Tappan Zee Bridge (2017–present) explained

Bridge Name:Tappan Zee Bridge
(Governor Mario M. Cuomo Bridge)
Official Name:Governor Mario M. Cuomo Bridge
Also Known As:New Tappan Zee Bridge; New NY Bridge
Carries:
8 automobile lanes, 2 bus lanes,
2 bicycle/pedestrian lanes[1]
Crosses:Hudson River
Locale:Connecting South Nyack (Rockland County) and Tarrytown (Westchester County)
Maint:New York State Thruway Authority
Design:Twin span cable-stayed bridge
Width:, total of both decks: 87feet and 96feet
Clearance:unlimited
Begin:2013
Cost:$3.9 billion (2013 project budget)
Opened:August 26, 2017 (westbound/northbound span)
September 11, 2018 (eastbound/southbound span)
Toll:Cars $10.94 Tolls-by-Mail; $10.94 non-NY E-ZPass; $6.25 NY E-ZPass (eastbound/southbound only)
Larger vehicles pay variable toll based on vehicle class and time of day (cashless toll)
Replaces:Tappan Zee Bridge (1955–2017)
Coordinates:41.0714°N -73.8911°W

The Tappan Zee Bridge, officially named the Governor Mario M. Cuomo Bridge after the former New York governor, is a twin cable-stayed bridge spanning the Tappan Zee section of the Hudson River between Tarrytown and Nyack in the U.S. state of New York. It was built to replace the original Tappan Zee Bridge opened in 1955, which was located just to the south. The bridge's north span carries the northbound and westbound automobile traffic of the New York State Thruway, Interstate 87 (I-87) and I-287; it also carries a shared use path for bicycles and pedestrians. The south span carries southbound and eastbound automobile traffic.

Although not as old as other bridges such as the George Washington, the original Tappan Zee was built in the midst of a material shortage during the Korean War and was thus only designed to last for approximately fifty years. The process to replace the bridge kicked off in 2012, with construction on the new spans beginning by contractor Tappan Zee Constructors in 2013. The Left Coast Lifter (one of the world's biggest cranes) was instrumental in the construction of the bridge. The north span officially opened to westbound traffic on August 26, 2017, and eastbound traffic temporarily began using the north span on October 6, 2017. Contractors then began demolishing the old bridge. An opening ceremony for the south span was held on September 7, 2018,[2] and traffic started using the new span three days later.

The bridge's official name, which does not include the words "Tappan Zee" like its predecessor, has been controversial since its announcement. A petition and several legislative bills have sought to officially rename the bridge to the Tappan Zee Bridge or similar names.

History

The Tappan Zee river crossing was named by 17th century Dutch settlers.[3] The Tappan Zee Bridge is the only crossing of the Hudson between Westchester and Rockland counties. The original Tappan Zee Bridge was a cantilever bridge built from 1952 to 1955.[4] [5] The bridge was long and spanned the Hudson at its second-widest point. It was the longest bridge in New York State, at a length of 16013feet including approaches.[6] Built immediately after the Korean War, the bridge had a low construction budget of only $81 million and a designed life-span of only 50 years.[7] During its first decade, the bridge carried fewer than 40,000 vehicles per day.

Planning

By the start of the 21st century, the old Tappan Zee Bridge was "decaying" and "overburdened". The deteriorating structure bore an average of 140,000 vehicles per day, substantially more traffic than its designed capacity.[8] The collapse of Minnesota's I-35W Mississippi River bridge in 2007 raised worries about the Tappan Zee Bridge's structural integrity.[9] These concerns, together with traffic overcapacity and increased maintenance costs, escalated the serious discussions already ongoing about replacing the Tappan Zee with a tunnel or a new bridge.[10] [11] Six options were identified and submitted for project study and environmental review.[12] The Federal Highway Administration issued a report in October 2011 designating the Tappan Zee's replacement to be a dual-span twin bridge. The new bridge was to be built a few yards to the north of the existing bridge, connecting to the existing highway approaches of the New York State Thruway (I-87/I-287) on both river banks.[13] The New York State Thruway Authority requested design proposals from four companies in 2012 and eventually received three project proposals.[14] [15] The authority awarded a $3.142 billion contract to Tappan Zee Constructors (TZC), whose proposal was not only the least expensive but also promised the shortest construction timeline and included plans to minimize environmental impact.[16] [15]

Originally, some motorists thought that bridge tolls could more than double (to $12-$15 for automobiles, eastbound only), rising to those of New York City's Hudson River crossings.[17] However, the state passed legislation freezing the toll on the bridge at $5 through 2020 in its 2016 legislative session.[18]

The new Tappan Zee Bridge was proposed to include four vehicle lanes on each span, for a total of eight lanes, as well as a shared-use bicycle and pedestrian path. Like its predecessor, the new Tappan Zee Bridge is to be administered by the New York State Thruway Authority. The authority is the project co-sponsor, along with the state Department of Transportation.[13]

Construction

The New York Metropolitan Transportation Council added the Tappan Zee Bridge to its list of projects eligible for federal funds in August 2012.[19] The United States Department of Transportation approved the plan on September 25, 2012. The approval process took fewer than 10 months as opposed to the traditional multi-year process as a result of being placed on a "fast track" for approval by the Obama administration.[20] On December 17, 2012, New York state officials dropped their proposal for a 45 percent increase on the state Thruway toll for trucks, while advancing a $3.14 billion project to replace the bridge.[21] The project was funded through a public-private partnership.[22]

Construction began as scheduled in October 2013,[23] [24] with completion targeted for 2017.[25] TZC, the contractor, was composed of several design, engineering, and construction firms including Fluor Corporation, American Bridge Company, Granite Construction Northeast and Traylor Bros. The Left Coast Lifter was used to install groups of pre-assembled girders one full span at a time.[26] The contractors were obliged to finish the bridge by 2018, after which the state would fine the contractors around $100,000 per day.[27]

By the end of 2013, General Electric had completed four seasons of dredging to remove contaminants from the river bottom. Approximately 70 percent of the sediments targeted for dredging were removed (totaling more than 1900000yd3 of sediment).[28]

On July 19, 2016, a crane used for the construction of the bridge collapsed onto the existing older bridge. Five people were injured, including three drivers and two bridge workers; no one was killed or critically injured.[29] [30]

Completion

The project timeline originally indicated that the old bridge would be closed in 2016 and that the demolition of the old bridge would begin in February 2017.[31] The new northbound/westbound span opened on August 26, 2017.[32] [33] Southbound/eastbound traffic remained on the existing span until October 6, 2017, when it was shifted to the new northbound/westbound span to allow for the completion of the new southbound/eastbound span.[34] The northbound/westbound span of the new Tappan Zee Bridge temporarily carried four lanes in both directions until the new southbound/eastbound span was completed.[35] [36]

After some delays, the project was later expected to be completed by June 15, 2018, at a cost of $3.98 billion.[37] However, the scheduled opening was later pushed back to mid-September.[38] The new southbound/eastbound span was supposed to open to traffic on September 8, 2018.[39] [40] An opening ceremony was held on that date,[41] [42] but the traffic shift itself was delayed when a piece of the old bridge came loose on September 7 while being demolished. The opening of the eastbound span, which was 160feet away from the old bridge, was delayed until the old bridge could be stabilized.[43] [44] After the old bridge was stabilized, all lanes were opened on September 11, 2018.[45] [46]

The demolition of the old bridge started in November 2017 with the removal of the first steel section from the Rockland County approach. The work continued to April 2018 including the removal of the truss sections. In May 2018, the 10-million-pound main span was removed, leaving only the east and west approaches.[47] The original plan was to complete the remaining demolition by taking down spans piece by piece in order to minimize the environmental impacts. However, when the instability of the eastern span was discovered in September 2018, it was decided to destroy it outright.[44] The explosive demolition of the eastern approach took place on January 15, 2019,[48] [49] while the western approach was lowered onto a barge on May 12, 2019, and hauled away.[50]

Structural problems

Reports of a coverup of structural problems emerged in December 2018. Dozens of bolts holding the steel girders together had failed, and some bolts broke more than a year after they had been tightened into the plates that hold the girders together. A presentation by a whistleblower included allegations that the bolts had broken due to hydrogen embrittlement, which weakened the metal.[51] The number of failed bolts was abnormally high for a project the size of this bridge. Engineering experts warned that the structural problems could compound, causing the girders to fall and the bridge to collapse.[52]

The issue was known as early as February 2016, when New York state officials had begun testing some bolts for breaks. The Attorney General of New York began investigating whether structural problems with the bridge had been covered up in 2017. According to a report in the Times Union, the attorney general's office relied on other investigations of the bridge instead of conducting its own investigations, and the office did not treat the allegations as serious. Third-party consultant Alta Vista conducted its own study, concluding in late 2017 that hydrogen embrittlement was not the cause of the broken bolts.

In March 2021, some records relating to the case were unsealed.[53] [54] Following this, U.S. Representative Mondaire Jones, whose district encompasses the bridge, and all Republican members of the New York State Assembly requested that the United States Department of Transportation investigate the allegations of structural deficiencies.[55] [56] In response, the Federal Highway Administration issued a statement claiming it had "no safety concerns" with either of the Tappan Zee Bridge's spans.[57] [58] In a lawsuit filed that month, a whistleblower claimed that TZC had knowingly delivered many defective high-strength bolts and taken measures to hide evidence of the defects.[59]

Description

The new Tappan Zee Bridge is composed of two cable-stayed decks and has a total length of .[60] [61] The main span of both decks is and is approached on either side by 515adj=midNaNadj=mid side spans.[62] [63] Each deck carries four lanes of traffic in one direction, plus inner and outer shoulders. The clearance below is .[64] Upon completion, the new Tappan Zee Bridge became one of the widest cable-stayed bridges in the world, having a combined width across both decks of 183feet. The new spans equal the width of the relatively short-span, cable-stayed Leonard Zakim Bridge in Boston.[65] Turkey's 3rd Bosphorus bridge, completed in 2016, has a single deck about 192feet wide. The new Tappan Zee Bridge is intended to last at least 100 years.

Each span contains four cable-stayed towers (two on each side of the Tappan Zee), with eight total across the length of the bridge. The towers are tall and lean five degrees outward from the vertical axis.[66] The towers are constructed of open-box beams, with cross beams linking the towers below each deck. The towers support a total of 192 cable stays, which consist of of steel strands. The decks of each span are composed of precast concrete panels, connected underneath by "edge girders" running parallel to the edges of each deck, as well as floor beams running perpendicularly to the deck. The cable stays are anchored to the outer faces of the edge girders underneath each span. The bridge is supported by 1,250 girders, each measuring up to long and high. They are secured to splice plates by about 500 bolts.

Bicycle-pedestrian path

The north span has a bicycle and pedestrian path, which opened on June 15, 2020. This path connects the towns of Tarrytown and South Nyack and measures 3.6 miles (5.8 km) in length. It has visitor centers at each end, named after the counties of Rockland and Westchester. Both of these contain restrooms, brochures, and interactive displays. The Westchester visitor center also has vendors that operate daily. The path is split into two lanes with bikes on the east and pedestrians on the west. The path has six scenic overlooks known as "belvederes." Each belvedere is named after a local point of interest and provides Wi-Fi, a seating area, bike racks (on most), informational kiosks, and trash cans. The path also contains LED displays for warning messages.[67] [68]

Lighting

The bridge is equipped with LEDs for the roadways and structures. The lights can be changed to a variety of colors for decorative purposes on major holidays such as Memorial Day and Christmas, traditional dates such as Mother's Day, Father's Day and St. Patrick's Day, and special commemorations throughout the year. The lighting system reportedly has the ability to be synced to music, although it has yet to be demonstrated.[69]

Tolls

The Tappan Zee Bridge charges tolls in the Westchester southbound/eastbound direction only. On weekdays, tolls are variable based on the New York State Thruway's vehicle classification system and the time of day, and are collected using a cashless toll system. On weekends, each vehicle class pays a flat rate. E-ZPass users pay the lowest rate possible, the rate normally charged from 12:00 midnight to 6:14 a.m., while other users are charged using the highest rate possible, the rate normally charged from 7:00 a.m. to 8:59 a.m. Class 2L vehicles, which have a height of less than 7.5feet and contain two axles, pay a flat rate of $7.48 at all times, $5.75 with a New York-issued E-ZPass, or $6.61 with an out-of-state E-ZPass.[70]

Public transportation

The Hudson Link BRT[71] runs the HO3, HO5, HO7, and HO7X across the bridge. In the summer months Hudson Link also runs free shuttle buses on the route of the HO7 bus.[72] Responding to widespread concerns about the lack of new public transit services, bridge planners agreed only to build one "dedicated express bus lane" in each direction for use during rush hour.[73] Construction on the new bridge's bus lanes finished in 2020, leaving one bus lane in each direction.[1] The bridge was also structurally built for expansion with commuter rail at a later date. The existing Tarrytown station of the Metro-North Railroad's Hudson Line is located about 2000feet from the new bridge's eastern landing.

Naming

During construction, the project's website referred to the crossing as the "New NY Bridge."[74] However, other sources referred to it as the "New Tappan Zee Bridge".[75] [76] Governor Andrew Cuomo signed a bill to name the bridge after his late father, former Governor Mario Cuomo, on June 29, 2017.[77] This has been met with significant opposition from residents of nearby localities, largely due to the fact the new name did not include "Tappan Zee" like its predecessor; this name has been viewed as an homage to the Tappan tribe that inhabited the area as well as Dutch settlers who arrived during the 17th century.[78] [79] [80] [81] Many, including the daughter of former New York Governor Malcolm Wilson (whose name was on the original Tappan Zee Bridge), were vocal in their opposition to the name.[82] [83] A Reclaim New York Initiative poll of Rockland and Westchester county residents found only 14.7% of respondents supported the new name.[84] [85] As of November 29, 2017, over 100,000 people had signed a Change.org petition called "Return the Cuomo Bridge its original name: The Tappan Zee. That bridge is our history."[86] [87] Despite the official name, "Tappan Zee Bridge" remains a common name for the structure.[88]

Lawmakers have proposed several bills to rename the bridge.[89] On December 6, 2017, State Assemblyman Kevin Byrne, a Republican from Mahopac in Putnam County, announced that he would introduce legislation to change the name of the bridge to the "Malcolm Wilson Tappan Zee Bridge."[90] The old Tappan Zee Bridge had been named for Wilson from 1994 to October 2017.[91] A compromise bill to rename the bridge the "Governor Mario M. Cuomo Tappan Zee Bridge" was later introduced and sponsored by both Senate Deputy Majority Leader John DeFrancisco, Republican of Upstate New York, as well as Assemblyman Byrne. On June 20, 2018, the State Senate voted 40–20 in favor of renaming the bridge. However, the effort failed after the Assembly's legislative session ended without the bill being put to a vote.[92]

After Cuomo's resignation in August 2021, another bill to change the official name to "Tappan Zee Bridge" was proposed in the New York state legislature.[93] [94] In February 2023, state senator James Skoufis sponsored another bill to change the official name of the bridge to the "Tappan Zee Bridge," becoming the first Democrat to sponsor such legislation.[95] [96]

See also

Further reading

External links

Notes and References

  1. Web site: FAQs. New NY Bridge.
  2. News: Vergari . Mark . September 7, 2018 . Photos: Governor Mario M. Cuomo bridge second span ceremony . Lohud . March 15, 2021.
  3. News: If You're Thinking of Living in Tarrytown; Rich History, Picturesque River Setting. Melvin. Tessa. August 21, 1994. The New York Times. December 30, 2007. The Dutch called this point, the river's widest, the Tappan Zee – Tappan probably for a group of Indians and Zee meaning "sea" in Dutch..
  4. Web site: Thruway Fact Book . New York State Thruway Authority . February 27, 2010.
  5. News: The Thruway Bridge Opens . The New York Times . December 15, 1955 . 36 . February 27, 2010.
  6. Web site: Tappan Zee Bridge 1955: Best, Longest, Safest. March 16, 2012 . nyacknewsandviews. February 5, 2013.
  7. News: A Bridge That Has Nowhere Left to Go . Patrick. McGeehan. The New York Times . January 17, 2006. February 27, 2010.
  8. Web site: About the Project . 2018 . The New NY Bridge . New York State Thruway Authority . May 21, 2018 . Why Replace the Tappan Zee Bridge? The Governor Malcolm Wilson Tappan Zee Bridge opened to traffic in 1955 and, until its retirement on October 6, 2017, was a vital artery for residents, commuters, travelers and commercial traffic. Bridge traffic grew to about 140,000 vehicles per day in 2016, far more than the Tappan Zee was designed to support. Heavy traffic, narrow lanes and the lack of emergency shoulders had the potential to create unsafe driving conditions. As a result, the bridge had twice the average accident rate per mile as the rest of the 570-mile Thruway system. Hundreds of millions of dollars were spent to maintain the structure in recent years, and the cost of maintaining it for the foreseeable future rivaled the cost of the new bridge, with no improvements to current traffic conditions. The New York State Thruway Authority retired the bridge on Oct. 6, 2017, after nearly 62 years of service..
  9. News: Tappan Zee Bridge has received 'poor' ratings. Poughkeepsie Journal . Gannett News Service . August 3, 2007 . August 9, 2008.
  10. Web site: Long List of Level 1 Alternatives . Tappan Zee Bridge Replacement . New York State . November 7, 2011 . Thruway Authority . MTA Metro-North Railroad . June 2003.
  11. News: Zhao. Yilu . From 156 Options, Down to 15 Ways to Go on Tappan Zee . November 7, 2011 . New York Times . July 24, 2003.
  12. Web site: Alternatives Analysis Report, Level 2 . Tappan Zee Bridge Replacement . New York State . November 7, 2011 . Department of Transportation . Thruway Authority . MTA Metro-North Railroad . January 2006.
  13. Web site: Tappan Zee Hudson River Crossing Project Scoping Information Packet. October 26, 2011. US Federal Highway Administration. Federal Highway Administration. October 13, 2011. dead. https://web.archive.org/web/20111030101223/http://www.tzbsite.com/tzbsite_2/pdf-library_2/2011-10-13%20Scoping%20Information%20Packet.pdf. October 30, 2011.
  14. Tappan Zee Bridge Project Enters Next Phase, Request for Proposal is Released . March 16, 2012 . February 28, 2019 . New York State.
  15. Web site: New NY Bridge Project to Replace Tappan Zee, Gets Final Contract Approval.
  16. Web site: Cheapest Proposal Chosen for the New Tappan Zee Bridge . Curbed New York . December 17, 2012 . February 28, 2019.
  17. News: NY proposes steep toll increases for new Tappan Zee bridge. August 4, 2012. Reuters.
  18. Web site: Tappan Zee tolls frozen until 2020. April 7, 2016. News 12 Westchester. News 12 Networks. August 1, 2016.
  19. Plotch, Philip Mark. Politics Across the Hudson: The Tappan Zee Megaproject. Rutgers University Press, New Jersey (2015). p. 165-168
  20. https://archive.today/20130118200330/http://www.businessweek.com/news/2012-09-25/cuomo-s-tappan-zee-plan-gets-u-dot-s-dot-approval-in-obama-fast-track
  21. Web site: New York State Advances $3.1 Billion Plan To Replace Tappan Zee Bridge. December 17, 2012 . CBS News New York. December 18, 2012.
  22. Web site: From Tappan Zee to Javits, how Cuomo's plans boost public-private partnerships. Mary Scott Nabers. Feb 12, 2016. New York Business Journal. November 9, 2018.
  23. News: September 28, 2014. Governor Cuomo Announces Beginning of Formal Construction of the New NY Bridge to Replace Tappan Zee. en. Office of Governor Andrew M. Cuomo. August 29, 2017. August 29, 2017. https://web.archive.org/web/20170829082629/https://www.governor.ny.gov/news/governor-cuomo-announces-beginning-formal-construction-new-ny-bridge-replace-tappan-zee. dead.
  24. Web site: October 16, 2013. New Tappan Zee construction starts. August 29, 2017. New York Post. Associated Press.
  25. News: Haughney. Christine. October 11, 2011. U.S. Says It Will Expedite Approval to Replace Deteriorating Tappan Zee Bridge. New York Times. November 7, 2011. The state will pay for the project by issuing $3 billion in bonds against its toll revenues; the remaining $2.2 billion will be financed with loans from labor pension funds and the Transportation Infrastructure Finance and Innovation Act..
  26. Web site: Tappan Zee Hudson River Crossing . October 2014.
  27. News: Goldmacher. Shane. 2018-12-14. Attorney General Investigating Broken Bolts on Mario Cuomo Bridge. en-US. The New York Times. 2021-08-16. 0362-4331.
  28. Web site: Hudson River PCB Dredging Project . Hudsondredging.com . April 24, 2016.
  29. Web site: Crane collapse on Tappan Zee Bridge injures at least 5; all lanes closed in both directions. NY Daily News. July 19, 2016.
  30. Web site: Four Hurt When Crane collapses onto Tappan Zee Bridge. July 19, 2016 . NY Post. July 19, 2016.
  31. Web site: About the project. New York State Thruway Authority. June 12, 2016.
  32. News: Opening day on new Tappan Zee Bridge shows sleek design, new features. August 27, 2017. en.
  33. News: Watch drone video of New York's new Tappan Zee Bridge. USA TODAY. August 27, 2017. en.
  34. News: Rockland-bound traffic to begin traveling on new Tappan Zee Bridge. August 26, 2017 . ABC7 New York. August 27, 2017. en-US.
  35. Web site: Gov. Cuomo Opens Thruway Bridge Across the Hudson Amid Questions About Tolls. DeWitt. Scott Willis, Karen. August 24, 2017 .
  36. Web site: Cold weather halts work on Gov. Mario M. Cuomo Bridge until March . Coyne . Matt . January 19, 2018 . lohoud . May 2, 2018.
  37. Web site: About. October 12, 2015. The New NY Bridge Project. en-US. August 1, 2016.
  38. News: Westchester-bound span of Cuomo bridge should be finished in mid-September: Governor. McKinney. Michael P.. August 28, 2018. The Journal News. August 31, 2018. en.
  39. Web site: Cuomo Bridge second span will open Saturday, enhanced bus service to start Oct. 29 . The Journal News . September 4, 2018 . September 6, 2018.
  40. Web site: Here's New Tappan Zee Bridge Traffic Shift Info, Timing For Second Span Opening . Greenburgh Daily Voice . January 27, 2018 . September 6, 2018.
  41. Web site: An 'Inappropriate' Mailer and a Delayed Bridge Opening Put Cuomo on the Defensive . The New York Times . September 9, 2018 . September 11, 2018.
  42. Web site: Vielkind . Jimmy . A bridge for Mario Cuomo, dedicated with love . Politico PRO . September 7, 2018 . September 11, 2018.
  43. Web site: 'Potentially Dangerous Situation' on Tappan Zee Delays Opening of New Cuomo Bridge Span . The New York Times . September 8, 2018 . September 9, 2018.
  44. News: Mays . Jeffery C. . Explosives to Be Used in the Demolition of a Tappan Zee Bridge Span . January 15, 2019 . The New York Times . January 5, 2019.
  45. Web site: Mario Cuomo Bridge: New opening date set; contractors deem Tappan Zee Bridge 'stable' . lohud.com . September 10, 2018 . September 11, 2018.
  46. News: Coyne . Matt . Gov. Mario M. Cuomo Bridge's second span opens to traffic . January 15, 2019 . Journal News . September 11, 2018.
  47. News: Coyne . Matt . Tappan Zee Bridge demolition timeline . January 15, 2019 . The Journal News . September 7, 2018.
  48. News: Photos: Tappan Zee Bridge demolition . The Journal News . January 15, 2019 . January 15, 2019.
  49. Web site: Farewell to Thee, Our Old Tappan Zee! Bridge Demolished With Explosives. NBC New York 4. January 15, 2019 . en. January 15, 2019.
  50. Web site: Tappan Zee: Final section of bridge is removed . Lohoud . en . May 13, 2019.
  51. Web site: Jonathan Dienst. Jaxon Van Derbeken. Paredes. David. December 13, 2018. I-Team: Whistleblower Alleges Cover-up of Past Bolt Failures on New Cuomo Bridge. August 16, 2021. NBC New York.
  52. Web site: Lyons. Brendan J.. August 12, 2021. Structural problems on Mario Cuomo bridge were covered up. August 16, 2021. Times Union.
  53. News: Broken bolts: Structural problems on the Gov. Mario M. Cuomo Bridge were covered up . Times Union . Brendan . Lyons . March 7, 2021 . en . March 13, 2021.
  54. Web site: Lahut. Jake. March 9, 2021. Andrew Cuomo has a new scandal, and it's the 'structural safety' of a bridge named after his father. August 16, 2021. Business Insider.
  55. News: Berger. Paul. 2021-03-15. Congressman Urges Safety Probe of Gov. Mario M. Cuomo Bridge. en-US. Wall Street Journal. 2021-08-16. 0099-9660.
  56. Web site: Arbetter. Susan. March 10, 2021. Republicans Want Investigation Into Governor Mario M. Cuomo Bridge. August 16, 2021. spectrumlocalnews.com.
  57. Web site: Taliaferro. Lanning. March 23, 2021. Cuomo Bridge Is Safe: Federal Highway Administration. August 16, 2021. Nyack-Piermont, NY Patch.
  58. Web site: March 23, 2021. Federal Highway Administration Vouches for Cuomo Bridge Safety. August 16, 2021. The Hudson Indy Westchester's Rivertowns News -. hr.
  59. Web site: March 28, 2021. Unsealed records allege a cover up of safety concerns on Gov. Mario M. Cuomo Bridge. August 16, 2021. WRGB.
  60. Web site: About the Project. The New NY Bridge. New York State Thruway Authority. October 4, 2013 . 2013 . https://web.archive.org/web/20140111013055/http://www.newnybridge.com/about/index.html . January 11, 2014.
  61. Web site: Old Tappan Zee Bridge plunges into the Hudson River in spectacular controlled explosion . ABC News . January 15, 2019 . August 16, 2021.
  62. Web site: Fries . Brianna . The Mario M. Cuomo Bridge Provides New Infrastructure and Artistic Architecture to Community . American Infrastructure . January 7, 2019 . August 16, 2021.
  63. Web site: Tappan Zee Hudson River Crossing . STRUCTURE magazine . November 5, 2012 . August 16, 2021.
  64. Web site: Design Features. The New NY Bridge. New York State Thruway Authority. December 9, 2017.
  65. Web site: Massachusetts Department of Transportation. MassDOT — The Big Dig — Tunnels and Bridges — The Cable-stayed Bridge. April 5, 2014. Girders, floor beams and two planes of cables support the bridge's 745-foot-long, 183-foot-wide main span..
  66. Web site: Cho. Aileen. September 13, 2018. New York's Old Tappan Zee Bridge Won't Go Out Quietly. August 16, 2021. Engineering News-Record.
  67. News: Keane . Isabel . Cuomo: Bike-pedestrian bridge path opens as 'home run' for region . 16 June 2020 . Lohud.com . 16 June 2020.
  68. Web site: Westchester Landing Path Vendor Schedule . New York State Thruway Authority . July 15, 2020 . Gov. Mario Cuomo M. Bridge . March 18, 2021.
  69. Web site: Why do Gov. Mario M. Cuomo Bridge lights change colors for special occasions, holidays. Frank. Esposito. Lohud.com. December 17, 2019.
  70. Web site: November 7, 2014. Incentive Pricing Toll Schedules - Cashless Tolling. April 10, 2023. New York State Thruway.
  71. Web site: Hudson Link map of Rockland and Westchester County . New York State Department of Transportation . October 2018 . Hudson Link . March 18, 2021.
  72. Web site: Bus Service to the Governor Mario M. Cuomo Bridge Path . New York State Department of Transportation . Hudson Link . March 18, 2021.
  73. News: Nicosia . Mareesa . New Tappan Zee Bridge: Nyack residents voice traffic, noise, toll concerns . September 11, 2012 . The Journal News . August 15, 2012 . Westchester & Rockland Counties, New York . [E]ight general-purpose lanes would be flanked on each side by wide shoulders, which would allow emergency vehicles to pass traffic. One-shoulder on each side of the bridge would serve as a dedicated express bus lane. . dead . https://web.archive.org/web/20131230235918/http://lohud.com/article/20120816/NEWS03/308160055/New-Tappan-Zee-Bridge-Nyack-residents-voice-traffic-noise-toll-concerns . December 30, 2013 .
  74. Web site: The New NY Bridge Project. www.newnybridge.com. en-US. August 27, 2017.
  75. Web site: New Tappan Zee Bridge to Open Westbound Side Aug 25, 2017 - Visit Nyack. August 22, 2017.
  76. Web site: Views From the New Tappan Zee Bridge.
  77. Web site: Bridge of Grand Ambitions Is Set to Open at the Tappan Zee. Joseph. Berger. August 24, 2017. The New York Times.
  78. Web site: Woyton . Michael . Petition Asking For Bridge Name Change Delivered To Albany . Patch.com . December 11, 2018 . en . June 12, 2018.
  79. Web site: Conley . Kirstan . Musumeci . Natalie . Thousands sign petition to change Cuomo Bridge back to Tappan Zee . New York Post . en . November 13, 2017.
  80. Web site: Fink . Zack . Petition calls for Mario Cuomo Bridge to return to old name . NY1 . December 11, 2018 . en.
  81. Web site: Fight over bridge name: Is it the Tappan Zee or Mario Cuomo? . News12.com . News 12 Networks . December 11, 2018 . en.
  82. News: Daughter wants to keep Malcolm Wilson's name on Tappan Zee Bridge. Campbell. Jon. June 22, 2017. Coloradoan. June 22, 2017.
  83. News: Cuomo Bridge name opposition grows: Tax Watch. Wilson. David McKay. November 23, 2017. The Journal News. November 23, 2017.
  84. News: Poll: Downstate residents dislike naming Tappan Zee bridge for Mario Cuomo. July 11, 2017. Capitol Confidential. October 7, 2017. en-US.
  85. News: Tappan Zee Bridge gets new name: The Governor Mario M. Cuomo Bridge. June 29, 2017. Lohud/The Journal News. June 30, 2017.
  86. News: Petition drive to change Gov. Mario Cuomo Bridge back to the Tappan Zee. November 14, 2017. WABC-TV.
  87. News: Thousands sign petition to change Cuomo Bridge back to Tappan Zee. Conley. Kirstan. November 13, 2017. New York Post. November 29, 2017. Musumeci. Natalie. en-US.
  88. Web site: NY Has to Replace New Bridge Signs . August 15, 2019.
  89. Web site: Everyone Still Mad About Bridge Andrew M. Cuomo Named the Mario M. Cuomo Bridge . March 23, 2022 .
  90. Web site: Wilson . David McKay . Tax Watch: Lawmaker plans bill to rename Cuomo Bridge as Tappan Zee Bridge . The Journal News . December 6, 2017 . February 22, 2023.
  91. Web site: Daughter wants to keep Malcolm Wilson's name on Tappan Zee Bridge . Lohud . June 22, 2017 . December 9, 2017.
  92. Web site: Push to restore Tappan Zee Bridge name comes up short in Albany . The Journal News . June 21, 2018 . January 16, 2019.
  93. Web site: Baquero . Lynda . Bring Back The Tappan Zee? Legislation Aims to Scrap Cuomo Name from NY Bridge . NBC New York . August 13, 2021 . August 16, 2021.
  94. Web site: Push to change Governor Mario Cuomo Bridge, back to Tappan Zee Bridge . ABC7 New York . August 13, 2021 . August 16, 2021.
  95. Web site: Tlaige . Amal . 20 February 2023 . Mario M. Cuomo Bridge could face name change . 21 February 2023 . WTEN.
  96. Web site: Kramer . Marcia . Powerful sponsor comes up with new bill to change name of Gov. Mario Cuomo Bridge back to Tappan Zee . CBS News . February 21, 2023 . February 22, 2023.