Toronto subway trackage explained

The Toronto Transit Commission (TTC) maintains three rapid transit lines and 75 stations on 76.9km (47.8miles) of route.[1] There are also two light-rail lines under construction.

Mainline trackage

Gauge

The TTC's heavy rail linesLines 1, 2, and 4are built to the unique Toronto gauge of, which is the same gauge used on the city's streetcar system. However, the former Line 3 Scarborough light metro system (which operated between 1985 and 2023) used standard-gauge track, as will three lines under construction : the light rail Line 5 Eglinton and Line 6 Finch West, along with the light metro Ontario Line.

Tunnels

Tunnels are either square or round, depending on the method of their construction: Square tunnels were built with the cut and cover method of digging trenches down from the surface, constructing the tunnel structure, and then backfilling.[2] Round tunnels are bored using a tunnel boring machine (TBM). The cut and cover technique was used extensively on the oldest portions of the subway system, while newer sections were predominantly or, in the case of the Toronto-York Spadina Subway Extension (TYSSE), which opened in 2017, entirely bored.

Some sections of track run on the surface, the most notable on the heavy rail subway system being the stretch of Line 1 Yonge–University in the median of Allen Road. However, the former light metro Line 3 was a surface or elevated route for nearly its entire length.

Crossovers

Diamond crossovers (or "scissors crossovers") are X-shaped track assemblies that are used, particularly at terminal stations, to allow trains to switch to the opposite platform or track to reverse direction. They also exist outside some through stations (mostly those that were former terminal stations) where they are often used to short turn trains. A single-crossover just east of Union Station is what remains of the former diamond-crossover, which was used when the station marked the southern terminus of the original line. The light-rail lines (Line 5 Eglinton and Line 6 Finch West) in some locations use a pair of single crossovers (one facing-point and the other trailing-point) or sometimes just a single crossover (either facing-point or other trailing-point) instead of diamond crossovers.

Crossovers are found in the vicinity of the following stations. Unless otherwise described, they are diamond crossings.

Centre and pocket tracks

Centre tracks allow a train to enter from either end into a third track, longer than the length of a standard train, between the two service tracks. Trains can either layover or short turn there, allowing other trains to pass them by, or reverse direction from this position with minimal interference with through trains compared to crossovers, which requires the reversal to take place on station platforms. Sometimes, in-service trains are diverted into centre tracks when there is track maintenance on one of the service tracks. Pocket tracks are a variation on the centre track, accessible only from one end. Some storage tracks have a short stub extending beyond the convergence back to the service tracks used to store work cars. All operating centre-track structures (with the exception of Finch West station, which was partially bored and has three fully separate tunnels) were built using the cut-and-cover method, and there are support columns between the tracks. However, at the under-construction and stations on Line 5 Eglinton, which were "mined" rather than excavated via cut-and-cover, all three tracks are housed within single tubular, columnless tunnels.[5]

Storage tracks are found in the vicinity of the following stations:

Other track features

Track configurations become more complicated where lines meet (at the SpadinaSt. GeorgeMuseumBayYonge junction and at Sheppard–Yonge), and at the entrances to subway yards.

On the heavy rail lines (1, 2 and 4), tracks usually continue for roughly the length of a train beyond the last station on a line; these are known as tail tracks. The only exception to this is at Don Mills station, where the tail tracks are less than two cars in length. This is likely because storage capacity is available at Sheppard–Yonge, which can store enough trains to service the line. The tail track structures at some terminal or former terminal stations also have, or have provisions for, a third tail track. Finch station has such a triple configuration, Vaughan Metropolitan Centre station is a terminal station with a trackless tunnel section for installation of a potential third tail track, and Sheppard West station was a former terminal also built with a trackless third tunnel north of it, which could now accommodate a future standard pocket track.

Other track features that exist include the following:

The Bloor wye was used for interlining between Lines 1 and 2 in 1966:

The tracks used for access to yards:

The Sheppard Wye allows the movement of out-of-service trains between the Sheppard line and the Davisville Yard on the Yonge line. The wye has the following features:

Each subway yard has different features that join them to the mainline. Subway operators generally get their train at a point where the yard meets the main line, at the Greenwood Portal, the Davisville Buildup (third platform of Davisville station), or the Wilson Hostler (platform-like in appearance seen heading between Wilson and Sheppard West stations on the east side of the yard) depending on the home yard. The light-rail lines have a similar feature at their maintenance and storage facilities.

See also

Notes and References

  1. Web site: 2013 TTC Operating Statistics . Toronto Transit Commission . 2015-01-14.
  2. Web site: How Cut and Cover Worked in 1951 . TTC Sidewalk Superintendents' Manual . Transit Toronto . 2018-04-30.
  3. Web site: TTC subway track diagram 2014 . Transit Toronto . Eliot . Rossi . 2014.
  4. Web site: Major vehicle testing milestone on Finch West LRT . . 2024-05-23 . 0:10 .
  5. Web site: See time-lapse video of Crosstown light rail vehicles moving along Toronto route (Time: 0:25 and 2:13) . . November 30, 2021 . December 6, 2021.
  6. Web site: Eglinton Crosstown Surface Flyover - December 2020 . . January 6, 2021 .
  7. Web site: Public Open House . . January 11, 2016 . https://web.archive.org/web/20211222183218/https://www.metrolinx.com/en/projectsandprograms/transitexpansionprojects/Finch_West_201601_Open_House_Presentation_EN.pdf . December 22, 2021 . live .