Tanzania Liquefied Natural Gas Project Explained

Tanzania Tanzania Liquefied Natural Gas Project
Location Map:Tanzania
Coordinates:-9.96°N 39.7089°W
Country:Tanzania
Province:Lindi, Lindi Region, Tanzania
City:Lindi
Founded:2025 (Expected)
Cost:US$30 billion

The Tanzania Liquefied Natural Gas Project (TLNGP), also Likong’o-Mchinga Liquefied Natural Gas Project (LMLNGP), is a planned liquefied natural gas processing plant in Tanzania.[1] [2]

Location

The plant would be located on approximately 2071.705ha in Likong'o Village in the town of Lindi on the Indian Ocean coast, approximately 461km (286miles), by road, south of Dar es Salaam. This is about 103km (64miles), by road, north-west of Mtwara, the nearest large town.

Overview

Tanzania has proven natural gas reserves of 57 trillion cubic feet,[3] with at least 49.5 trillion cubic feet of those reserves far offshore in the Indian Ocean.[4] The government of Tanzania through the Tanzania Petroleum Development Corporation, in partnership with the BG Group (a division of Shell), Equinor, ExxonMobil, and Ophir Energy, plans to build an onshore liquefied natural gas export terminal at this location in Lindi.[5]

History

The first offshore discovery of natural gas in Tanzania was made in 2010.[4] Since then, other finds have been made by several petroleum prospecting companies, which decided in 2014 to build a liquefaction facility in Lindi, targeting primarily the Asian market.[6] In August 2016, Tanzanian President John Magufuli publicly urged government bureaucrats to fast track the project so that construction could start.[7] The government of Tanzania announced in May 2016 its plan to build a gas pipeline to neighboring Uganda.[8]

Stakeholders

Talks between the government of Tanzania and the six oil companies involved in the project began in earnest in September 2016.

As of 2022, the oil companies currently involved include:[9]

Also participating in the talks are the following parastatal agencies of the Tanzanian government.[9]

Negotiations

In May 2018, The East African reported that the government of Tanzania was searching for a transaction adviser, to guide the Tanzania Petroleum Development Company through negotiations for a Host Government Agreement with the gas project developers. The two year contract for the selected adviser involves the development of a technical, legal and commercial framework for the LNG project. The adviser is also responsible for supporting and building capacity of the government team, as well as crafting the appropriate strategy in the negotiations towards the "host government agreement".[10] In June 2018, the Tanzanian English-language newspaper, The Citizen, reported that the projected start date was now in 2022.[11] [12] In 2022, the government nailed an agreement with the companies for the construction of the LNG. A team of experts is in negotiations with some investors as the project will be executed in Lindi region. [13] The project is all set to begin soon.[14]

Construction

In May 2019, the EastAfrican newspaper reported that construction was planned to start in 2022 and conclude in 2028, as announced by the Tanzanian Minister of Energy, Medard Kalemani.[15] In June 2022, the government of Tanzania signed agreements with Equinor of Norway and British Shell, reviving discussions and negotiations about moving the project forward. Final investment decision (FID) of this project, whose development cost is projected at US$30 billion, is now expected in 2025.[16]

In May 2023, TanzaniaInvest reported that Jared Kuehl, Shell's Vice President for Tanzania and Country Chair, disclosed that in the coming weeks, the International Energy Companies (IECs) involved in the Tanzania LNG project anticipated signing a Host Government Agreement (HGA) for the onshore elements of the project and a Production Sharing Agreement (PSA) for its upstream component[17]

However, there were no official updates from the parties involved after that announcement. In March 2024, the United States issued a serious warning to Tanzanian authorities regarding delays in finalizing negotiations for the country's lucrative liquefied natural gas (LNG) project[18]

In May 2024, The Citizen newspaper reported that Tanzania's Attorney General raised queries on the draft HGA submitted for his vetting[19]

See also

External links

Notes and References

  1. Web site: Tanzania says LNG project could cost up to $30 bln . . 13 November 2014 . Fumbuka Ng'wanakilala . 29 April 2024.
  2. Web site: . Tanzania’s gas plant and Bagamoyo port top EA’s $75.5b mega projects . 3 February 2020 . James Anyanzwa . 7 February 2020 . Nairobi, Kenya.
  3. Web site: Gas fuels Tanzania, Mozambique growth . 22 September 2016 . 30 August 2016 . Neil . Ford . The Africa Report.
  4. Web site: Tanzania Sees Decision on $15 Billion LNG Project in Three Years . 24 August 2016 . 19 June 2015 . Rakteem . Katakey . Bloomberg News.
  5. Web site: 9 February 2016 . Tanzania LNG project makes progress . African Influence Exchange . 24 August 2016 . Mining.com.
  6. Web site: Holter . Statoil, BG to Build Tanzania LNG Plant in Lindi, Minister Says . 24 August 2016 . Mikael . 14 February 2014 . Bloomberg News.
  7. Web site: Tanzania's President Magufuli orders officials to speed up LNG project . 24 August 2016 . 23 August 2016 . Fumbuka . Ng'wanakilala . Nairobi . The EastAfrican.
  8. Web site: Tanzania upstages Mozambique on gas . 28 August 2016 . . 28 August 2016 . Allan Olingo . Nairobi, Kenya.
  9. Web site: 18 September 2016 . Tanzania explores construction of LNG plant, export terminal. 18 September 2016 . Kennedy . Senelwa . Nairobi . .
  10. Web site: 19 May 2018 . Tanzania shops for advisers on $30b gas project . 14 May 2018 . . Allan . Olingo . Nairobi.
  11. Web site: 27 June 2018. Tanzania's Natural Gas Plant Construction to Start in 2022 . 26 June 2018 . . Samuel . Kamndaya . Dar es Slaam.
  12. Web site: 21 March 2019 . LNG Project On The Right Track: Director . 21 March 2019 . . Mirondo . Rosemary . Dar es Salaam.
  13. Web site: Tanzania: How Tanzania is Bagging Billions in Natural Gas Investments. All Africa. May 3, 2022.
  14. Web site: TANZANIA TO SIGN THE 70TRI/- LNG PROJECT NEXT WEEK. Daily News Tanzania. June 4, 2022.
  15. Web site: 29 May 2019 . Tanzania Says Construction of LNG Plant To Start In 2022 . . 29 May 2019 . The EastAfrican Quoting Reuters . Nairobi, Kenya.
  16. Web site: . 11 June 2022 . Tanzania signs LNG framework agreement with Equinor and Shell . 24 August 2022 . Nuzulack Dausen and Gwladys Fouche.
  17. Web site: TanzaniaInvest . 22 May 2023 . Energy Companies Agree Deal for Tanzania's LNG Project, Approvals to Be Signed Soon . 31 May 2024 . TanzaniaInvest . Dar es Salaam, Tanzania.
  18. Web site: LNG Project Delays Could Lead To Investor Withdrawal, U.S. Warns Tanzania . 4 March 2024 . TanzaniaInvest . 31 May 2024 . TanzaniaInvest . Dar es Salaam, Tanzania.
  19. Web site: 30 May 2024 . LNG project: It's back to the negotiating table . . 31 May 2024 . Dar es Salaam, Tanzania.