Temporary Generation North Explained

Temporary Generation North
Country:Australia
Location:Elizabeth South
Coordinates:-34.744°N 138.653°W
Commissioned:November 2017
Decommissioned:Q1 2021
Owner:Government of South Australia
Th Fuel Primary:diesel
Th Technology:gas turbine
Ps Units Decommissioned:5
Ps Units Manu Model:General Electric TM2500
Ps Electrical Capacity:154MW
Status:decommissioned

Temporary Generation North and its smaller sibling Temporary Generation South were gas turbine power stations in South Australia. They were bought by the Government of South Australia in 2017 as a response to the 2016 South Australian blackout and load-shedding in February 2017.

Temporary Generation North was five open cycle gas turbines installed at the former Holden site in Elizabeth South, a northern suburb of Adelaide. It was closed in the first quarter of 2021 so that the turbines could be moved to become the Snapper Point Power Station at Outer Harbor.[1]

The generators were purchased to be used only in emergency shortfalls in electricity supply to the grid, such as in extreme weather. Both sets were first used on 24 January 2019 to deal with a supply shortfall in Victoria.[2]

The intent of the Weatherill ALP state government was that the turbines would be converted from diesel fuel to natural gas and moved to a single location while remaining owned by the government.[3]

In August 2019, the state government (following the 2018 election, now controlled by the Liberal party) announced that it had arranged 25-year leases of the power stations to two different companies, with the leases taking effect from May 2020. Both companies operate wind farms in South Australia.[4] The five northern generators were leased to Nexif Energy and are being relocated to a new site at Outer Harbor and operating on natural gas, intended to be before the end of 2020. Nexif Energy also proposes to convert them to combined cycle with a steam turbine in the following few years.[5] This schedule was delayed by the COVID-19 pandemic, with Temporary Generation North closing in the first quarter of 2021, and Snapper Point in commissioning as of April 2022.[6]

Notes and References

  1. News: Thompson . Sarah . Macdonald . Anthony . Boyd . Tim . 28 March 2021 . Advisers pitch to sell Denham’s Nexif as renewables run hot . . https://web.archive.org/web/20210328103618/https://www.afr.com/street-talk/advisers-pitch-to-sell-denham-s-nexif-as-renewables-run-hot-20210328-p57ep0 . 28 March 2021 . 9 June 2022.
  2. News: Power generators switched on for first time as SA, Victoria suffer through heatwave . 25 January 2019 . 30 June 2019 . ABC News.
  3. News: Generators installed at former Holden site and desal plant to reduce summer blackout risk . Leah . MacLennan . 13 November 2017 . 30 June 2019 . ABC News.
  4. News: Leasing out state-owned diesel generators will push prices down: expert . Bension . Siebert . . 29 August 2019 . 30 August 2019.
  5. Web site: NEXIF ENERGY TO PROVIDE 154MW OF RELIABLE GAS GENERATION TO THE SOUTH AUSTRALIAN POWER GRID . . 28 August 2019 . 30 August 2019.
  6. News: Tisheva . Plamena . Nexif Energy completes 222-MW Aussie wind project, closes refinancing . 26 April 2022 . 9 June 2022 . Renewables Now.