia-news/politics/liberal-mp-criticises-daniel-andrews-government-as-removed-from-reality-over-victorian-bayside-level-crossing-closure/news-story/01ad910442ea80749c315722cf3166b9 . live .
  82. Web site: Davis . Davis . 14 October 2020 . Press release: Allan and level crossing cowboys oversee a billion dollar blowout . 6 November 2022 . vic.liberal.org.au . 6 November 2022 . https://web.archive.org/web/20221106102027/https://vic.liberal.org.au/media-releases/2020-10-14-allan-and-level-crossing-cowboys-oversee-a-billion-dollar-blowout?topic=public-transport . live .
  83. Web site: Wahlquist . Calla . Bowers . Mike . 2018 . Victorian election 2018: On the ground in Cranbourne part 1 . 12 November 2022 . The Guardian . en . 12 November 2022 . https://web.archive.org/web/20221112111826/https://www.theguardian.com/australia-news/ng-interactive/2018/oct/31/victorian-election-2018-on-the-ground-in-cranbourne-part-1 . live .
  84. Web site: 29 October 2022 . The Daniel Andrews paradox: the enduring appeal of Australia's most divisive premier . 2 November 2022 . the Guardian . en . 2 November 2022 . https://web.archive.org/web/20221102101426/https://www.theguardian.com/australia-news/2022/oct/30/the-daniel-andrews-paradox-the-enduring-appeal-of-australias-most-divisive-premier . live .
  85. Web site: Carey . Adam . 14 December 2017 . Level crossing removal program poor value for money: Auditor-General Andrew Greaves . 12 November 2022 . The Age . en . 12 November 2022 . https://web.archive.org/web/20221112111827/https://www.theage.com.au/national/victoria/level-crossing-removal-program-poor-value-for-money-auditorgeneral-andrew-greaves-20171214-h04ed0.html . live .
  86. Web site: Abbott . Lachlan . 17 August 2022 . Barred from their own street, residents fume at handling of level crossing works . 12 November 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920172835/https://www.theage.com.au/politics/victoria/barred-from-their-own-street-residents-fume-at-handling-of-level-crossing-works-20220817-p5ban1.html . live .
  87. Web site: Jacks . Timna . 23 January 2018 . Just a minute: Level crossing project resulting in small time savings, data shows . 12 November 2022 . The Age . en . 12 November 2022 . https://web.archive.org/web/20221112111838/https://www.theage.com.au/national/victoria/just-a-minute-level-crossing-project-resulting-in-small-time-savings-data-shows-20180123-p4yys5.html . live .
  88. News: Masanauskas . John . 17 August 2022 . Melbourne's leafy east set for level crossing removal mayhem . Herald Sun . 12 November 2022 . 12 November 2022 . https://web.archive.org/web/20221112121846/https://www.heraldsun.com.au/news/victoria/melbournes-leafy-east-set-for-level-crossing-removal-mayhem/news-story/9a74fb970bb887e2217bcf2c679fa70a . live .
  89. Web site: 15 December 2015 . Benefits to non-motorists from level crossing removals . 6 November 2022 . Daniel Bowen . en-AU . 6 November 2022 . https://web.archive.org/web/20221106085420/https://www.danielbowen.com/2015/12/15/grade-separation-benefits/ . live .
  90. Web site: 11 January 2016 . Level crossing removal – all options must be on the table Public Transport Users Association (Victoria, Australia) . 12 November 2022 . Public Transport Users Association . en-AU . 12 November 2022 . https://web.archive.org/web/20221112074954/https://www.ptua.org.au/2016/01/11/level-crossing-options/ . live .
  91. Web site: AAP . 19 August 2014 . Do more on Victorian transport: RACV . 6 November 2022.
  92. Web site: Woodcock . Ian . Stone . John . 2016 . The Benefits of Level Crossing Removal: lessons from Melbourne's historical experience . 12 November 2022 . University of Melbourne, RMIT University . 12 November 2022 . https://web.archive.org/web/20221112111839/https://researchrepository.rmit.edu.au/esploro/outputs/report/The-Benefits-of-Level-Crossing-Removal-lessons-from-Melbournes-historical-experience/9921860675101341 . live .
  93. Web site: Managing the Level Crossing Removal Program . 1 November 2022 . Victorian Auditor-General's Office . en . 1 November 2022 . https://web.archive.org/web/20221101093250/https://www.audit.vic.gov.au/report/managing-level-crossing-removal-program . live .
  94. News: Carey . Adam . 14 December 2017 . Level crossing removal program poor value for money: Auditor-General Andrew Greaves . The Age . 14 December 2017 . 14 December 2017 . https://web.archive.org/web/20171214182343/http://www.theage.com.au/victoria/level-crossing-removal-program-poor-value-for-money-auditorgeneral-andrew-greaves-20171214-h04ed0.html . live .
  95. Web site: Victorian auditor-general . Follow-up level crossing removal report . live . 1 November 2022 . 1 November 2022 . https://web.archive.org/web/20221101091744/https://www.parliament.vic.gov.au/file_uploads/20201014-Follow-up_level_crossing_removal_report_k2c4ZRcV.pdf .
  96. Web site: Skyrail protest in Coburg Hundreds of angry residents marched through Coburg to protest a Skyrail on the Upfield line through the northern suburbs. www.7plus.com.au/news #7News By 7NEWS Melbourne Facebook . 6 November 2022 . www.facebook.com . en . 6 November 2022 . https://web.archive.org/web/20221106090340/https://www.facebook.com/7NEWSMelbourne/videos/skyrail-protest-in-coburg/1886776784746451/ . live .
  97. Web site: Hundreds march down Melbourne highway in protest of Sky Rail construction . 6 November 2022 . www.9news.com.au . 18 September 2016 . 6 November 2022 . https://web.archive.org/web/20221106090341/https://www.9news.com.au/national/hundreds-march-down-melbourne-highway-in-protest-of-sky-rail-construction/fc8b264d-d437-4ca7-bed4-ac33079c6fff . live .
  98. Web site: Landy . Sam . Johnston . Matt . 20 October 2014 . Victorian state election 2014: Labor's key promises in detail . live . 14 November 2022 . Herald Sun . 14 November 2022 . https://web.archive.org/web/20221114022203/https://www.heraldsun.com.au/news/victoria-state-election-2014/victorian-state-election-2014-labors-key-promises-in-detail/news-story/c905df37da58db80bce6016fc530c03d .
  99. Web site: 22 June 2022 . Charman Road, Cheltenham . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171632/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/park-and-charman-roads-cheltenham . live .
  100. Web site: 21 June 2022 . Lochiel Avenue, Edithvale . 11 December 2022 . Victoria's Big Build . 3 December 2022 . https://web.archive.org/web/20221203183202/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/lochiel-avenue-edithvale . live .
  101. Web site: 21 June 2022 . Mascot Avenue, Bonbeach . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920184257/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mascot-avenue-bonbeach . live .
  102. Web site: Willingham . Richard . 23 June 2015 . Three suburban train stations to be rebuilt underground: St Albans, Ginifer and Heatherdale . 14 November 2022 . The Age . en . 14 November 2022 . https://web.archive.org/web/20221114020700/https://www.theage.com.au/national/victoria/three-suburban-train-stations-to-be-rebuilt-undergound-20150623-ghv0la.html . live .
  103. Web site: Victoria’s Big Build . 2022-06-22 . Burke Road, Glen Iris . 2023-12-12 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024104557/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/burke-road-glen-iris . live .
  104. Web site: Victoria’s Big Build . 2022-06-21 . Centre Road, Bentleigh . 2023-12-12 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225040244/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/centre-road-bentleigh . live .
  105. Web site: Victoria’s Big Build . 2022-06-21 . North Road, Ormond . 2023-12-12 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225060347/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/north-road-ormond . live .
  106. Web site: Victoria’s Big Build . 2022-06-21 . McKinnon Road, McKinnon . 2023-12-12 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225040244/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mckinnon-road-mckinnon . live .
  107. Web site: Victoria’s Big Build . 2022-06-21 . Furlong Road, St Albans . 2023-12-12 . Victoria’s Big Build . en . 17 April 2023 . https://web.archive.org/web/20230417073135/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/furlong-road-st-albans . live .
  108. Web site: Victoria’s Big Build . 2022-06-21 . Main Road, St Albans . 2023-12-12 . Victoria’s Big Build . en . 17 April 2023 . https://web.archive.org/web/20230417073140/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/main-road-st-albans . live .
  109. Web site: Victoria’s Big Build . 2022-06-21 . Mountain Highway, Bayswater . 2023-12-12 . Victoria’s Big Build . en . 24 February 2023 . https://web.archive.org/web/20230224100144/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mountain-highway-bayswater . live .
  110. Web site: Victoria’s Big Build . 2022-06-21 . Scoresby Road, Bayswater . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060849/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/scoresby-road-bayswater . live .
  111. Web site: 21 June 2022 . Blackburn Road, Blackburn . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920184258/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/blackburn-road-blackburn . live .
  112. Web site: 21 June 2022 . Heatherdale Road, Mitcham . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172816/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/heatherdale-road-mitcham . live .
  113. Web site: 21 June 2022 . Camp Road, Campbellfield . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920170627/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/camp-road-campbellfield . live .
  114. Web site: Victoria’s Big Build . 2022-06-21 . Melton Highway, Sydenham . 2023-12-12 . Victoria’s Big Build . en . 7 April 2023 . https://web.archive.org/web/20230407105103/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/melton-highway-sydenham . live .
  115. Web site: Victoria’s Big Build . 2022-06-21 . Chandler Road, Noble Park . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055355/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/chandler-road-noble-park . live .
  116. Web site: Victoria’s Big Build . 2022-06-21 . Corrigan Road, Noble Park . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055457/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/corrigan-road-noble-park . live .
  117. Web site: Victoria’s Big Build . 2022-06-21 . Heatherton Road, Noble Park . 2023-12-12 . Victoria’s Big Build . en . 7 April 2023 . https://web.archive.org/web/20230407105103/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/heatherton-road-noble-park . live .
  118. Web site: Victoria’s Big Build . 2022-06-21 . Centre Road, Clayton . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055349/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/centre-road-clayton . live .
  119. Web site: Victoria’s Big Build . 2022-06-21 . Clayton Road, Clayton . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055424/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/clayton-road-clayton . live .
  120. Web site: Victoria’s Big Build . 2022-06-21 . Grange Road, Alphington . 2023-12-12 . Victoria’s Big Build . en . 25 March 2023 . https://web.archive.org/web/20230325074128/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/grange-road-alphington . live .
  121. Web site: Victoria’s Big Build . 2022-06-21 . Lower Plenty Road, Rosanna . 2023-12-12 . Victoria’s Big Build . en . 25 March 2023 . https://web.archive.org/web/20230325073136/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/lower-plenty-road-rosanna . live .
  122. Web site: Victoria’s Big Build . 2022-06-21 . Grange Road, Carnegie . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055754/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/grange-road-carnegie . live .
  123. Web site: Victoria’s Big Build . 2022-06-21 . Koornang Road, Carnegie . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055927/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/koornang-road-carnegie . live .
  124. Web site: Victoria’s Big Build . 2022-06-21 . Murrumbeena Road, Murrumbeena . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060647/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/murrumbeena-road-murrumbeena . live .
  125. Web site: Victoria’s Big Build . 2022-06-21 . Poath Road, Hughesdale . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060737/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/poath-road-hughesdale . live .
  126. Web site: Victoria’s Big Build . 2022-06-21 . Skye/Overton Road, Frankston . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060902/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/skye-overton-road-frankston . live .
  127. Web site: Victoria’s Big Build . 2022-06-21 . Thompsons Road, Lyndhurst . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024061025/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/thompsons-road-lyndhurst . live .
  128. Web site: Victoria’s Big Build . 2022-06-21 . Kororoit Creek Road, Williamstown North . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055935/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/kororoit-creek-road-williamstown-north . live .
  129. Web site: Victoria’s Big Build . 2022-06-22 . Abbotts Road, Dandenong South . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055139/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/abbotts-road-dandenong-south . live .
  130. Web site: 21 June 2022 . Buckley Street, Essendon . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172548/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/buckley-street-essendon . live .
  131. Web site: Victoria’s Big Build . 2022-06-21 . Seaford Road, Seaford . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060857/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/seaford-road-seaford . live .
  132. Web site: Victoria’s Big Build . 2022-06-21 . Aviation Road, Laverton . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055203/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/aviation-road-laverton . live .
  133. Web site: High Street, Reservoir . 19 September 2022 . engage.vic.gov.au . 20 September 2022 . https://web.archive.org/web/20220920173417/https://engage.vic.gov.au/lxrp-reservoir . live .
  134. Web site: 21 June 2022 . Eel Race Road, Carrum . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172203/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/eel-race-road-carrum . live .
  135. Web site: 21 June 2022 . Mascot Avenue, Bonbeach . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920184257/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mascot-avenue-bonbeach . live .
  136. Web site: 21 June 2022 . Station Street, Carrum . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172914/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/station-street-carrum . live .
  137. Web site: 21 June 2022 . Toorak Road, Kooyong . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172754/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/toorak-road-kooyong . live .
  138. Web site: Victoria’s Big Build . 2022-06-22 . Balcombe Road, Mentone . 2023-12-12 . Victoria’s Big Build . en . 1 March 2023 . https://web.archive.org/web/20230301034259/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/balcombe-road-mentone . live .
  139. Web site: Victoria’s Big Build . 2022-06-22 . Charman Road, Cheltenham . 2023-12-12 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171632/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/park-and-charman-roads-cheltenham . live .
  140. Web site: Victoria’s Big Build . 2022-06-22 . Bell Street, Coburg . 2023-12-12 . Victoria’s Big Build . en . 9 April 2023 . https://web.archive.org/web/20230409094924/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/bell-street-coburg . live .
  141. Web site: Victoria’s Big Build . 2022-06-22 . Moreland Road, Brunswick . 2023-12-12 . Victoria’s Big Build . en . 9 April 2023 . https://web.archive.org/web/20230409094954/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/moreland-road-brunswick . live .
  142. Web site: Victoria’s Big Build . 2023-05-24 . Werribee Street, Werribee . 2023-12-12 . Victoria’s Big Build . en . 28 October 2023 . https://web.archive.org/web/20231028081531/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/werribee-street-werribee . live .
  143. Web site: Victoria’s Big Build . 2022-06-22 . Cherry Street, Werribee . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055418/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/cherry-street-werribee . live .
  144. Web site: Victoria’s Big Build . 2023-02-24 . South Gippsland Highway, Dandenong South . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060911/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/south-gippsland-highway . live .
  145. Web site: Victoria’s Big Build . 2022-06-21 . Bondi Road, Bonbeach . 2023-12-12 . Victoria’s Big Build . en . 2 December 2023 . https://web.archive.org/web/20231202054538/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/bondi-road-bonbeach . live .
  146. Web site: Victoria’s Big Build . 2022-06-21 . Edithvale Road, Edithvale . 2023-12-12 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225034736/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/edithvale-road-edithvale . live .
  147. Web site: Victoria’s Big Build . 2022-06-21 . Lochiel Avenue, Edithvale . 2023-12-12 . Victoria’s Big Build . en . 3 December 2022 . https://web.archive.org/web/20221203183202/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/lochiel-avenue-edithvale . live .
  148. Web site: Victoria’s Big Build . 2023-02-24 . Manchester Road, Mooroolbark . 2023-12-12 . Victoria’s Big Build . en . 2 December 2023 . https://web.archive.org/web/20231202054539/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/manchester-road-mooroolbark . live .
  149. Web site: Victoria’s Big Build . 2023-02-24 . Maroondah Highway, Lilydale . 2023-12-12 . Victoria’s Big Build . en . 1 March 2023 . https://web.archive.org/web/20230301034317/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/maroondah-highway-lilydale . live .
  150. Web site: Victoria’s Big Build . 2023-02-24 . Ferguson Street, Williamstown . 2023-12-12 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024104556/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/ferguson-street-williamstown . live .
  151. Web site: Victoria’s Big Build . 2023-05-16 . Clyde Road, Berwick . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055430/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/clyde-road-berwick . live .
  152. Web site: 12 July 2022 . Hallam Road, Hallam . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172725/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/hallam-road-hallam . live .
  153. Web site: 15 September 2022 . Bell Street, Preston . 11 December 2022 . Victoria's Big Build . 11 January 2023 . https://web.archive.org/web/20230111060956/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/bell-street-preston . live .
  154. Web site: Victoria’s Big Build . 2023-04-12 . Glenroy Road, Glenroy . 2023-12-12 . Victoria’s Big Build . en . 11 April 2023 . https://web.archive.org/web/20230411104740/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/glenroy-road-glenroy . live .
  155. Web site: 22 June 2022 . Evans Road, Lyndhurst . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172621/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/evans-road-lyndhurst . live .
  156. Web site: Victoria’s Big Build . 2022-06-22 . Munro Street, Coburg . 2023-12-12 . Victoria’s Big Build . en . 9 April 2023 . https://web.archive.org/web/20230409124708/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/munro-street-coburg . live .
  157. Web site: Victoria’s Big Build . 2022-06-22 . Reynard Street, Coburg . 2023-12-12 . Victoria’s Big Build . en . 9 April 2023 . https://web.archive.org/web/20230409094943/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/reynard-street-coburg . live .
  158. Web site: 22 June 2022 . Cardinia Road, Pakenham . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171752/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/cardinia-road-pakenham . live .
  159. Web site: Victoria’s Big Build . 2022-06-21 . Argyle Avenue, Chelsea . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055153/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/argyle-avenue-chelsea . live .
  160. Web site: Victoria’s Big Build . 2022-06-21 . Chelsea Road, Chelsea . 2023-12-12 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225034741/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/chelsea-road-chelsea . live .
  161. Web site: Victoria’s Big Build . 2022-06-21 . Swanpool Avenue, Chelsea . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024061012/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/swanpool-avenue-chelsea . live .
  162. Web site: Victoria’s Big Build . 2023-02-24 . Old Geelong Road, Hoppers Crossing . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060715/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/old-geelong-road-hoppers-crossing . live .
  163. Web site: Victoria’s Big Build . 2022-06-21 . Greens Road, Dandenong South . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055800/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/greens-road-dandenong-south . live .
  164. Web site: 6 September 2022 . Cramer Street, Preston . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920173324/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/cramer-street-preston . live .
  165. Web site: 6 September 2022 . Murray Road, Preston . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920173210/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/murray-road-preston . live .
  166. Web site: Victoria’s Big Build . 2023-04-14 . Oakover Road, Preston . 2023-12-12 . Victoria’s Big Build . en . 1 April 2023 . https://web.archive.org/web/20230401075459/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/oakover-road-preston . live .
  167. Web site: Victoria’s Big Build . 2023-07-07 . Fitzgerald Road, Ardeer . 2023-12-12 . Victoria’s Big Build . en . 10 July 2023 . https://web.archive.org/web/20230710120026/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/fitzgerald-road-ardeer . live .
  168. Web site: Victoria’s Big Build . 2023-07-07 . Robinsons Road, Deer Park . 2023-12-12 . Victoria’s Big Build . en . 10 July 2023 . https://web.archive.org/web/20230710120040/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/robinsons-road-deer-park . live .
  169. Web site: Victoria’s Big Build . 2023-04-12 . Gap Road, Sunbury . 2023-12-12 . Victoria’s Big Build . en . 21 March 2023 . https://web.archive.org/web/20230321082847/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/gap-road-sunbury . live .
  170. Web site: Victoria’s Big Build . 2023-07-26 . Mt Derrimut Road, Deer Park . 2023-12-12 . Victoria’s Big Build . en . 10 July 2023 . https://web.archive.org/web/20230710115816/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mt-derrimut-road-deer-park . live .
  171. Web site: 3 August 2022 . Mont Albert Road, Mont Albert . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171828/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mont-albert-road-mont-albert . live .
  172. Web site: 3 August 2022 . Mont Albert Road, Mont Albert . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171828/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mont-albert-road-mont-albert . live .
  173. Web site: 28 June 2022 . Neerim Road, Glen Huntly . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920175743/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/neerim-road-glen-huntly . live .
  174. Web site: 28 June 2022 . Glen Huntly Road, Glen Huntly . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171905/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/glen-huntly-road-glen-huntly . live .
  175. Web site: Victoria’s Big Build . 2023-12-11 . Camms Road, Cranbourne . 2023-12-12 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055323/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/camms-road-cranbourne . live .
  176. Web site: 22 June 2022 . Main Street, Pakenham . 19 September 2022 . Victoria’s Big Build . en . 9 December 2022 . https://web.archive.org/web/20221209013441/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/main-street-pakenham . live .
  177. Web site: 22 June 2022 . McGregor Road, Pakenham . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172042/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mcgregor-road-pakenham . live .
  178. Web site: 22 June 2022 . Racecourse Road, Pakenham . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174622/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/racecourse-road-pakenham . live .
  179. Web site: 21 June 2022 . Webster Street, Dandenong . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172844/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/webster-street-dandenong . live .
  180. Web site: 7 September 2022 . Webb Street, Narre Warren . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174238/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/webb-street-narre-warren . live .
  181. Web site: 21 June 2022 . Cave Hill Road, Lilydale . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920173746/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/cave-hill-road-lilydale . live .
  182. Web site: 29 August 2022 . Bedford Road, Ringwood . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920173600/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/bedford-road-ringwood . live .
  183. Web site: 21 June 2022 . Brunt Road, Beaconsfield . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172707/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/brunt-road-beaconsfield . live .
  184. Web site: 9 September 2022 . Keon Parade, Reservoir . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920173002/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/keon-parade-reservoir . live .
  185. Web site: 21 June 2022 . Station Street, Officer . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174236/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/station-street-officer . live .
  186. Web site: 29 August 2022 . Dublin Road, Ringwood East . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174234/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/dublin-road-ringwood-east . live .
  187. Web site: 7 September 2022 . Coolstore Road, Croydon . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174239/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/coolstore-road-croydon . live .
  188. Web site: Victoria’s Big Build . 2023-11-22 . Warrigal Road, Mentone . live . https://web.archive.org/web/20220920173008/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/warrigal-road-mentone . 20 September 2022 . 2023-12-13 . Victoria’s Big Build . en.
  189. Web site: 21 June 2022 . Parkers Road, Parkdale . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172840/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/parkers-road-parkdale . live .
  190. Web site: 21 June 2022 . Calder Park Drive, Calder Park . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171222/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/calder-park-drive-calder-park . live .
  191. Web site: 21 June 2022 . Progress Street, Dandenong South . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171857/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/progress-street-dandenong-south . live .
  192. Web site: Victoria’s Big Build . 2024-05-03 . Piling works underway at Progress Street . 2024-05-03 . Victoria’s Big Build . en.
  193. Web site: 21 June 2022 . Station Street, Beaconsfield . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174623/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/station-street-beaconsfield . live .
  194. Web site: 21 June 2022 . Holden Road, Calder Park . 19 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174028/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/holden-road-calder-park . live .
  195. News: 9 October 2022 . Victorian opposition pledges to cap public transport fares at $2 a day . en-AU . ABC News . 9 October 2022 . 9 October 2022 . https://web.archive.org/web/20221009231822/https://www.abc.net.au/news/2022-10-09/victorian-election-promises-2-dollar-public-transport/101516028 . live .
  196. Web site: 19 September 2022 . Level Crossing Removal Project . 9 October 2022 . Victoria’s Big Build . en . 21 September 2022 . https://web.archive.org/web/20220921194737/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project . live .
  197. Web site: 25 October 2022 . Making Macleod level crossing-free . 25 October 2022 . Victoria’s Big Build . en . 25 October 2022 . https://web.archive.org/web/20221025061053/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/making-macleod-level-crossing-free . live .
  198. Web site: Victoria’s Big Build . 2023-10-10 . Old Calder Highway, Diggers Rest . 2023-12-01 . Victoria’s Big Build . en . 17 April 2023 . https://web.archive.org/web/20230417074743/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/diggers-rest . live .
  199. Web site: Site establishment works continue in Diggers Rest . 2024-05-31 . levelcrossingremovalproject.cmail20.com.
  200. Web site: Victoria’s Big Build . 2023-11-14 . Mordialloc level crossings . 2023-12-01 . Victoria’s Big Build . en . 4 December 2023 . https://web.archive.org/web/20231204050218/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mordialloc . live .
  201. Web site: Victoria’s Big Build . 2023-10-02 . Maddox Road and Champion Road, Newport . 2023-12-01 . Victoria’s Big Build . en . 4 December 2023 . https://web.archive.org/web/20231204051721/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/newport . live .
  202. Web site: Victoria’s Big Build . 2023-11-27 . Melton level crossing removals . 2023-12-01 . Victoria’s Big Build . en . 5 December 2023 . https://web.archive.org/web/20231205091327/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/melton . live .
  203. Web site: Victoria’s Big Build . 2023-08-02 . Maidstone Street, Altona . 2023-12-01 . Victoria’s Big Build . en . 4 December 2023 . https://web.archive.org/web/20231204053224/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/maidstone-street-altona . live .
  204. Web site: Victoria’s Big Build . 2023-02-24 . Ruthven Street, Macleod . 2023-12-01 . Victoria’s Big Build . en . 25 March 2023 . https://web.archive.org/web/20230325073754/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/ruthven-street-macleod . live .
  205. Web site: Victoria’s Big Build . 2023-02-24 . Werribee Line level crossing removals . 2023-12-01 . Victoria’s Big Build . en . 27 October 2022 . https://web.archive.org/web/20221027233002/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/werribee . live .
  206. Web site: Victoria’s Big Build . 2023-03-07 . Seaford level crossings . 2023-12-01 . Victoria’s Big Build . en . 4 December 2023 . https://web.archive.org/web/20231204051722/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/seaford . live .
  207. Web site: Victoria’s Big Build . 2023-09-07 . Frankston Line level crossing removals . 2023-12-01 . Victoria’s Big Build . en . 4 December 2023 . https://web.archive.org/web/20231204053223/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/frankston . live .
  208. Web site: Victoria’s Big Build . 2023-10-04 . Brunswick and Parkville . live . https://web.archive.org/web/20230408051010/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/brunswick . 8 April 2023 . 2023-12-01 . Victoria’s Big Build . en.
  209. Web site: Carey . Adam . 15 November 2016 . Hawkstowe is go: Third train station announced for Mernda rail extension . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920173053/https://www.theage.com.au/national/victoria/hawkstowe-is-go-third-train-station-announced-for-mernda-rail-extenstion-20161115-gspb8i.html . live .
  210. Web site: Boseley . Matilda . 1 April 2018 . Mernda train line ahead of schedule . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920173024/https://www.theage.com.au/national/victoria/mernda-train-line-ahead-of-schedule-20180401-p4z7by.html . live .
  211. Web site: 19 June 2022 . Pakenham East Station location fact sheet . 20 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920182752/https://bigbuild.vic.gov.au/library/level-crossing-removal-project/pakenham/pakenham/community-updates-and-fact-sheets/pakenham-east-station-fact-sheet . live .
  212. Web site: Carton . Donna . 24 November 2017 . Southland Station finally ready to open this Sunday . Herald Sun Leader.
  213. Web site: 28 March 2022 . A 'Union' of 2 communities and more open space in the heart of Union Road . 20 September 2022 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920174048/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/a-union-of-2-communities-and-more-open-space . live .
  214. Web site: Abbott . Lachlan . 17 August 2022 . Barred from their own street, residents fume at handling of level crossing works . 20 September 2022 . The Age . en . 20 September 2022 . https://web.archive.org/web/20220920172835/https://www.theage.com.au/politics/victoria/barred-from-their-own-street-residents-fume-at-handling-of-level-crossing-works-20220817-p5ban1.html . live .
  215. Web site: Victoria’s Big Build . 2022-06-22 . Burke Road, Glen Iris . 2023-12-02 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024104557/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/burke-road-glen-iris . live .
  216. Web site: Victoria’s Big Build . 2022-06-21 . McKinnon Road, McKinnon . 2023-12-02 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225040244/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mckinnon-road-mckinnon . live .
  217. Web site: Victoria’s Big Build . 2022-06-21 . Centre Road, Bentleigh . 2023-12-02 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225040244/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/centre-road-bentleigh . live .
  218. Web site: Victoria’s Big Build . 2022-06-21 . North Road, Ormond . 2023-12-02 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225060347/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/north-road-ormond . live .
  219. Web site: Victoria’s Big Build . 2022-06-21 . Furlong Road, St Albans . 2023-12-02 . Victoria’s Big Build . en . 17 April 2023 . https://web.archive.org/web/20230417073135/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/furlong-road-st-albans . live .
  220. Web site: Victoria’s Big Build . 2022-06-21 . Main Road, St Albans . 2023-12-02 . Victoria’s Big Build . en . 17 April 2023 . https://web.archive.org/web/20230417073140/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/main-road-st-albans . live .
  221. Web site: Victoria’s Big Build . 2022-06-21 . Mountain Highway, Bayswater . 2023-12-02 . Victoria’s Big Build . en . 24 February 2023 . https://web.archive.org/web/20230224100144/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mountain-highway-bayswater . live .
  222. Web site: Victoria’s Big Build . 2022-06-21 . Heatherdale Road, Mitcham . 2023-12-02 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172816/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/heatherdale-road-mitcham . live .
  223. News: 22 October 2017 . Southland Station Set For A Festive Opening . en-US . Premier of Victoria . live . 31 October 2017 . https://web.archive.org/web/20171107005219/https://www.premier.vic.gov.au/southland-station-set-for-a-festive-opening/ . 7 November 2017.
  224. Web site: Victoria’s Big Build . 2022-06-21 . Heatherton Road, Noble Park . 2023-12-02 . Victoria’s Big Build . en . 7 April 2023 . https://web.archive.org/web/20230407105103/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/heatherton-road-noble-park . live .
  225. Web site: Victoria’s Big Build . 2022-06-21 . Clayton Road, Clayton . 2023-12-02 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055424/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/clayton-road-clayton . live .
  226. Web site: Victoria’s Big Build . 2022-06-21 . Lower Plenty Road, Rosanna . 2023-12-02 . Victoria’s Big Build . en . 25 March 2023 . https://web.archive.org/web/20230325073136/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/lower-plenty-road-rosanna . live .
  227. Web site: Victoria’s Big Build . 2022-06-21 . Koornang Road, Carnegie . 2023-12-02 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024055927/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/koornang-road-carnegie . live .
  228. Web site: Frankston Station Precinct Redevelopment . live . https://web.archive.org/web/20171111042241/http://economicdevelopment.vic.gov.au/transport/rail-and-roads/public-transport/frankston-station-precinct-redevelopment . 11 November 2017 . 5 January 2018 . economicdevelopment.vic.gov.au.
  229. Web site: Victoria’s Big Build . 2022-06-21 . Murrumbeena Road, Murrumbeena . 2023-12-02 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060647/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/murrumbeena-road-murrumbeena . live .
  230. Web site: Victoria’s Big Build . 2022-06-21 . Poath Road, Hughesdale . 2023-12-02 . Victoria’s Big Build . en . 24 October 2023 . https://web.archive.org/web/20231024060737/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/poath-road-hughesdale . live .
  231. Web site: Victoria’s Big Build . 2021-01-25 . Mernda Rail Extension . 2023-12-02 . Victoria’s Big Build . en . 27 February 2021 . https://web.archive.org/web/20210227005603/https://levelcrossings.vic.gov.au/projects/mernda-rail-extension-project . live .
  232. Web site: Victoria’s Big Build . 2023-04-14 . High Street, Reservoir . 2023-12-02 . Victoria’s Big Build . en . 1 April 2023 . https://web.archive.org/web/20230401075331/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/high-street-reservoir . live .
  233. Web site: Victoria’s Big Build . 2022-06-21 . Station Street, Carrum . 2023-12-02 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172914/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/station-street-carrum . live .
  234. Web site: Victoria's Big Build . 2022-06-21 . Balcombe Road, Mentone . 2 December 2023 . Victoria's Big Build . 1 March 2023 . https://web.archive.org/web/20230301034259/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/balcombe-road-mentone . live .
  235. Web site: Victoria’s Big Build . 2022-06-22 . Charman Road, Cheltenham . 2023-12-02 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171632/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/park-and-charman-roads-cheltenham . live .
  236. Web site: Victoria’s Big Build . 2022-06-22 . Bell Street, Coburg . 2023-12-02 . Victoria’s Big Build . en . 9 April 2023 . https://web.archive.org/web/20230409094924/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/bell-street-coburg . live .
  237. Web site: Victoria’s Big Build . 2022-06-22 . Moreland Road, Brunswick . 2023-12-02 . Victoria’s Big Build . en . 9 April 2023 . https://web.archive.org/web/20230409094954/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/moreland-road-brunswick . live .
  238. Web site: Victoria’s Big Build . 2022-06-16 . Your new Lilydale Station . 2023-12-02 . Victoria’s Big Build . en . 2 December 2023 . https://web.archive.org/web/20231202060038/https://bigbuild.vic.gov.au/library/level-crossing-removal-project/lilydale/manchester-maroondah/fact-sheets/your-new-lilydale-station . live .
  239. Web site: Victoria’s Big Build . 2023-02-24 . Manchester Road, Mooroolbark . 2023-12-02 . Victoria’s Big Build . en . 2 December 2023 . https://web.archive.org/web/20231202054539/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/manchester-road-mooroolbark . live .
  240. Web site: Victoria’s Big Build . 2022-06-21 . Bondi Road, Bonbeach . 2023-12-02 . Victoria’s Big Build . en . 2 December 2023 . https://web.archive.org/web/20231202054538/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/bondi-road-bonbeach . live .
  241. Web site: Victoria’s Big Build . 2022-06-21 . Chelsea Road, Chelsea . 2023-12-02 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225034741/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/chelsea-road-chelsea . live .
  242. Web site: Victoria’s Big Build . 2022-06-21 . Edithvale Road, Edithvale . 2023-12-02 . Victoria’s Big Build . en . 25 February 2023 . https://web.archive.org/web/20230225034736/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/edithvale-road-edithvale . live .
  243. Web site: Victoria’s Big Build . 2023-02-24 . Ferguson Street, Williamstown . 2023-12-02 . Victoria’s Big Build . en . 24 October 2022 . https://web.archive.org/web/20221024104556/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/ferguson-street-williamstown . live .
  244. Web site: Merinda Park Station Precinct Cranbourne Line Upgrade . 2023-12-02 . Engage Victoria . en . 1 March 2023 . https://web.archive.org/web/20230301034258/https://engage.vic.gov.au/project/lxrp-cranbourne-line-upgrade/page/merinda-park-station-precinct . live .
  245. Web site: Victoria’s Big Build . 2022-10-26 . Hallam Road, Hallam . 2023-12-02 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920172725/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/hallam-road-hallam . live .
  246. Web site: Victoria’s Big Build . 2023-04-12 . Glenroy Road, Glenroy . 2023-12-02 . Victoria’s Big Build . en . 11 April 2023 . https://web.archive.org/web/20230411104740/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/glenroy-road-glenroy . live .
  247. Web site: Victoria’s Big Build . 2023-09-06 . Happy 1st birthday to the new Preston and Bell stations . 2023-12-02 . Victoria’s Big Build . en . 2 December 2023 . https://web.archive.org/web/20231202054536/https://bigbuild.vic.gov.au/news/level-crossing-removal-project/happy-1st-birthday-to-the-new-preston-and-bell-stations . live .
  248. Web site: Victoria’s Big Build . 2023-07-26 . Mt Derrimut Road, Deer Park . 2023-12-02 . Victoria’s Big Build . en . 10 July 2023 . https://web.archive.org/web/20230710115816/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/mt-derrimut-road-deer-park . live .
  249. Web site: Victoria’s Big Build . 2023-03-16 . Montmorency upcoming major works in March and April . 2023-12-02 . Victoria’s Big Build . en . 2 December 2023 . https://web.archive.org/web/20231202060038/https://bigbuild.vic.gov.au/library/level-crossing-removal-project/rail/hurstbridge/works/montmorency-upcoming-major-works-in-march-and-april . live .
  250. Web site: Victoria’s Big Build . 2023-05-29 . Union Road, Surrey Hills . 2023-12-02 . Victoria’s Big Build . en . 18 February 2023 . https://web.archive.org/web/20230218044632/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/union-road-surrey-hills . live .
  251. Web site: Victoria’s Big Build . 2023-05-29 . Union Road, Surrey Hills . 2023-12-02 . Victoria’s Big Build . en . 18 February 2023 . https://web.archive.org/web/20230218044632/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/union-road-surrey-hills . live .
  252. Web site: Victoria’s Big Build . 2023-09-25 . Glen Huntly Road, Glen Huntly . 2023-12-02 . Victoria’s Big Build . en . 20 September 2022 . https://web.archive.org/web/20220920171905/https://bigbuild.vic.gov.au/projects/level-crossing-removal-project/projects/glen-huntly-road-glen-huntly . live .