Zimmerberg Base Tunnel Explained

Zimmerberg Base Tunnel
Line:Gotthard Line
Location:Zürich, Switzerland
Coordinates:47.3277°N 8.5312°W
System:Swiss Federal Railways (SBB CFF FFS)
Status:Active since 2003
Start:Zürich
End:Thalwil
Opened:April 2003[1]
Owner:SBB Infrastructure
Operator:SBB CFF FFS
Traffic:Railway
Character:Passenger and freight
Length:9.4km (05.8miles)[2]
Notrack:2
Gauge: (standard gauge)
El:15 kV 16.7 Hz

The Zimmerberg Base Tunnel (ZBT) is a railway tunnel under the Zimmerberg mountains in Switzerland. Phase I of the tunnel was opened to traffic during April 2003.

The ZBT has been divided into two phases of work; as of 2020, only Phase I is operational while Phase II remains in the planning and preparation stages. Zimmerberg I is about 10 km long and links Zürich with Thalwil and bypasses a section of the Lake Zürich left-bank railway line, allowing rail traffic to traverse the mountains more efficiently than traditional routes.

Phase I

During the 1990s, Switzerland embarked upon a major programme of modernization and improvements across its railway infrastructure.[3] The NRLA initiative sought to provide better alternatives to the steep mountain railways across Gotthard, Ceneri and Lötschberg through the construction of a number of base-level tunnels that enabled trains to more rapidly and efficiently traverse the Swiss Alps. The Zimmerberg Base Tunnel (ZBT) was one such tunnel constructed under the initiative.[4]

Phase I of the Zimmerberg Base Tunnel is a major feature of the route between Zürich and Thalwil. Construction represented a major milestone in Swiss railway infrastructure, the tunnel being the longest double-track tunnel to have been constructed by the nation in excess of 100 years.[5] The tunnel was designed to accommodate high speed transit, with trains traversing at peak speeds of up to 200 km/h. Reportedly, the projected cost of the 10.7 km Phase I section has been calculated at 820 million Swiss francs. During September 1997, construction of the tunnel commenced.[5] [6]

The local geography and location of the tunnel posed some challenges to the construction effort, such as the need to avoid impacting nearby urban development, as well as little cover being available at key areas. Boring operations through the rock incorporated both the use of a tunnel boring machine (TBM) along with some conventional techniques, such as blasting, soil injection, and pipe arches amongst other auxiliary construction measures intended to reduce the risk of excessive settlement.[7] Approximately 315 meters of the tunnel's length features a continuous grouted ceiling, which was done to reduce deformation and permeability as well as a potential loss of cover. This was created by injecting a precise mixture of cement and slurry via pressurized grouting pipes across 120,000 valves; areas were tested for potential weaknesses and promptly re-grouted where appropriate.

From an early stage of the project, the tunnel's opening was projected for June 2003,[5] a date which was fulfilled on time.[8]

Phase II

The proposed Phase II of the Zimmerberg Base Tunnel is one element of the wider Rail 2030 programme, which has an overall projected budget of 21 billion Swiss francs.[9] However, during 2010, it was reported that further work on the project had been put on hold indefinitely. At the time, work was underway on multiple other base tunnels, including the Ceneri Base Tunnel and the Gotthard Base Tunnel.[10]

If it is built as per the original plans, Phase II of the tunnel will bring its length to about 20 km, and will link Zürich with Zug. Even following its completion, it is planned to retain the intermediate exit to Thalwil, which would still be used by passenger and freight trains going to Chur as well as by international trains to Austria. Until Phase II is completed, capacity and speeds both remain heavily constrained by traditional routes; the Swiss Federal parliament has voted to include the work in its long term expansion plan for 2030–2035.[11] [12]

See also

External links

Notes and References

  1. Web site: Gotthard Base Tunnel . railway-technology.com . 9 June 2020.
  2. Web site: Project data – raw construction Gotthard Base Tunnel . 1 June 2016 . AlpTransit Gotthard AG . Lucerne, Switzerland . 15 December 2016.
  3. New Gotthard Rail Link: a Technical Challenge . Structural Engineering International . 10 . 2000 . 1 . Peter . Zbinden . 28–29 . 10.2749/101686600780620937 . 1016-8664 . 1683-0350 . 110985378 . 23 March 2018.
  4. The AlpTransit scheme: New railway lines in base tunnels under the Swiss Alps . Peter . Zuber . Tunnelling and Underground Space Technology . 12 . 3 . July 1997 . 357–360. 10.1016/S0886-7798(97)00029-1 . 0886-7798 .
  5. How the Zimmerberg-Base Tunnel is Being Built in the City of Zurich . Bosshard, Martin and Matter, Jürg . 2000 . 16 . IABSE Congress Report . 782–789 . 10.2749/222137900796356080. 3-85748-101-3 .
  6. Web site: Gotthard Basetunnel: Aspects of Long Tunnels . indico.cern.ch . F . Amberg . 14 February 2014.
  7. Web site: SBB Zimmerberg base tunnel . Basler & Hofmann . 9 June 2020 . 14 June 2021 . https://web.archive.org/web/20210614120310/https://www.baslerhofmann.ch/en/projects/en-projekte-detailansicht/projekt/zimmerberg-basistunnel-tunnelbau.html . dead .
  8. Successful grouting for the Zimmerberg Base Tunnel . Tunnelling and Underground Space Technology. Underground Space for Sustainable Urban Development. Proceedings of the 30th ITA-AITES World Tunnel Congress Singapore, 22–27 May 2004 . July 2004 . 19 . 4–5 . trid.trb.org . 10 June 2020. Matter . J. . Portner . J. . 0886-7798.
  9. Web site: Zimmerberg Base Tunnel . 3 May 2010 . dead . https://web.archive.org/web/20100820094606/http://www.alptransit.ch/en/status-of-the-work/zimmerberg-base-tunnel/ . 20 August 2010 . Official project site
  10. Web site: Gotthard: A titanic tunnel . newcivilengineer.com . Martina . Booth . 29 April 2010.
  11. Web site: Swiss obsession with tunnels continues . swissinfo.ch . Christian . Raaflaub . 1 June 2017.
  12. Web site: Swiss adopt SFr 13bn plan to increase rail capacity by 2035 . railjournal.com . Quintus . Vosman . 14 November 2019.