Willow Creek Dam (Oregon) Explained

Willow Creek Dam
Dam Crosses:Willow Creek
Res Name:Willow Creek Lake
Location:Morrow County, Oregon, U.S.
Operator:U.S. Army Corps of Engineers
Dam Height:160feet
Construction Began:1979
Opening:1983
Cost:$37,231,332 (as of June 18, 1997)
Res Capacity Total:gross 13250acre.ft
usable 9765acre.ft
Res Catchment:96sqmi
Res Surface:126acres max
95acres min[1]
Coordinates:45.347°N -119.5446°W

Willow Creek Dam is a dam in Morrow County of the U.S. state of Oregon, located just east of Heppner's city limits. It was the first major dam in the United States constructed of roller-compacted concrete.[2]

The dam's drainage basin is 96sqmi[3] of arid rolling hills in the lower basin but with headwaters in the northern Umatilla National Forest.The dam's original purpose was primarily to store water for flood control, but also to serve recreation, fish and wildlife, and irrigation uses.[3] The dam impounds Willow Creek to create Willow Creek Lake.

The lake level can be a maximum of 2113.51NaN1 elevation and a minimum of 20631NaN1 for a total usable storage capacity of 9765acre.ft.[3]

History

A major flood killed approximately one quarter of Heppner's population in June 1903—about 250 people. The flooding creek flow was 36000cuft/s as a result of a flash flood caused by thunderstorms, known as the Heppner Flood of 1903.[4]

A flood control study was completed in 1962 at a total cost of $219.[5] In 1965, a flood control project was authorized by U.S. Congress.[6]

In 1979, the purpose of a dam project was changed to defer irrigation development for the future and eliminate water supply and water quality control.[1]

Construction feasibility tests in 1972 placed a few layers of roller-compacted concrete.[7] A 1:36 model (one inch equals three feet) was built and studied to determine downstream flooding and pool siltation characteristics as affected by the dam's spillway.[8]

The dam was constructed by the Army Corps of Engineers between November 1981 and February 1983.[2] [9] [10] Construction completed nearly on schedule, despite the workers initially being unfamiliar with the materials, processing, and techniques. It came in less than its budget of $50 million at $35 million. The dam's construction validated economic and construction speed benefits where 330000m2 of concrete were finished in less than five months at about $17 per cubic meter ($13/yd3), which includes additional efforts to correct defects.

However, as soon as the lake began filling, significant leakage was evident through the seams of the layers of concrete. The lake was drained and a $2 million remedial effort included injecting grout through bores drilled from top to bottom. The initial rate of leakage was 33m3/s. After remediation, the leakage was less than 11m3/s. Concern over the dam's safety has continued, especially with the memory of the 1903 flash flood.

Within a few years of construction, problems were noted with stratification of the water and anoxic decomposition producing hydrogen sulfide. Concerns were expressed that this could in turn give rise to sulfuric acid leading to concrete damage. Controversy continued for some years and the handling of the problem itself was criticized. In 2004, an aeration plant was installed to address the root cause, as had been called for 18 years earlier.[9] Subsequent controversy surrounded the politics of a small town being used as an experiment for new construction technology.[11] SolarBee devices to circulate the water were installed in 2009.[12]

The dam won an American Society of Civil Engineers (ASCE) award in 1985.[13]

See also

External links

Notes and References

  1. Web site: Willow Creek Lake . US Army Corps of Engineers . June 18, 1997 . 2009-08-30 .
  2. Web site: Two Jobs Not for the Faint of Heart: "Changing site conditions" on South American dams take on a new meaning . Stephen H. Daniels . Engineering News-Record . August 19, 2002 . 2009-08-30.
  3. Web site: Willow Creek Dam and Lake . Columbia Basin Water Management Division . U.S. Army Corps of Engineers . 2009-08-30 . 1998-12-03 . https://web.archive.org/web/19981203120633/http://www.nwd-wc.usace.army.mil/report/wil.htm . dead .
  4. Book: willow Creek Disaster Documentary.
  5. Web site: Individual Project . 2009-08-31 . 2009-01-09 . https://web.archive.org/web/20090109230804/http://www.nww.usace.army.mil/dpn/dpn_project.asp?project_id=305 . dead .
  6. Web site: 89-298 Flood Control Act of 1965, Section 204, Columbia River Basin. https://web.archive.org/web/20090726064919/http://www.nww.usace.army.mil/dpn/publaw.htm . 2009-07-26 .
  7. Book: Significance of Tests and Properties of Concrete and Concrete-Making Materials (STP, 169c) . . Paul Klieger . Joseph F. Lamond . January 1, 1994 . 567 . 978-0-8031-2053-2.
  8. Web site: Willow Creek Dam Spillway and Stilling Basin at Heppner, Oregon. Hydraulic Model Investigation. . https://web.archive.org/web/20120227061738/http://oai.dtic.mil/oai/oai?verb=getRecord&metadataPrefix=html&identifier=ADA134687 . dead . February 27, 2012 . J. L. Lencioni . U.S. Army Corps of Engineers . April 1983.
  9. Reliably Safe . Douglas Larson . . January–February 2008 . 96 . 1 . 6 . 10.1511/2008.69.6 . 2009-08-30 . Am Sci, Reliably Safe. (start date conflicts with USACE source)
  10. Web site: Roller Compacted Concrete . US Army Corps of Engineers, Technical Assistance Team . October 21, 2003 . 2009-08-30 . 2009-06-18 . https://web.archive.org/web/20090618042934/https://transportation.erdc.usace.army.mil/tsmcx/downloads/RCCCorpsDXBrochure.pdf . dead . (secure connection certificate invalid)
  11. Reliably Safe . Douglas Larson . American Scientist . January–February 2008 . 96 . 1 . 6 . 10.1511/2008.69.6 . 2009-08-30.
  12. Web site: Unknown.
  13. Web site: ASCE Honors and Awards . 2009-08-31 . 2014-02-16 . https://web.archive.org/web/20140216215414/http://content.asce.org/handa/PastOCEAWinners.html . dead .