Nuclear decommissioning explained

Nuclear decommissioning is the process leading to the irreversible complete or partial closure of a nuclear facility, usually a nuclear reactor, with the ultimate aim at termination of the operating licence. The process usually runs according to a decommissioning plan, including the whole or partial dismantling and decontamination of the facility, ideally resulting in restoration of the environment up to greenfield status. The decommissioning plan is fulfilled when the approved end state of the facility has been reached.

The process typically takes about 15 to 30 years, or many decades more when an interim safe storage period is applied for radioactive decay. Radioactive waste that remains after the decommissioning is either moved to an on-site storage facility where it is still under control of the owner, or moved to a dry cask storage or disposal facility at another location. The final disposal of nuclear waste from past and future decommissioning is a growing still unsolved problem.

Decommissioning is an administrative and technical process. The facility is dismantled to the point that it no longer requires measures for radiation protection. It includes clean-up of radioactive materials. Once a facility is fully decommissioned, no radiological danger should persist. The license will be terminated and the site released from regulatory control. The plant licensee is then no longer responsible for the nuclear safety.

The costs of decommissioning are to be covered by funds that are provided for in a decommissioning plan, which is part of the facility's initial authorization. They may be saved in a decommissioning fund, such as a trust fund.

There are worldwide also hundreds of thousands small nuclear devices and facilities, for medical, industrial and research purposes, that will have to be decommissioned at some point.[1]

Definition

Nuclear decommissioning is the administrative and technical process leading to the irreversible closure of a nuclear facility such as a nuclear power plant (NPP), a research reactor, an isotope production plant, a particle accelerator, or uranium mine. It refers to the administrative and technical actions taken to remove all or some of the regulatory controls from the facility to bring about that its site can be reused. Decommissioning includes planning, decontamination, dismantling and materials management.[2]

Decommissioning is the final step in the lifecycle of a nuclear installation. It involves activities from shutdown and removal of nuclear material to the environmental restoration of the site.[3] The term decommissioning covers all measures carried out after a nuclear installation has been granted a decommissioning licence until nuclear regulatory supervision is no longer necessary. The aim is ideally to restore the natural initial state that existed before the construction of the nuclear power plant, the so-called greenfield status.[4]

Decommissioning includes all steps as described in the decommissioning plan, leading to the release of a nuclear facility from regulatory control. The decommissioning plan is fulfilled when the approved end state of the facility has been reached. Disposal facilities for radioactive waste are closed rather than decommissioned. The use of the term decommissioning implies that no further use of the facility (or part thereof) for its existing purpose is foreseen. Though decommissioning typically includes dismantling of the facility, it is not necessarily part of it as far as existing structures are reused after decommissioning and decontamination.[5] ,p. 49-50

From the owner's perspective, the ultimate aim of decommissioning is termination of the operating license, once he has given certainty that the radiation at the site is below the legal limits, which in the US is an annual exposure of 25 millirem in case of releasing of the site to the public for unrestricted use. The site will be dismantled to the point that it no longer requires measures for radiation protection. Once a facility is decommissioned no radioactive danger persists and it can be released from regulatory control.

The complete process usually takes about 20 to 30 years.[3] In the US, the decommissioning must be completed within 60 years of the plant ceasing operations, unless a longer time is necessary to protect public health and safety;[6] up to 50 years are for radioactive decay and 10 years to dismantle the facility.[7]

Steps in the decommissioning process

The decommissioning process encompasses:

pre-decommissioning
decommissioning

Decommissioning plan

Under supervision of the IAEA, a member state first developes a decommissioning plan to demonstrate the feasibility of decommissioning and assure that the associated costs are covered. At the final shutdown, a final decommissioning plan describes in detail how the decommissioning will take place, how the facility will be safely dismantled, ensuring radiation protection of the workers and the public, addressing environmental impacts, managing radioactive and non-radioactive materials, and termination of the regulatory authorization.[2] In the EU, decommissioning operations are overseen by Euratom. Member states are assisted by the European Commission.[3]

The progressive demolition of buildings and removal of radioactive material is potentially occupationally hazardous, expensive, time-intensive, and presents environmental risks that must be addressed to ensure radioactive materials are either transported elsewhere for storage or stored on-site in a safe manner.

Disposal of nuclear waste

Radioactive waste that remains after the decommissioning is either moved to an on-site storage facility where it still is under control of the plant owner, or moved to a dry cask storage or disposal facility at another location.[9] The problem of long-term disposal of nuclear waste is still unsolved. Pending the availability of geologic repository sites for long-term disposal, interim storage is necessary. As the planned Yucca Mountain nuclear waste repository – like elsewhere in the world – is controversial, on- or off-site storage in the US usually takes place in Independent Spent Fuel Storage Facilities (ISFSI's).[10]

In the UK, all eleven Magnox reactors are in decommissioning under responsibility of the NDA. The spent fuel was removed and transferred to the Sellafield site in Cumbria for reprocessing.[11] Facilities for "temporary" storage of nuclear waste – mainly 'Intermediate Level Waste' (ILW) – are in the UK called Interim Storage Facilities (ISF's).[12]

Environmental impact assessment

The decommission of a nuclear reactor can only take place after the appropriate licence has been granted pursuant to the relevant legislation. As part of the licensing procedure, various documents, reports and expert opinions have to be written and delivered to the competent authority, e.g. safety report, technical documents and an environmental impact assessment (EIA). In the European Union these documents are a precondition for granting such a licence is an opinion by the European Commission according to Article 37 of the Euratom Treaty.[13] On the basis of these general data, the Commission must be in a position to assess the exposure of reference groups of the population in the nearest neighbouring states.

Options

There are several options for decommissioning:

Immediate dismantling (DECON in the United States;)
Shortly after the permanent shutdown, the dismantling and/or decontamination of the facility begins. Equipment, structures, systems and components that contain radioactive material are removed and/or decontaminated to a level that permits the ending of regulatory control of the facility and its release, either for unrestricted use or with restrictions on its future use.[5] ,p. 50 The operating license is terminated.[6]

Deferred dismantling (SAFSTOR in the United States; "care and maintenance" (C&M) in the UK)
The final decommissioning is postponed for a longer period, usually 30 to 50 years. Often the non-nuclear part of the facility is dismantled and the fuel removed immediately. The radioactive part is maintained and monitored in a condition that allows the radioactivity to decay. Afterwards, the plant is dismantled and the property decontaminated to levels that permit release for unrestricted or restrict use.[5] In the US, the decommissioning must be completed within 60 years.[6] With deferred dismantling, costs are shifted to the future, but this entails the risk of rising expenditures for decades to come and changing rules.[14] Moreover, the site cannot be re-used until the decommissioning is finished, while there are no longer revenues from production.

Partial entombment
The US has introduced the so-called In Situ Decommissioning (ISD) closures. All aboveground structures are dismantled; all remaining belowground structures are entombed by grouting all spaces. Advantages are lower decommissioning costs and safer execution. Disadvantages are main components remaining undismantled and definitively inaccessible. The site has to be monitored indefinitely.

This method was implemented at the Savannah River Site in South Carolina for the closure of the P and R Reactors. With this method, the cost of decommissioning for each reactor was about $73 million. In comparison, the decommissioning of each reactor using traditional methods would have been an estimated $250 million. This resulted in a 71% decrease in cost.[15] Other examples are the Hallam nuclear reactor and the Experimental Breeder Reactor II.

Complete entombment
The facility will not be dismantled. Instead it is entombed and maintained indefinitely, and surveillance is continued until the entombed radioactive waste is decayed to a level permitting termination of the license and unrestricted release of the property. The licensee maintains the license previously issued.[16] This option is likely the only possible one in case of a nuclear disaster where the reactor is destroyed and dismantling is impossible or too dangerous. An example of full entombment is the Chernobyl reactor.

In IAEA terms, entombment is not considered an acceptable strategy for decommissioning a facility following a planned permanent shutdown, except under exceptional circumstances, such as a nuclear disaster. In that case, the structure has to be maintained and surveillance continued until the radioactive material is decayed to a level permitting termination of the licence and unrestricted release of the structure.[5] ,p. 50

Costs

The calculation of the total cost of decommissioning is challenging, as there are large differences between countries regarding inclusion of certain costs, such as on-site storage of fuel and radioactive waste from decommissioning, dismanting of non-radioactive buildings and structures, and transport and (final) disposal of radioactive waste.[17] ,p. 61

Moreover, estimates of future costs of deferred decommissioning are virtually impossible, due to the long periode, where inflation and rising costs are unpredictable. Nuclear decommissioning projects are characterized by high and highly variable costs, long schedule and a range of risks. Compared with non-nuclear decommissioning, additional costs are usually related with radiological hazards and safety & security requirements, but also with higher wages for required higher qualified personnel. Benchmarking, comparing projects in different countries, may be useful in estimating the cost of decommissioning. While, for instance, costs for spent fuel and high-level-waste management significantly impacts the budget and schedule of decommissioning projects, it is necessary to clarify which is the starting and the ending point of the decommissioning process.[18]

The effective decommissioning activities begin after all nuclear fuel has been removed from the plant areas that will be decommissioned and these activities form a critical component of pre-decommissioning operations, thus should be factored into the decommissioning plan. The chosen option – immediate or deferred decommissioning – impacts the overall costs. Many other factors also influence the cost. A 2018 KPMG article about decommissioning costs observes that many entities do not include the cost of managing spent nuclear fuel, removed from the plant areas that will be decommissioned (in the US routinely stored in ISFSIs).[19]

In 2004, in a meeting in Vienna, the International Atomic Energy Agency estimated the total cost for the decommissioning of all nuclear facilities.Decommissioning of all nuclear power reactors in the world would require US$187 billion; US$71 billion for fuel cycle facilities; less than US$7 billion for all research reactors; and US$640 billion for dismantling all military reactors for the production of weapons-grade plutonium, research fuel facilities, nuclear reprocessing chemical separation facilities, etc. The total cost to decommission the nuclear fission industry in the World (from 2001 to 2050) was estimated at US$1 trillion.[20] Market Watch estimated (2019) the global decommissioning costs in the nuclear sector in the range of US$1 billion to US$1.5 billion per 1,000-megawatt plant.

The huge costs of research and development for (geological) longterm disposal of nuclear waste are collectively defrayed by the taxpayers in different countries, not by the companies.

Decommissioning funds

The costs of decommissioning are to be covered by funds that are provided for in a decommissioning plan, which is part of the facility's initial authorization, before the start of the operations. In this way, it is ensured that there will be sufficient money to pay for the eventual decommissioning of the facility. This may for example be through saving in a trust fund or a guarantee from the parent company[21]

Switzerland has a central fund for decommissioning its five nuclear power reactors, and another one for disposal the nuclear waste.[22] Germany has also a state-owned fund for decommissioning of the plants and managing radioactive waste, for which the reactor owners have to pay. The UK Government (the taxpayers) will pay most of the costs for both nuclear decommissioning and existing waste.[23] The decommissioning of all Magnox reactors is entirely funded by the state.[24]

Since 2010, owners of new nuclear plants in the Netherlands are obliged to set up a decommissioning fund before construction is started.[25]

Underfunding

The economic costs of decommissioning will increase as moreassets reach the end of their life, but few operators have put aside sufficient funds.

In 2016 the European Commission assessed that European Union's nuclear decommissioning liabilities were seriously underfunded by about 118 billion euros, with only 150 billion euros of earmarked assets to cover 268 billion euros of expected decommissioning costs covering both dismantling of nuclear plants and storage of radioactive parts and waste.[26]

In Feb 2017, a committee of the French parliament warned that the state-controlled EDF has underestimated the costs for decommissioning. France had set aside only €23 billion for decommissioning and waste storage of its 58 reactors, which was less than a third of 74 billion in expected costs,[26] while the UK's NDA estimated that clean-up of UK's 17 nuclear sites will cost between €109-€250 billion. EDF estimated the total cost at €54 billion. According to the parliamentary commission, the clean-up of French reactors will take longer, be more challenging and cost much more than EDF anticipates. It said that EDF showed "excessive optimism" concerning the decommissioning.[23] EDF values some €350 million per reactor, whereas European operators count with between 900 million and 1.3 billion euros per reactor. The EDF's estimate was primarily based on the single historic example of the already dismantled Chooz A reactor. The committee argued that costs like restoration of the site, removal of spent fuel, taxes and insurance and social costs should be included.[27]

Similar concerns about underfunding exist in the United States, where the U.S. Nuclear Regulatory Commission has located apparent decommissioning funding assurance shortfalls and requested 18 power plants to address that issue.[28] The decommissioning cost of Small modular reactors is expected to be twice as much respect to Large Reactors.[29]

Examples by country

In France, decommissioning of Brennilis Nuclear Power Plant, a fairly small 70 MW power plant, already cost €480 million (20x the estimate costs) and is still pending after 20 years. Despite the huge investments in securing the dismantlement, radioactive elements such as plutonium, caesium-137 and cobalt-60 leaked out into the surrounding lake.[30] [31]

In the UK, the decommissioning of civil nuclear assets were estimated to be £99 to £232 billion (2020), earlier in 2005 under-estimated to be £20-40 billion. The Sellafield site (Calder Hall, Windscale and the reprocessing facility) alone accounts for most of the decommissioning cost and increase in cost;[32] as of 2015, the costs were estimated £53.2 billion.[24] In 2019, the estimate was even much higher: £97 billion.[33] A 2013 estimate by the United Kingdom's Nuclear Decommissioning Authority predicted costs of at least £100 billion to decommission the 19 existing United Kingdom nuclear sites.[34]

In Germany, decommissioning of Niederaichbach nuclear power plant, a 100 MW power plant, amounted to more than €143 million.

Lithuania has increased the prognosis of decommissioning costs from €2019 million in 2010 to €3376 million in 2015.[32]

United States

The decommissioning can only be completed after the on-site storage of nuclear waste has been ended. Under the 1982 Nuclear Waste Policy Act, a "Nuclear Waste Fund", funded by tax on electricity was established to build a geologic repository. On May 16, 2014, collection of the fee was suspended[35] after a complaint by owners and operators of nuclear power plants. By 2021, the Fund had a balance of more than $44 billion, including interest. Later, the Fund has been put back into the general fund and is being used for other purposes. As the plan for the Yucca Mountain nuclear waste repository has been canceled, DOE announced in 2021 the establishing of an interim repository for nuclear waste.[36]

Because the government has failed to establish a central repository, the federal government pays about half-a-billion dollars a year to the utilities as penalty, to compensate the cost of storage at more than 80 ISFSI sites in 35 states as of 2021. As of 2021, the government had paid $9 billion to utility companies for their interim storage costs, which may grow to $31 billion or more.[36]

Nuclear waste costed the American taxpayers through the Department of Energy (DOE) budget as of 2018 about $30 billion per year, $18 billion for  nuclear power and $12 billion for waste from nuclear weapons programs.[37]

KPMG estimated the total cost of decommissioning the US nuclear fleet as of 2018 to be greater than US$150 billion. About two-thirds can be attributed to costs for termination of the NRC operating licence; 25% to management of spent fuel; and 10% to site restoration.[19] The decommissioning of only the three uranium enrichment facilities would have an estimated cost (2004) of US$18.7 to 62 billion, with an additional US$2 to 6 billion for the dismantling of a large inventory of depleted uranium hexafluoride. A 2004 GAO report indicated the "costs will have exceeded revenues by $3.5 billion to $5.7 billion (in 2004 dollars)" for the 3 enrichment facilities slated for decommissioning.[38]

International collaboration

Organizations that promote the international sharing of information, knowledge, and experiences related to nuclear decommissioning include the International Atomic Energy Agency, the Organization for Economic Co-operation and Development's Nuclear Energy Agency and the European Atomic Energy Community. In addition, an online system called the Deactivation and Decommissioning Knowledge Management Information Tool was developed under the United States Department of Energy and made available to the international community to support the exchange of ideas and information. The goals of international collaboration in nuclear decommissioning are to reduce decommissioning costs and improve worker safety.

Decommissioning of ships, mobile reactors, and military reactors

Many warships and a few civil ships have used nuclear reactors for propulsion. Former Soviet and American warships have been taken out of service and their power plants removed or scuttled. Dismantling of Russian submarines and ships and American submarines and ships is ongoing. Russia has a fleet of nuclear-powered vessels in decommissioning, dumped in the Barents Sea. Estimated cost for the decommissioning of the two K-27 and K-159 submarines alone was €300 million (2019),[39] or $330 million.[40] Marine power plants are generally smaller than land-based electrical generating stations.

The biggest American military nuclear facility for the production of weapons-grade plutonium was Hanford site (in the State of Washington), now defueled, but in a slow and problematic process of decontamination, decommissioning, and demolition. There is "the canyon", a large structure for the chemical extraction of plutonium with the PUREX process. There are also many big containers and underground tanks with a solution of water, hydrocarbons and uranium-plutonium-neptunium-cesium-strontium (all highly radioactive). With all reactors now defueled, some were put in SAFSTOR (with their cooling towers demolished). Several reactors have been declared National Historic Landmarks.

List of inactive or decommissioned civil nuclear reactors

A wide range of nuclear facilities have been decommissioned so far. The number of decommissioned nuclear reactors out of the List of nuclear reactors is small. As May 2022, about 700 nuclear reactors have been retired from operation in several early and intermediate stages (cold shut-down, defueling, SAFSTOR, internal demolition), but only about 25 have been taken to fully "greenfield status".[41] Many of these sites still host spent nuclear fuel in the form of dry casks embedded in concrete filled steel drums.[42]

As of 2017, most nuclear plants operating in the United States were designed for a life of about 30–40 years[43] and are licensed to operate for 40 years by the US Nuclear Regulatory Commission.[44] [45] As of 2020, the average age of these reactors was about 39 years.[45] Many plants are coming to the end of their licensing period and if their licenses are not renewed, they must go through a decontamination and decommissioning process.[43] [46] [41]

Generally are not included the costs of storage of nuclear waste, including spent fuel, and maintenance of the storage facility, pending the realization of repository sites for long-term disposal[17] ,p. 246 (in the US Independent Spent Fuel Storage Installations (ISFSI's).[9] Thus many entities do not include the cost of managing spent nuclear fuel, removed from the plant areas that will be decommissioned.[19] There are, however, large differences between countries regarding inclusion of certain costs, such as on-site storage of fuel and radioactive waste from decommissioning, dismanting of non-radioactive buildings and structures, and transport and (final) disposal of radioactive waste.[17] ,p. 61
The year of costs may refer to the value corrected for exchange rates and inflation until that year (e.g. 2020-dollars).

The stated power in the list is preferably given in design net capacity (reference unit power) in MWe, similar to the List of commercial nuclear reactors.

+Dismantled or inactive civil nuclear reactors[47] [48] [49]
CountryLocationReactor typeOperative lifeDecommissioningDecommissioning costs
AustriaZwentendorfBWR 723 MWeNever activated due to referendum in 1978[50] Now a technics museum
BelgiumPWR (BR-3)1962–1987
(25 years)
2002- [51] Still unknown
BulgariaKozloduy
Units 1, 2, 3, 4[52]
PWR VVER-440
(4 x 408 MWe)
Reactors 1,2 closed in 2003,
reactors 3,4 closed in 2006
OngoingStill unknown
CanadaGentilly
Unit 1
(Québec)
CANDU-BWR
250 MWe
180 days
(between 1966 and 1973)
Ongoing"Static state" since 1986[53] [54] [55] Still unknownstage two:
$25 million
CanadaGentilly-2(Québec)CANDU-BWR
675 MWe
October 1, 1983 to December 28, 2012 Ongoing$1.8 billion (estimated) [56]
Pickering NGS
Units A2, A3
(Ontario)
CANDU-PWR
8 x 542 MWe
30 years
(from 1974 to 2004)
OngoingTwo units currently in "cold standby"
Decommissioning to begin in 2020[57] [58]
Still unknowncalculated: $270–430/kWe
China[59] Beijing (CIAE)HWWR 10 MWe (multipurpose Heavy Water Experimental Reactor for the production of plutonium and tritium)49 years
(1958–2007)
SAFSTOR until 2027Still unknownproposed: $6 million for dismantling
$5 million for fuel remotion
France[60] BrennilisHWGCR 70 MWe12 years
(1967–1979)
OngoingPhase 3
(fire during decommissioning in 2015) [61]
Still unknownalready spent €480 million
(20 times the forecasted amount) [62] [63]
FranceBugey
Unit 1
UNGG
Gas cooled, graphite moderator
1972–1994OngoingpostponedStill unknown
FranceChinon
Units 1, 2, 3
Gas-graphite
(1973–1990)
OngoingpostponedStill unknown
FranceChooz-APWR 300 MW24 years
(1967–1991)
2007-OngoingDeferred dismantling;[64]
dismantling to finish by 2025
Still unknown
FranceSaint-LaurentGas-graphite1969–1992OngoingPostponedStill unknown
FranceRapsodie at
Cadarache
Experimental
Fast breeder nuclear reactor
(sodium-cooled)
40 MWe
15 years
(1967–1983)
1983- Ongoing
dismantling planned by 2005; general decontamination planned by 2020
[65]
Still unknown
FrancePhénix at
Marcoule
Experimental
Fast breeder nuclear reactor
(sodium-cooled)
233 MWe
36 years
(1973–2009)[66]
2005- Ongoing
non-nuclear dismantling finished in 2011; finalising expected between 2031 and 2043.[67]
Still unknown
FranceSuperphénix at
Creys-Malville
Fast breeder nuclear reactor
(sodium-cooled)
11 years
(1985–1996)[68]
Ongoing1) Defuelled
2) Extraction of Sodium[69]
Pipe cutting with a robot [70] [71]
Still unknown
East GermanyGreifswald
Units 1, 2, 3, 4, 5, 6
VVER-440
5 x 408 MWe
Reactors 1–5 closed in 1989/1990,
reactor 6: finished but never operated

OngoingImmediate
dismantling
(underwater cutting)
Still unknown
East GermanyRheinsberg
Unit 1
VVER-210
70–80 MWe
24 years
(1966–1990)
OngoingIn dismantling
since 1996
Safstor (underwater cutting)
Still unknown
East GermanyStendal
Units 1, 2, 3, 4
VVER-1000
(4 x 1000 MWe)
Never activated
(1st reactor 85% completed)
Not radioactive
(Cooling towers demolished;
Structure in exhibition
inside an
industrial park)
Still unknown
West GermanyGundremmingen-ABWR
250 MWe

11 years
OngoingImmediate
dismantling
pilot project
(underwater cutting)
Still unknown
India[72] Rajasthan Atomic Power Station
Unit 1
(Rajasthan)
PHWR 100 MWe (similar to CANDU)44 years
(1970–2014)
OngoingStill unknown
Italy[73] CaorsoBWR
840 MWe[74] [75]
3 years
(1978 – Closed in 1987 after referendum in 1986)
SAFSTOR

30 years
(internal demolition)

€450 million (dismantling)
+ €300 million (fuel reprocessing)[76] [77] [78] [79]
ItalyGarigliano (Caserta)BWR
150 MWe[80]
Closed on March 1, 1982OngoingStill unknown
ItalyLatina (Foce Verde)Magnox
210 MWe Gas-graphite[81]
24 years
(1962 – Closed in 1986 after referendum)
SAFSTOR

30 years
(internal demolition)

Still unknown
ItalyTrino VercellesePWR Westinghouse,
270 MWe[82]

(Closed in 1986 after referendum)
SAFSTOR

30 years
(internal demolition)

Still unknown
JapanFukushima Dai-ichi
Unit 1
BWR 439 MWeNovember 17, 1970 – March 11, 2011OngoingSince 2011 Tōhoku earthquake and tsunami of March 11
[83] [84] [85] Hydrogen explosion (INES 7)[86] [87]
Estimated at ¥10 trillion (US$100 billion) for decontaminating Fukushima and dismantling all reactors in Japan and considering long time damage to environment and economy, including agriculture, cattle breeding, fishery, water potabilization, tourism, loss of reputation in the world
(without considering further health care spending and reduction of life expectancy).[88]
JapanFukushima Dai-ichi
Unit 2
BWR 760 MWeDecember 24, 1973 – March 11, 2011OngoingStill unknown
JapanFukushima Dai-ichi
Unit 3
BWR 760 MWeOctober 26, 1974 – March 11, 2011OngoingStill unknown
JapanFukushima Dai-ichi
Unit 4
BWR 760 MWeFebruary 24, 1978 – March 11, 2011OngoingSince March 11, 2011 Reactor defueled when tsunami hit
Damage to spent fuel cooling-pool
(INES 4)
Still unknown
JapanFukushima Dai-ichi
Unit 5
BWR 760 MWeSeptember 22, 1977 – March 11, 2011Planned decommissioning
Cold shutdown since March 11, 2011
Still unknown
JapanFukushima Dai-ichi
Unit 6
BWR 1067 MWeMay 4, 1979 – March 11, 2011Planned decommissioning
Cold shutdown since March 11, 2011
Still unknown
JapanFukushima Daini
Unit 1[89]
BWR 1067 MWeJuly 31, 1981 – 11 March 2011Planned decommissioning
Cold shutdown since March 11, 2011
[90]
Still unknown
JapanFugen[91] Advanced thermal reactor
(MOX fuel core,
heavy water-BWR)
165 MWe
1979–2003OngoingSince March 11, 2011 Cold shutdown [92] [93] [94] Still unknown
JapanTokai
Unit 1
Magnox (GCR) 160 MWe 1966–1998deferred dismantling: 10 years[95] [96]
then decon
until 2018

¥93 billion[97]
(€660 million of 2003)
North KoreaYongbyonMagnox-type
(reactor for the production of nuclear weapons through PUREX treatment)
1985–2005
(20 years)
Deactivated after a treaty[98]
deferred dismantling; cooling tower dismantledStill unknown
NetherlandsDodewaardBWR Westinghouse
55 MWe
1968–1997
(28 years)
2002-2100+
safe-storage; start dismantling in 2045;
separate interim storage of high-level waste at COVRA for 100 years or longer[99] ,p. 171
estimated cost €134 million (1999); €180 million (2016),p. 174
RussiaMayak[100]
(Chelyabinsk-65)
PUREX plant for
uranium enrichment
1946–1956
(10 years)
OngoingStill unknown
RussiaSeversk[101]
(Tomsk-7)
Three plutonium reactors
Plant for uranium enrichment
Two fast-breeder reactors closed (of three),
after disarmaments agreements with USA in 2003.[102]
OngoingStill unknown
SlovakiaJaslovské Bohunice
Units 1, 2[103] [104]
VVER 440/230
2 X 440 MWe
(1978–2006)
(1980–2008)
OngoingStill unknown
Spain[105] José CabreraPWR
1 x 160 MWe
(Westinghouse)
38 years
(1968–2006)
2010-2023[106] [107] [108] Still unknown
Estimation increased from 135 mln in 2003 to 217.8 mln in 2014[109]
SpainSanta María de Garoña
(Burgos)
BWR/3
1 x 466 MWe
(by Dutch RDM)
1966–2013OngoingDefueledStill unknown
SpainVandellós
Unit 1
UNGG
480 MWe
(gas-graphite)
18 years
Incident:
fire in a turbogenerator
(1989)
SAFSTOR

30 years
(internal demolition)

Still unknownPhases 1 and 2: €93 million
SwedenBarsebäck
Units 1, 2
BWR 2 x 615 MW Reactor 1: 24 years 1975–1999
Reactor 2: 28 years 1977 – 2005
SAFSTOR

demolition will begin in 2020

The Swedish Radiation Safety Authority has assessed that the costs for decommissioning and final disposal for the Swedish nuclear power industry may be underestimated by SKB by at least 11 billion Swedish kronor ($1.63 billion)[110]
SwedenOskarshamnUnits 1, 2BWR 1 x 473 MWBWR 1 x 638 MW Reactor 1: 45 years 1972–2017
Reactor 2: 41 years 1975 – 2016
OngoingStill unknown
SwedenRinghalsUnits 1, 2BWR 1 x 881 MWPWR 1 x 904 MW Reactor 1: 44 years 1976–2020
Reactor 2: 44 years 1975 – 2019
OngoingStill unknown
Switzerland[111] DIORITMWe CO2-Gas-heavy water
(experimental)
Decommissioned[112] Still unknown
SwitzerlandLUCENS8,3 MWe CO22-Gas-heavy water
(experimental)
(1962–1969)
Incident: fire in 1969
Decommissioned[113] Still unknown
SwitzerlandSAPHIR0,01–0,1 MWe
(Light water pool)
39 years
(1955–1994)
(Experimental demonstrator)
DecommissionedStill unknown
UkraineChernobyl-4
(110 km
from Kiev)
RBMK-1000
1000 MWe
hydrogen explosion,
then graphite fire (1986)

(INES 7)
OngoingENTOMBMENT
(armed concrete "sarcophagus")
Still unknown
Future: riding sarcophagus in steel[114]
LocationReactor typeOperative lifeDecommissioningDecommissioning
costs
BerkeleyMagnox
(2 x 138 MWe)
1962–1989
(27 years)
save storageStill unknown
BradwellMagnox
2 x 121 MWe
1962–2002
(40 years)
2002-2083 or later
save storage[115]
Still unknown
Calderhall
Sellafield
Magnox
4 x 60 MWe
1956-2003
(44–46 years)[116] [117]
save storage[118] Still unknown
ChapelcrossMagnox
4 x 60 MWe
("sister reactor" to Calderhall)
1959–2004
(45 years)
save storage Still unknown
Dounreay

DMTR
(Research facility of UKAEA)

Fast-neutron reactor1958–1969OngoingDemolition contract awarded December 2018[119] Still unknown
Dounreay

DFR
(Research facility of UKAEA)

Loop-type fast breeder.14 MWe.[120] 1959–1977Ongoing[121] Still unknown
Dounreay

PFR
(Research facility of UKAEA)

Pool-type fast breeder cooled by liquid sodium, fueled with MOX.250 MWe.[122] 1974–1994
(with average 26.9% load)[123]
Delays and reliability problems before reaching full power.[124]
Remotely operated robot 'Reactorsaurus' will be sent in to decontaminate equipment as too dangerous a task for a human.[125] Control panel has been earmarked for an exhibition at London Science Museum (2016). [126] Still unknown
SGHWR
92 MWe
1968 to 1990
(22 years)
1995-
dismantled;
off-site storage of waste
[127]
Still unknown

[128] [129]

LocationReactor typeOperative lifeDecommissioningDecommissioning
costs
Connecticut Yankee
Connecticut
PWR
619 MWe
1968–1996
(28 years)
1998-2007
DECON; on-site ISFSI waste storage[130]
931 mln;
additional $575.5 mln in court awarded from DOE for waste storage at 3 plants[131]
Crystal River 3
Florida
PWR
825 MWe
1977–2009
(32 years)
2013-2037 (estimated)
DECON; on-site
ISFSI waste storage[132]
In 2013 estimated ~$1,2 bln[133]
Dresden
Unit 1
(Illinois)
BWR
207 MWe
1960–1978
(18 years)
Defueled in safety in 1998
now in SAFSTOR[134]
Fuel in on-site dry-casks.[135]
Still unknown
Fort St. Vrain
(Colorado)
HTGR
(helium-graphite)
330 MWe
1979–1989
(10 years)[136]
1989-1992
(3 years)
dismantled; off-site ISFSI waste storage;
replaced by conventional station[137]
$283 million[138]
Pacific Gas & Electric –
Humboldt Bay
Unit 3
BWR 63 MWe1963–1976
(13 years)[139]
1988-2021
(33 years)
License terminated in Oct 2021;
site released for unrestricted use;
New license for on-site storage facility for the spent fuel.
[140]
Unknown

Fund for $53.3 million required for decommissioning of storage alone.
Maine YankeePWR
860 MWe
24 years
(closed in 1996)
DECON; on-site ISFSI waste storage[141] [142] $635 million[143]
Piqua NGS
(Ohio)
OCM (Organically Cooled/Moderated) reactor 46 MWe[144] 2 years
(closed in 1966)
ENTOMB
(coolant design inadequate for neutron flux)
Still unknown
Rancho Seco NGS[145]
(California)
PWR 913 MWe12 years
(Closed after a referendum in 1989)
SAFSTOR

5–10 years
completed in 2009 [146]
Fuel in insite long-term dry-cask storage

$538.1 million [147]
San Onofre NGS Unit 1
(California)
1967–1992
(25 years)[148]
1993-2032 (estimated)
dismantled; on-site ISFSI waste storage for whole plant[149]
Still unknown
San Onofre NGS Units 2, 3
(California)[150]
PWR
1070 MWe
1080 MWe
Unit 2: 1983–2013
Unit 3: 1984–2013
In 2011, Edison finished replacing the steam generators in both reactors with improved Mitsubishi ones, but the new design had several problems, cracked, causing leaks and vibrations.[151]
in defueling.Permanent shutdown – DECON
soon defueling[152]
Still unknown2014 cost forecast:
$3.926 billion[153]
to $4.4 billion[154]
Shippingport
(Pennsylvania)
BWR 60 MWe25 years
(closed in 1989)
Decon completed
dismantled in 5 years
(first small experimental reactor)
$98.4 million[155]
Three Mile Island Nuclear Generating Station
Unit 2
(Pennsylvania)
PWR 913 MWe1978–1979
Core meltdown incident
Post-Defuelling
Phase 2 (1979)
$805 million
(estimated)[156]
Trojan
(Oregon)
PWR 1,180 MWe16 years
(Closed in 1993 because of proximity to seismic fault)
SAFSTOR
(cooling tower demolished in 2006)
[157]
Vermont YankeeBWR 620 MWe
(General Electric)
1972–2014
(42 years)
Ongoing
2015–
~$1.24 billion
Yankee Rowe
(Massachusetts)
PWR 180 MWe1961–1991
(30 years)
Construction cost was $45 million
completed in 2007[158]
on-site ISFSI waste storage
$608 million (See main article)
Zion
Units 1, 2
(Illinois)
2 x PWR 1040 MWe
(Westinghouse)
1973/1974–1998
(25 years)
1998-2020 [159]
after SAFSTOR full dismantling;
New on-site for spent fuel storage
Costs for SAFSTOR unknown;
for dismantling & decontamination estimated in 2010 $1 billion
+ demolition city fees millions;[160]
for remaining waste unknown

See also

External links

Notes and References

  1. https://www-pub.iaea.org/MTCD/publications/PDF/rwmst2/IAEA-WMDB-ST-2-Part-2.pdf Decommissioning of nuclear facilities
  2. https://www.iaea.org/topics/decommissioning Decommissioning of nuclear installations.
  3. https://energy.ec.europa.eu/topics/nuclear-energy/decommissioning-nuclear-facilities_en Decommissioning of nuclear facilities.
  4. https://www.grs.de/en/research-and-assessment/decommissioning-dismantling Decommissioning & dismantling.
  5. https://www-pub.iaea.org/MTCD/Publications/PDF/IAEA-NSS-GLOweb.pdf IAEA Nuclear Safety and Security Glossary
  6. https://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html Backgrounder on Decommissioning Nuclear Power Plants.
  7. https://www.mass.gov/doc/meeting-exhibit/download Overview of Reactor Decommissioning
  8. https://www.epri.com/research/products/1003426 Summary of License Termination Plan Submittals by Three Nuclear Power Plants
  9. https://www.nrc.gov/waste/spent-fuel-storage.html Storage of Spent Nuclear Fuel
  10. https://www.nrc.gov/reading-rm/basic-ref/glossary/independent-spent-fuel-storage-installation-isfsi.html Independent spent fuel storage installation (ISFSI)
  11. https://web.archive.org/web/20170316204352/https://nda.blog.gov.uk/2017/01/13/radiological-hazard-on-all-magnox-nuclear-sites-across-uk-set-to-reduce-by-99/ Radiological hazard on all Magnox nuclear sites across UK set to reduce by 99%.
  12. https://newsnet.scot/news-analysis/nuclear-decommissioning-chapelcross-a-timeline/ Nuclear Decommissioning: Chapelcross a timeline.
  13. Web site: Heuel-Fabianek, B., Kümmerle, E., Möllmann-Coers, M., Lennartz, R. (2008): The relevance of Article 37 of the Euratom Treaty for the dismantling of nuclear reactors. atw – International Journal for Nuclear Power 6/2008. https://web.archive.org/web/20080911042258/http://www.fz-juelich.de/portal/lw_resource/datapool/__pages/pdp_1407/atw-2008-06_HEUEL-FABIANEK.pdf. dead. September 11, 2008.
  14. https://www.reutersevents.com/nuclear/us-utilitys-deferred-reactor-clean-shows-cost-pressure-early-closures US utility’s deferred reactor clean-up shows cost pressure on early closures.
  15. https://www.dndkm.org/DOEKMDocuments/BestPractices/26-EFCOG%20Best%20Practice%20-%20SRS%20P%20and%20R%20Reactor%20Basins%20ISD%20Final.pdf SRS P and R Reactor Disassembly Basin In Situ Decommissioning.
  16. https://www.nrc.gov/reading-rm/basic-ref/glossary/entomb.html ENTOMB
  17. https://www.oecd-nea.org/jcms/pl_14910 Costs of decommissioning nuclear power plants
  18. http://eprints.whiterose.ac.uk/117185/1/Copy%20to%20deposit.pdf How benchmarking can support the selection, planning and delivery of nuclear decommissioning projects
  19. https://assets.kpmg.com/content/dam/kpmg/ca/pdf/2018/06/ca-decommissioning-nuclear.pdf Decommissioning nuclear – Understanding the reporting obligations
  20. Web site: Status of Decommissioning of Nuclear Facilities around the World.
  21. Backgrounder on Decommissioning Nuclear Power Plants. U.S.NRC:
    "Before a nuclear power plant begins operations, the licensee must establish or obtain a financial mechanism – such as a trust fund or a guarantee from its parent company – to ensure there will be sufficient money to pay for the ultimate decommissioning of the facility."
    Decommissioning of nuclear installations. IAEA:
    "As part of a facility’s initial authorization, a decommissioning plan is developed that demonstrates the feasibility of decommissioning and provides assurance that provisions are in place to cover the associated costs."
  22. https://www.neimagazine.com/news/newsrepository-delay-reduces-swiss-npps-decommissioning-costs-5703898 Repository delay reduces Swiss NPPs' decommissioning costs.
  23. https://theecologist.org/2017/mar/16/edf-facing-bankruptcy-decommissioning-time-frances-ageing-nuclear-fleet-nears EDF facing bankruptcy as decommissioning time for France's ageing nuclear fleet nears.
  24. Table of the cost of decommissioning of the UK Magnox reactors, entirely funded by the state (in 2015-pounds): Nuclear Decommissioning Authority: Strategy, Appendix B, p. 129. March 2016.Via
  25. https://www.volkskrant.nl/nieuws-achtergrond/geld-tekort-voor-sloop-dodewaard~b14aded7/ Geld tekort voor sloop Dodewaard .
  26. https://www.reuters.com/article/uk-europe-nuclear-idUKKCN0VP2KN EU short of 118 billion euros in nuclear decommissioning funds.
  27. https://www.reutersevents.com/nuclear/frances-lower-cost-decommissioning-plan-rests-chooz-reactor-learnings France's lower-cost decommissioning plan rests on Chooz A reactor learnings
  28. Web site: NRC Requests Plans from 18 Nuclear Power Plants to Address Apparent Decommissioning Funding Assurance Shortfalls . Nuclear Regulatory Commission . June 19, 2009 . 2014-12-30.
  29. Locatelli. Giorgio. Mancini. Mauro. July 2, 2010. Competitiveness of Small-Medium, New Generation Reactors: A Comparative Study on Decommissioning. Journal of Engineering for Gas Turbines and Power. 132. 10. 102906. 10.1115/1.4000613. 0742-4795. 11311/565407. free.
  30. Web site: Brennilis.. November 29, 2007. Le Telegramme. 26 October 2021. 18 May 2022. https://web.archive.org/web/20220518233031/https://www.letelegramme.fr/ar/viewarticle1024.php?aaaammjj=20071129&article=20071129-2063574&type=ar. dead.
  31. Web site: Ouest-France: "Brennilis : EDF se fait taper sur les doigts". https://web.archive.org/web/20110501102123/http://www.mayennesurvoltee.com/Mayenne_survoltee/Actualites/actua_nation/actua_brennilis_12072007/BRENNILIS.jpg. dead. May 1, 2011.
  32. 2020-09-01. Developing policies for the end-of-life of energy infrastructure: Coming to terms with the challenges of decommissioning. Energy Policy. en. 144. 111677. 10.1016/j.enpol.2020.111677. 0301-4215. free. Invernizzi. Diletta Colette. Locatelli. Giorgio. Velenturf. Anne. Love. Peter ED.. Purnell. Phil. Brookes. Naomi J.. 11311/1204791. free. Free access.
  33. https://www.gov.uk/government/publications/nuclear-provision-explaining-the-cost-of-cleaning-up-britains-nuclear-legacy/nuclear-provision-explaining-the-cost-of-cleaning-up-britains-nuclear-legacy#latest-estimate Nuclear Provision: the cost of cleaning up Britain’s historic nuclear sites.
  34. Nuclear Decommissioning Authority: Managing risk at Sellafield . February 4, 2013. London: The Stationery Office Limited. House of Commons Committee of Public Accounts .
  35. United States Senate Congressional Record Vol. 163, No. 90 (Senate - May 24, 2017), United States Reports (Government).
  36. https://www.cnbc.com/2021/12/18/nuclear-waste-why-theres-no-permanent-nuclear-waste-dump-in-us.html The feds have collected more than $44 billion for a permanent nuclear waste dump — here’s why we still don’t have one.
  37. https://earth.stanford.edu/news/steep-costs-nuclear-waste-us The steep costs of nuclear waste in the U.S.
  38. United States General Accounting Office.URANIUM ENRICHMENT: Decontamination and Decommissioning Fund Is Insufficient to Cover Cleanup Costs., United States Reports (Government).
  39. https://bellona.org/news/nuclear-issues/2020-03-major-european-bank-could-help-russia-lift-its-sunken-nuclear-submarines Major European bank could help Russia lift its sunken nuclear submarines.
  40. https://www.bbc.com/future/article/20200901-the-radioactive-risk-of-sunken-nuclear-soviet-submarines Russia’s ‘slow-motion Chernobyl’ at sea.
  41. Web site: Nuclear Decommissioning: Decommission nuclear facilities - World Nuclear Association. www.world-nuclear.org.
  42. https://infcis.iaea.org/NFCIS/Facilities/5?Country=All&Status=In%20operation&Type=22&Scale=All&SearchText=Search%20Facilities List of Nuclear Fuel Cycle Facilities
  43. Web site: Nuclear Decommissioning: Decommission nuclear facilities . World-nuclear.org . 2013-09-06 . 19 October 2015 . https://web.archive.org/web/20151019172620/http://www.world-nuclear.org/info/Nuclear-Fuel-Cycle/Nuclear-Wastes/Decommissioning-Nuclear-Facilities/ . dead .
  44. https://www.nrc.gov/info-finder/decommissioning/ U.S. Nuclear Regulatory Commission:Sites Undergoing Decommissioning (by Location or Name)
  45. Web site: How old are U.S. nuclear power plants and when was the last one built? – FAQ – . U.S. Energy Information Administration (EIA) . 2021-05-17.
  46. Web site: NRC: Decommissioning of Nuclear Facilities . NRC . June 28, 2013 . 2013-09-06.
  47. World Nuclear Association Decommissioning Nuclear Facilities published by www.world-nuclear.org (Association of nuclear reactors builders), March 2017
  48. NRC Locations of Power Reactor Sites Undergoing Decommissioning
  49. Office of Scientific and Technical Information (OSTI) Appendix A – A Summary of the Shutdown and Decommissioning Experience for Nuclear Power Plants in the United States and the Russian Federation. Appendix B – A Summary of the Regulatory Environment for the Shutdown and Decommissioning of Nuclear Power Plants in the United States and the Russian Federation. Appendix C – Recommended Outlines for Decommissioning Documentation
  50. Web site: sustainabilityinstitute.org is registered with Pair Domains. https://web.archive.org/web/20110511102256/http://www.sustainabilityinstitute.org/dhm_archive/index.php?display_article=vn166zwented. dead. May 11, 2011. Sustainability Institute.
  51. https://web.archive.org/web/20190401060959/https://science.sckcen.be/en/Facilities/BR3 Belgian Reactor 3 - BR3
  52. Web site: Nuclear Power in Bulgaria | Bulgarian nuclear energy - World Nuclear Association. www.world-nuclear.org.
  53. Web site: Taking Canada's Gentilly-1 to a "static state (by Balarko Gupta). https://web.archive.org/web/20110429052517/http://www.iaea.org/Publications/Magazines/Bulletin/Bull274/27405092729.pdf. dead. April 29, 2011. IAEA.
  54. Web site: ASCE: Gentilly-1 a study in nuclear decommission. https://web.archive.org/web/20110427010401/http://cedb.asce.org/cgi/WWWdisplay.cgi?8801395. dead. April 27, 2011.
  55. http://www.ccnr.org/gentilly_hq.html A Chernobyl in Québec?
  56. https://www.cbc.ca/news/canada/montreal/quebec-nuclear-reactor-shutdown-will-cost-1-8-billion-1.1159201 Quebec nuclear reactor shutdown will cost $1.8 billion CBC news. October 03, 2012
  57. http://www.opg.com/power/nuclear/pickering/ Ontario Power Generation: Pickering Nuclear Power
  58. Web site: Relicensing Pickering Nuclear Generating Station. FAIREWINDS. 21 January 2014. 13 February 2014. https://web.archive.org/web/20140213015832/http://fairewinds.org/reports/relicensing-analysis-pickering-ngs-fairewinds-associates. dead.
  59. Web site: IAEA: Decommissioning in China.
  60. Web site: Nuclear Power in France | French Nuclear Energy - World Nuclear Association. www.world-nuclear.org.
  61. http://7seizh.info/2015/09/23/brennilis-incendie-a-centrale-nucleaire-plan-durgence-declenche Brennilis: Incendie À La Centrale Nucléaire, Le Plan D’urgence Déclenché
  62. Web site: The global state of nuclear decommissioning: costs rising, funds shrinking, and industry looks to escape liability by decades of delay.
  63. BRENNILIS, LABORATOIRE DU DÉMANTÈLEMENT. September 1, 2011. www.usinenouvelle.com.
  64. Web site: WM2009 Conference, March 1–5, 2009 Phoenix, AZ – International Cooperation for the Dismantling of Chooz A Reactor Pressure Vessel – 9087.
  65. https://web.archive.org/web/20150402132154if_/http://www.iaea.org/OurWork/ST/NE/NEFW/CEG/documents/ws102003_michaille1-e.pdf Decommissioning of LMRs in France
  66. Web site: Phenix Decommissioning Project - Overview. Michel. Soldaini. January 15, 2008. 21144200. www.osti.gov.
  67. https://archive.wikiwix.com/cache/display2.php?url=http%3A%2F%2Fwww.visiatome.fr%2FLocal%2Fvisiatome%2Ffiles%2F566%2FDemantelement.de.la.centrale.Phenix.a.Marcoule.par.Jean-Paul.Grandjean.le.14.mars.2013.pdf Demantelement de la centrale Phenix
  68. Web site: Superphénix; still more problems ahead | Wise International. www.wiseinternational.org.
  69. Web site: ANS / Store / Journals / Electronic Articles / Nuclear Technology / Volume 150 / Number 1 / Recent Sodium Technology Development for the Decommissioning of the Rapsodie and Superphénix Reactors and the Management of Sodium Wastes . July 1, 2015 . July 2, 2015 . https://web.archive.org/web/20150702041334/http://www.ans.org/store/j_3608 . dead .
  70. http://www-pub.iaea.org/MTCD/publications/PDF/te_1633_web.pdf Decommissioning of Fast Reactors after Sodium Draining
  71. Web site: Decommissioning of nuclear installations: World first for the robot CHARLI - 2013 - News . July 1, 2015 . September 26, 2015 . https://web.archive.org/web/20150926041336/http://www.uk.areva.com/EN/home-824/news2013decommissioning-of-nuclear-installations-world-first-for-the-robot-charli.html . dead .
  72. Web site: INDIA – CISED: Economics of Nuclear Power Heavy Water Reactors . January 12, 2009 . https://web.archive.org/web/20090225155112/http://www.cised.org/EconomicsofNuclearPowerfromHeavyWaterReactors.pdf . February 25, 2009 . dead .
  73. Web site: Country Nuclear Waste Profile - NEWMDB - IAEA. newmdb.iaea.org.
  74. http://www.zonanucleare.com/questione_scorie_italia/inventario_rifiuti_radioattivi/indice_centrale_caorso.htm Zona Nucleare – La centrale nucleare in fase di smantellamento ex-ENEL di Caorso
  75. Web site: Il Fiume Po: La Centrale Nucleare di Caorso. https://web.archive.org/web/20110501143001/http://www.ilfiumepo.net/it/caorso.html. dead. May 1, 2011.
  76. Web site: Il decommissioning della centrale nucleare di Caorso . https://web.archive.org/web/20150503052119/http://www.tecnosophia.org/documenti/Articoli/SessioneI/Guerzoni.pdf . 2015-05-03 . 6 . Renzo Guerzoni . Sogin.
  77. Web site: Via libera allo smantellamento della centrale di Caorso . July 26, 2011 . https://web.archive.org/web/20120328054629/http://energia24club.it/articoli/0,1254,51_ART_93751,00.html . March 28, 2012 . dead .
  78. Web site: Accordo tra la SOGIN e la Sudsvik svedese. https://web.archive.org/web/20120328054706/http://www.dire.it/caorso_accordo.php?menu=3&cont=22745&lingua=it. dead. March 28, 2012.
  79. Web site: PER CAORSO UN ADDIO LUNGO MEZZO SECOLO PIANO ENEL PER SMANTELLARE LA C - la Repubblica.it. Archivio - la Repubblica.it.
  80. http://www.zonanucleare.com/questione_scorie_italia/inventario_rifiuti_radioattivi/indice_centrale_garigliano.htm Zona Nucleare – La centrale nucleare in fase di smantellamento ex-ENEL di Garigliano
  81. http://www.zonanucleare.com/questione_scorie_italia/inventario_rifiuti_radioattivi/indice_centrale_latina.htm Zona Nucleare – La centrale nucleare in fase di smantellamento ex-ENEL di Foce Verde
  82. http://www.zonanucleare.com/questione_scorie_italia/inventario_rifiuti_radioattivi/indice_centrale_trino_vercellese.htm Zona Nucleare – La centrale nucleare in fase di smantellamento ex-ENEL di Trino Vercellese
  83. Web site: Fukushima Nuclear Accident Update Log. June 2, 2011. www.iaea.org.
  84. News: 3 nuclear reactors melted down after quake, Japan confirms . CNN. June 7, 2011. July 13, 2011.
  85. Web site: 'Melt-through' at Fukushima? / Govt report to IAEA suggests situation worse than meltdown . Yomiuri . June 8, 2011 . June 8, 2011 . June 7, 2011 . https://web.archive.org/web/20110607225045/http://www.yomiuri.co.jp/dy/national/T110607005367.htm . dead .
  86. Web site: Japan to raise Fukushima crisis level to worst . April 12, 2011 . dead . https://web.archive.org/web/20110412003205/http://www3.nhk.or.jp/daily/english/12_05.html . April 12, 2011 . mdy-all .
  87. News: Japan raises nuclear crisis to same level as Chernobyl . Reuters . April 12, 2011.
  88. http://www.japantimes.co.jp The Japan Times
  89. Web site: The Other Fukushima Nuclear Power Plant.
  90. Web site: Fukushima Daini Nuclear Power Station all shutdown | NextBigFuture.com. March 12, 2011.
  91. Web site: Fugen NPP official website . March 10, 2017 . https://web.archive.org/web/20051101085946/http://www.jnc.go.jp/zfugen/ . November 1, 2005 . dead .
  92. Web site: Fugen Decommissioning Engineering Center. https://web.archive.org/web/20110523143824/http://www.jaea.go.jp/english/04/turuga/info/rd/rd.html. dead. May 23, 2011.
  93. Web site: 原発解体~世界の現場は警告する~|NHKスペシャル(文字おこし)(1) : 座間宮ガレイの世界. blog.livedoor.jp.
  94. Web site: Deconstruction of Nuclear power plant. vimeo.com.
  95. http://www.iaea.org/inisnkm/nkm/aws/htgr/abstracts/abst_29059902.html Article in IAEA-TECDOC—1043: Permanent cessation of Tokai power plant's operation
  96. http://sciencelinks.jp/j-east/article/200520/000020052005A0825407.php Science Links Japan: Progression of decommissioning of Tokai power plant. First case of power reactor in Japan
  97. https://books.google.com/books?id=W7OZkUOOVD0C&pg=PA118&lpg=PA118&dq=Decommissioning+cost+of+Tokai#PPA1,M1 Organisation for Economic Co-operation and Development/Nuclear Energy Agency, report 2003
  98. Web site: Nuclear agreement: N Korea halts decommissioning. August 26, 2008. the Guardian.
  99. https://www.oecd-nea.org/rwm/profiles/Netherlands_report_web.pdf Radioactive waste management and decommissioning in the Netherlands.
  100. Web site: Inquinamento - Greenpeace Italia. www.greenpeace.org.
  101. Web site: UK-Russia Closed Nuclear Cities Partnership. https://web.archive.org/web/20090814190933/http://www.cncp.ru/eng/cities/seversk/seversk.shtml. dead. August 14, 2009.
  102. Web site: World Nuclear Association - World Nuclear News. www.world-nuclear-news.org.
  103. Web site: BBC News | Europe | Full ahead for Slovak nuclear reactor. news.bbc.co.uk.
  104. Web site: YAHOO NEWS: Slovakia forced to restart nuclear reactors after Ukrainian gas crisis.
  105. http://www.world-nuclear.org/information-library/country-profiles/countries-o-s/spain.aspx Nuclear Power in Spain
  106. https://www.enresa.es/eng/index/activities-and-projects/dismantling-and-environmental-restoration/dismantling-of-the-jose-cabrera-nuclear-power-plant Dismantling of the Jose Cabrera Nuclear Power Plant
  107. https://www.neimagazine.com/news/newsdismantling-of-spains-jos-cabrera-npp-almost-complete-9815975 Dismantling of Spain’s José Cabrera NPP almost complete
  108. https://www.world-nuclear-news.org/Articles/Decommissioning-milestone-at-Spain-s-Zorita-plant Decommissioning milestone at Spain's Zorita plant
  109. https://www.oecd-nea.org/rwm/workshops/findecom/presentations/2_3-garcia.pdf Comparison of estimated and actual decommissioning cost of José Cabrera NPP
  110. Web site: Business News Today: Read Latest Business news, India Business News Live, Share Market & Economy News. The Economic Times.
  111. Web site: Nuclear Energy Agency: Decommissioning in Switzerland.
  112. [Swiss Federal Nuclear Safety Inspectorate|ENSI]
  113. the same source
  114. http://www.ebrd.com European Bank for Reconstruction and Development
  115. https://nda.blog.gov.uk/first-of-the-uks-earliest-nuclear-sites-to-be-sealed-for-a-period-of-care-and-maintenance/ First of the UK’s earliest nuclear sites to be sealed for a period of “care and maintenance”.
  116. https://web.archive.org/web/20040222073030/http://www.bnfl.com/index.aspx?page=413 Calder Hall Celebrates 40 Years of Operation – Press Release
  117. News: First nuclear power plant to close . The Guardian . London . Paul . Brown . March 21, 2003 .
  118. http://webarchive.nationalarchives.gov.uk/20150817115932/http://www.nda.gov.uk/documents/upload/NDA-Calder-Hall-Nuclear-Power-Station-Feasibility-Study-2007.pdf NDA Calder Hall Nuclear Power Station Feasibility Study 2007
  119. Web site: Scotland's oldest nuclear reactor to go as demolition contract awarded. GOV.UK. en. 2019-03-05.
  120. Web site: Dounreay completes first phase of breeder shipments - World Nuclear News. www.world-nuclear-news.org. 2019-03-05.
  121. Web site: Free at last as jammed fuel is lifted out. GOV.UK. 4 December 2017 . en. 2019-03-05.
  122. News: New nuclear reactor for Dounreay . BBC . February 9, 1966 . April 10, 2016.
  123. Web site: PRIS: Dounreay PFR . IAEA . April 28, 2014.
  124. Book: 73–88 . Fast Breeder Reactor Programs: History and Status . Frank von Hippel . International Panel on Fissile Materials . 978-0-9819275-6-5 . February 2010 . April 28, 2014. etal.
  125. Web site: 'Reactorsaurus' to rip up station. BBC. May 5, 2009. May 5, 2009.
  126. News: BBC News – Plan to display parts of Dounreay at London museum. BBC Online. April 24, 2014.
  127. https://www.onr.org.uk/sites/winfrith.htm Winfrith
  128. https://www.nrc.gov/info-finder/decommissioning/index.html#alpha Sites Undergoing Decommissioning
  129. https://www.nrc.gov/images/reading-rm/doc-collections/maps/isfsi-facility-types.png Map of ISFSI Locations
  130. https://connyankee.com/decommissioning/ Decommissioning.
  131. https://connyankee.com/fuel-storage/ Fuel Storage
  132. https://www.nrc.gov/info-finder/decommissioning/power-reactor/cr3.html Crystal River Unit 3 Nuclear Generating Plant.
  133. https://www.tampabay.com/news/business/energy/shutting-down-crystal-river-nuclear-plant-will-cost-12-billion-take-60/2156453/ Shutting down Crystal River nuclear plant will cost $1.2 billion, take 60 years.
  134. Web site: Dresden - Unit 1. NRC Web.
  135. Web site: UCSUSA: Dresden Nuclear Generating Station.
  136. https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=623 FORT ST. VRAIN
  137. https://web.archive.org/web/20101226163544/http://xcelenergy.com/Minnesota/Company/About_Energy_and_Rates/Power%20Generation/ColoradoPlants/Pages/FortStVrainStation.aspx Fort St. Vrain Station
  138. https://www.assemblee-nationale.fr/14/pdf/rap-info/i4428.pdf No 4428 - Rapport d'information
  139. https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=599 Humboldt Bay Permanent Shutdown
  140. https://www.nrc.gov/reading-rm/doc-collections/news/2021/21-051.pdf NRC Terminates Humboldt Bay Nuclear Power Plant License
  141. Web site: Maine Yankee USA Nuclear Power Station Project - Power Technology | Energy News and Market Analysis. www.power-technology.com.
  142. Web site: Maine Yankee Decommissioning 80% Complete. https://web.archive.org/web/20110501093148/http://local.ans.org/ne/Ted%20-%20ANS%2010-30-03.pdf. dead. May 1, 2011.
  143. Web site: Maine Yankee Decommissioning Experience Report. 7 January 2009. 10 December 2014. https://web.archive.org/web/20141210020242/http://maineyankee.com/public/pdfs/epri/my%20epri%20report-2005.pdf. dead.
  144. US NRC Information Digest 2008–2009
  145. Web site: OSTI.GOV. www.osti.gov.
  146. http://www.power-eng.com/articles/2009/10/rancho-seco-nuclear-power-plant-ends-decommissioning.html Rancho Seco nuclear power plant ends decommissioning
  147. Web site: SACRAMENTO MUNICIPAL AUTHORITY DISTRICT: RANCHO SECO REPORT ON DECOMMISSIONING FUNDING STATUS.
  148. https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=604 SAN ONOFRE-1
  149. https://www.nrc.gov/info-finder/decommissioning/power-reactor/san-onofre-unit-1.html San Onofre – Unit 1
  150. Web site: Fission Stories #92: San Onofre's Allegators. May 15, 2012. All Things Nuclear.
  151. Web site: Cracked Steam Generator Tubes at San Onofre. March 27, 2012. All Things Nuclear.
  152. NRC Plans for Decommissioning of San Onofre Nuclear Generating Station Units 2 and 3 July 8, 2016
  153. Web site: San Onofre Nuclear Generating Station Units 2 and 3 Irradiated Fuel Management Plan . Southern California Edison . September 23, 2014 . NRC . 14.
  154. News: Calif. nuclear plant to cost $4.4 billion to dismantle. 3 August 2014. AP. CBS News. Aug 2, 2014.
  155. Web site: Shippingport station decommissioning project start of physical decommissioning. F. P.. Crimi. January 1, 1986. 5660448. www.osti.gov.
  156. Web site: Three Mile Island - Unit 2. NRC Web.
  157. News: Koberstein . Paul . Trojan: PGE's Nuclear Gamble . . A1 . March 9, 2005 . 2007-06-15 . dead . https://web.archive.org/web/20070929115456/http://www.wweek.com/editorial/3118/6073/ . September 29, 2007 . mdy-all .
  158. https://www.benningtonbanner.com/local-news/yankee-rowe-decommissioning-complete/article_6ccd0d48-d9af-5abb-b445-7787224f3a9c.html Yankee Rowe decommissioning complete
  159. https://www.nrc.gov/info-finder/decommissioning/power-reactor/zion-nuclear-power-station-units-1-2.html Zion Units 1 & 2.
  160. https://www.chicagotribune.com/news/ct-bn-xpm-2010-08-23-28516755-story.html Exelon sets stage for dismantling Zion reactor