Taralga Wind Farm | |
Coordinates: | -34.4271°N 149.8576°W |
Country: | Australia |
Location: | Near Taralga, New South Wales |
Status: | O |
Construction Began: | September 2013 |
Commissioned: | Mid 2015 |
Cost: | A$280 million[1] |
Owner: | State Power Investment Corp |
Operator: | CWP Renewables |
Ps Units Operational: | 21 × 2.0 MW 21 × 1.8 MW 9 × 3.0 MW |
Ps Units Manu Model: | Vestas V90-2.0MW Vestas V100-1.8MW Vestas V90-3.0MW |
Wind Hub Height: | 80m (260feet) |
Wind Rotor Diameter: | 90m (300feet) 100m (300feet) |
Wind Farm Type: | Onshore |
Ps Site Elevation: | 910 metres |
Ps Electrical Capacity: | 106.8 |
Ps Electrical Cap Fac: | 32.28% (average 2016-2020) |
Ps Annual Generation: | 302 GWh (average 2016-2020) |
The Taralga Wind Farm is a wind farm located near Taralga, New South Wales. Owned by Pacific Blue, it commenced operation in 2015.
Taralga Wind Farm was CBD Energy/Santander's first and only wind farm. It is a 106.8 megawatt wind farm with 51 turbines. The energy produced by the wind farm can power around 45,000 average Australian households per year, saving over 258,000 tonnes of greenhouse gas emissions per year.[1]
The Taralga Wind Farm is near Taralga.
On 20 February 2012, approval was granted by the government of New South Wales for work to commence on the Taralga Wind Farm, after the approval of the Stage 1 CEMP. The project consists of 51 wind turbines generating 106.8 Megawatts of electricity on ridges to the east of Taralga. Electricity generated by the project will be fed into the national power grid through a 37.5 km transmission line to Marulan Substation.
The project created up to 200 local jobs during the construction phase.[2] Approval of the wind farm followed an unsuccessful challenge by the Taralga Landscape Guardians in the Land and Environment Court of New South Wales to block the project on the grounds of aesthetic and environmental impacts including noise emissions and blighting of the landscape. Chief Justice Brian Preston ruled in favour of approving the wind farm as the long-term benefit of reduced greenhouse gas emissions was in the greater public interest.[3] In June 2015, the wind farm was fully commissioned and commenced commercial operations. The layout of the wind farm can be seen through this link.
In March 2015, the Chinese state-owned utility State Power Investment Corp agreed to purchase the Wind Farm for a reported A$300 million, which includes the A$200 million debt facility from the CBD Energy (now BlueNRGY) and Banco Santander subsidiary Capital Riesgo joint venture.[4]
the project was operated under an O&M contract with Vestas Australia, with Wind Prospect / CWP acting as asset managers.[5]
To help fund the construction of the wind farm, CBD Energy/Santander signed a A$200 million project finance debt facility agreement with ANZ, CEFC, and EKF.[1] The project had off-take backing from EnergyAustraliaThe total project cost was A$280 million.
The wind farm began grid commissioning in December 2014 and reached full output in July 2015[6] and has operated continuously since then. The generation table uses eljmkt nemlog to obtain generation values for each month.
2014 | 1,834 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | N/A | N/A | N/A | N/A | 1,834* | |
2015 | 219,430 | 6,237* | 5,993* | 11,950* | 13,024* | 20,423* | 14,382* | 31,897 | 34,421 | 19,168 | 22,959 | 20,562 | 18,414 | |
2016 | 318,480 | 17,309 | 13,246 | 12,180 | 12,716 | 45,007 | 33,133 | 40,319 | 26,627 | 28,697 | 41,827 | 23,462 | 23,957 | |
2017 | 291,587 | 21,822 | 18,912 | 16,330 | 13,517 | 17,780 | 15,305 | 43,412 | 37,790 | 45,278 | 19,473 | 13,241 | 28,727 | |
2018 | 299,383 | 19,557 | 17,018 | 19,435 | 17,990 | 29,260 | 27,049 | 42,007 | 41,402 | 24,603 | 20,004 | 23,740 | 17,318 | |
2019 | 312,021 | 16,489 | 16,257 | 20,909 | 15,721 | 30,528 | 20,116 | 37,777 | 37,695 | 29,488 | 23,993 | 35,632 | 27,416 | |
2020 | 288,735 | 19,621 | 20,795 | 17,089 | 30,067 | 24,518 | 22,239 | 22,983 | 40,801 | 29,118 | 24,366 | 16,695 | 20,443 | |
2021 | 20,241 | 13,589 | 25,640 | 20,241 | 23,335 | 29,065 | 31,064 | 35,415 | 34,735 |