Bridge Name:Unity Bridge
Other Name:Unity Bridge 1
Carries:2 lanes
Crosses:Ruvuma River
Designer:Norconsult
Design:Box girder bridge[1]
Height:up to
Spans:18
Builder:China Geo-Engineering Corporation
Begin:16 October 2005
Cost:US$ 35 million
Inaugurated:12 May 2010

The Unity Bridge (sometimes called "Unity Bridge 1") across Ruvuma River at Negomano, Mozambique,[2] between Tanzania and Mozambique, was proposed as early as 1975, shortly after Mozambique's independence.It was the idea of the two countries' former Presidents, Mwalimu Nyerere and Samora Machel. Several design studies and limited construction work were completed in the early 1980s, but the Unity Bridge was not finished due to lack of funds.

In 2002, the two national governments made a formal agreement to build a new bridge across the river. The first foundation stones were laid both on Tanzanian and Mozambican sides on October 10, 2005. Construction was initially planned to be finished in 2008.

In 2005, Norconsult was awarded the contract for preliminary design and construction supervision of the bridge. It was planned to be about 720 m long.

The project was hoped to boost development in Mtwara Region (Tanzania), Cabo Delgado (Mozambique) as well as in the Southern African Development Community region as it is an important component of the Mtwara Development Corridor. It would also shorten the distance along the Cape to Cairo Road.[3]

Environmentalists say it will destroy Niassa Reserve in Mozambique which is home to elephant, buffalo, sable and roan herds.[4]

The Unity Bridge over the Rovuma River was built by the China Geo-Engineering Corporation with COWI as consultants for the detailed design and finally inaugurated on 12 May 2010 by the presidents of Mozambique and Tanzania.

The rehabilitation of access roads on both sides of the bridge is to be started. A second, smaller bridge, Unity 2, was completed in 2007.

See also

References

Notes

  1. Web site: Technical specifications . . 7 March 2013.
  2. Web site: Ministry of Trade and Industry (South Africa). Prefeasibility And Environmental Baseline Study For The Ruvuma River Interface Final Report . Selous - Niassa Wildlife Corridor . 21 August 2005 . PDF . 56 . 17 March 2010. etal.
  3. Web site: Valy . Bayano . Bridging the Ruvuma, bridging unity . Southern African News Features . January 2005 . 17 March 2010.
  4. News: 'Unity Bridge' to link Mozambique and Tanzania . Mail & Guardian . Johannesburg . 8 October 2005 . 17 March 2010.