Tarong Power Station Explained

Tarong Power Station
Location Map Caption:Location of the Tarong Power Station in Queensland, Australia
Coordinates:-26.7811°N 151.915°W
Country:Australia
Location:Tarong, Queensland
Status:O
Construction Began:1979
Commissioned:1 Unit: May 1984
2 Unit: May 1985
3 Unit: February 1986
4 Unit: November 1986
Cost:A$1.23 billion
Owner:Stanwell Corporation
Th Fuel Primary:Bituminous coal
Ps Units Operational:4 × 350 MW
Ps Units Manu Model:Hitachi
Ps Electrical Capacity:1,400 MW
Website:https://www.stanwell.com/energy-assets/

The Tarong Power Station is a coal fired power station located on a site in Tarong in the South Burnett Region near the town of Nanango, in Queensland, Australia. The station has a maximum generating capacity of 1,400 megawatts, generated from four turbines. Coal is supplied via a conveyor from Meandu Mine, which is 1.5km (00.9miles) away and is also owned by Stanwell.

Construction and design

The location near Nanango was the preference of the premier of the day, Joh Bjelke-Petersen, out of a total of three possible locations that were considered.[1] It was decided to build a new power station at Tarong in 1978, with work beginning in the following year.[2] Initially it was expecting to be operating by October 1985 but this date was brought forward by 17 months to cover the expected growth in demand. Unit 1 was commissioned in May 1984, with Unit 2 following exactly 12 months later. Unit 3 was commissioned in February 1986, and finally Unit 4 was commissioned just 9 months later in November 1986. Thus the accelerated construction program included not only bringing forward the dates, but also compressing the timeline.

The design included Queensland's first hyperbolic natural draught cooling towers which rise to 116.5 m. The power station has one chimney which is 20 m in diameter and rises 210 m.[2] There are two control rooms. The total construction cost including water supply facilities was A$1,230 million.

Stanwell decided in 2021 to install a 150 MW grid battery at Tarong.[3] Scheduled for 2023, the battery will add approximately two hours of storage to the facility.[4] However, the battery was doubled to 300 MW and 600 MWh, installed in 2024.[5]

Emissions

The power station was the site for a pilot project which had been expected to reduce emissions by 1000 tonnes per year by collected carbon dioxide from flue gases.[6] The project was developed by CSIRO and launched in 2010.[6]

A second trial to capture greenhouse gas emissions was conducted by MBD Energy. The technology being trialled collected carbon dioxide and pumped it into waste water where it synthesised oil-rich algae into edible seaweed products or oils.[7] Research measured performance of certain bacteria types.[8] [9]

Demand reduction

In October 2012, Stanwell announced plans to shut down two generating units for two years.[10] The electricity market was oversupplied and wholesale electricity prices were relatively low.[11] The scaling down of operations resulted in the loss of employment for some workers. Both units have since been successfully restarted.

Return to service

Because of higher natural gas prices in 2014 power generators turned to coal-fired power.[12] In July 2014, one of two units shut down in 2012 returned to service. The recommissioning task was a first for a turbine of that type and took 20,000 hours to complete.[12] The second turbine is expected to be operating by 2015.

See also

External links

Notes and References

  1. News: van Vonderen . Jessica . 1 January 2009 . Power plays revealed with 1978 Cabinet minutes release . . . 6 November 2021 .
  2. Book: Dunn, Col . The History of Electricity in Queensland . 1985 . Col Dunn . Bundaberg . 0-9589229-0-X . 169–170 .
  3. Web site: Mazengarb . Michael . Tarong coal generator to add 150MW big battery in Queensland "battery blitz" . RenewEconomy . en-AU . 2021-05-27.
  4. Web site: Stanwell advances battery storage plans . 27 May 2021 . Stanwell Corporation . 1 November 2021 .
  5. Web site: Heavy lifting complete, as final 38 tonne Tesla Megapack installed at battery project next to coal plant . RenewEconomy . en-AU . 22 May 2024.
  6. News: Tarong Energy and CSIRO launch carbon capture plant . Sophie Benjamin . 5 August 2011 . 3 December 2010 . ABC Southern Queensland . Australian Broadcasting Corporation .
  7. News: Carbon-capture support spurs MBD's $100m IPO . Tracy Lee . 5 August 2011 . 1 August 2011 . The Australian .
  8. Zhang . Xing . Microalgae removal of CO 2 from flue gas . 2015 . 10.13140/RG.2.2.26617.77929.
  9. von Alvensleben . Nicolas . Magnusson . Marie . Heimann . Kirsten . Salinity tolerance of four freshwater microalgal species and the effects of salinity and nutrient limitation on biochemical profiles . Journal of Applied Phycology . April 2016 . 28 . 2 . 861–876 . 10.1007/s10811-015-0666-6. 17645537 .
  10. News: Jobs go as Tarong power station winds back . 19 November 2012 . 11 October 2012 . Brisbane Times .
  11. News: Tarong brings units out of cold storage . Jordan Philp . 30 July 2014 . 5 February 2014 . The South Burnett Times .
  12. News: Electricity providers return to coal-fired power as natural gas export revenue soars . Eric Tlozek . 30 July 2014 . 3 July 2014 . ABC News .