Bridge Name:Waldo–Hancock Bridge
Official Name:Waldo–Hancock Bridge
Carries: and
Crosses:Penobscot River
Locale:Bucksport, Maine, (Hancock County, Maine)
Maint:Maine Department of Transportation
Id:(Bridge No. 2973)
Design:Suspension bridge
Mainspan:8001NaN1
Length:20401NaN1
Width:201NaN1 roadway with
Two NaN1NaN1 sidewalks
Height:2361NaN1
Below:1351NaN1
Begin:1929
Complete:1931
Open:November 16, 1931
Closed:December 30, 2006 (Demolished 2013)
Toll:1931–1953
Coordinates:44.5607°N -68.802°W
Extra:
Embed:yes
Waldo–Hancock Bridge
Built:1931
Architect:Robinson & Steinman
Architecture:Suspension
Added:June 20, 1985
Delisted:December 18, 2013[1]
Area:4acres
Refnum:85001267

The Waldo–Hancock Bridge was the first long-span suspension bridge erected in Maine, as well as the first permanent bridge across the Penobscot River downstream from Bangor. The name comes from connecting Waldo and Hancock counties. The bridge was built in 1931 and retired in 2006, when the new Penobscot Narrows Bridge was opened just a few yards away, and it was demolished in 2013.

The bridge was 2040feet long with a clear center span of 800feet between towers. It had two 350feet side spans and carried a 201NaN1 wide roadway with two NaN1NaN1 sidewalks. It used stiffening trusses that are 9feet deep. Each of the main catenary cables were NaNinches in diameter, and consisted of 37 strands of 37 wires. The deck was 135feet above water level to allow passage of large ships. The total cost of the span was less than $850,000 in 1931 dollars (about $12 million in 2010 dollars), significantly under its allocated budget.

Construction

David B. Steinman, of Robinson and Steinman, was the designer. The bridge was fabricated by American Bridge Company (superstructure) and Merritt-Chapman & Scott (substructure).

Technologically, the Waldo–Hancock Bridge represented a number of firsts. It was one of the first two bridges in the U.S. (along with the St. Johns Bridge in Portland, Oregon, completed in June 1931) to employ Robinson and Steinman's prestressed twisted wire strand cables, which were first used on the 1929 Grand Mère Suspension Bridge over the Saint-Maurice River in Quebec. The prefabrication and prestressing of the cables decreased the number of field adjustments required, saving considerable time, effort, and money. As an additional experiment in efficiency, the Waldo–Hancock cables were marked prior to construction, ensuring proper setting. This method had never been used before and proved successful in this instance. These innovations, invented and pioneered by Steinman, were a significant step forward for builders of suspension bridges.

The Waldo–Hancock was also the first bridge to make use of the Vierendeel truss in its two towers, giving it an effect that Steinman called "artistic, emphasizing horizontal and vertical lines." This attractive and effective truss design was later used in a number of important bridges, including the Triborough Bridge and Golden Gate Bridge.[2]

The Waldo–Hancock Bridge was noted at the time for its economy of design and construction. It cost far less than had been appropriated by the State Highway Commission, which enabled the construction of a second bridge between Verona Island and Bucksport. When opened in 1931 the bridge collected tolls used to retire the bonds issued to finance its construction. All tolls were lifted twenty-two years later on October 31, 1953, however, when those original construction bonds were paid off. Original tolls ranged from 10¢ for "one or two horse vehicle including driver" to 50¢ for "auto truck or tractor over 26,000 pounds".

Rehabilitation, replacement, and retirement

As the bridge approached its seventieth anniversary with the end of the century, a series of routine safety inspections made by the Maine Department of Transportation revealed that over those seven decades the structure's two main suspension cables and the many vertical bridge deck stringers had become seriously corroded, thereby deteriorating their ability to support the deck, roadway and the traffic that crossed it. These engineering studies made it clear that the bridge required immediate major rehabilitation and eventual replacement.[3]

Work was undertaken to rehabilitate the bridge starting in 2000 by Cianbro and Piasecki Steel Construction Corp. with cable work by Williamsport Wirerope Works Inc., by focusing on strengthening the cables. The two cables were done separately, one a time. Piasecki Steel Construction Corp. of Castleton, New York, rehabilitated the north cable in 2002. At this point the bridge was discovered to be beyond permanent repair and would have to be abandoned and replaced by a new structure to be built adjacent to the aging bridge.[4] Work then shifted to temporary strengthening. For the south cable, MDOT in August 2003 hired Pittsfield, Maine-based Cianbro Corp. under a $4-million emergency contract.

The rehabilitation used a single wire thickness (2inches galvanized helical 91-wire strands) to facilitate fabricating and installing the cables more quickly. New concrete anchorages with up to 30feet anchor rods were built by Cianbro. Crews installed continuous runs of strands on new saddles bolted and welded on new base plates atop cable bents and the main towers. Workers placed two groups of four strands 12feet above each main cable to allow for pulls. Each strand weighs 4 tons (3.6 metric tons). A rope pull was walked across, connected to a NaNinches pull cable, then winched back across and connected to the strand, which was fed through a tensioner holding back about 15000lb to smooth the pull.

"We hooked and rehooked one strand per day on average," says Archie J. Wheaton, Cianbro project superintendent. "The strands were connected to anchor rods; then we set the sag." The new auxiliary cables are connected to existing double suspender cables by NaNinches steel rods, then tensioned with 30-ton (27.2 metric ton) jacks, bringing the new cables about 3feet from the main cables.[5]

A new construction, the Penobscot Narrows Bridge, was built alongside the older one.[6] The new bridge was opened to traffic on December 30, 2006, at which point the Waldo–Hancock Bridge was ceremoniously closed. Barricades were erected at both ends, closing the bridge to both cars and pedestrians.

Demolition

The Maine Department of Transportation announced on February 14, 2012, that the bridge would be demolished starting that summer and be completed by the fall. The schedule was designed to accommodate the needs of two endangered species, the Peregrine falcon and the Shortnose sturgeon. Barges were placed in the Penobscot River onto which sections of the bridge were lowered. The concrete piers in the river are all that remains, and MDOT worked with the United States Coast Guard to design lights for them once the Bridge was removed to aid ships in the river.[7] Later, MaineDOT announced that the low bid of $5.35 million by S&R Corp. of Lowell, Massachusetts, was accepted.[8]

Demolition was delayed until 2012, beginning with the November 20 removal of the bridge's flag poles, and was completed in June 2013.[9]

See also

Further reading

The following sources are referenced in the HAER documentation:

External links

Notes and References

  1. http://www.nps.gov/history/nr/listings/20131227.htm NRHP actions list, December 27, 2013
  2. Web site: Farnham . Katherine Larson . 1999 . Waldo–Hancock Bridge . Historic American Engineering Record . 1 . Library of Congress . November 8, 2020.
  3. Web site: History . Waldo–Hancock Bridge Replacement Project . Maine Department of transportation . May 1, 2006.
  4. Web site: Waldo–Hancock Suspension Bridge . Bridgemeister.com . May 1, 2006.
  5. Web site: Angelo . William J. . 2003 . Maine Cables Get Extra Support in Rare Procedure . ENR.com Engineering News Record . May 1, 2006.
  6. This image is a spectacular overhead view of the roadway advancing on the new bridge from the Maine DOT site
  7. News: Miller . Kevin . 2012 . Demolition of 86-year-old Penobscot River bridge to begin this fall . Bangor Daily News . February 14, 2012.
  8. News: Moretto . Mario . 2012 . State receives low bid of $5.35 million for demolition of Waldo–Hancock Bridge, to start in October . Bangor Daily News . August 12, 2012.
  9. Web site: MaineDOT . Waldo–Hancock Bridge Removal . February 3, 2013.