Subansiri Lower Project | |
Name Official: | Subansiri Lower Hydroelectric Power Project (LSHEP) |
Location Map: | India |
Location Map Caption: | Location of the Subansiri Lower Dam in Arunachal Pradesh and Assam |
Coordinates: | 27.5536°N 94.2586°W |
Country: | India |
Location: | Arunachal Pradesh |
Status: | UC |
Construction Began: | December 2007 |
Cost: | Rs. 62.9 billion (December 2002 est.) |
Owner: | NHPC Limited |
Dam Type: | Concrete gravity |
Dam Height: | 1160NaN0 |
Dam Height Foundation: | 1300NaN0 |
Dam Length: | 2840NaN0 |
Dam Volume: | 22500000NaN0 |
Dam Crosses: | Lower Subansiri River |
Spillway Type: | Ski jump |
Spillway Capacity: | 375000NaN0 |
Res Capacity Total: | 1.37km3 |
Res Capacity Active: | 0.44km3 |
Res Surface: | 33.50NaN0[1] |
Plant Operator: | NHPC Limited |
Plant Commission: | 2016-2018 (est.) |
Plant Turbines: | Francis-type |
Plant Capacity: | 2,000 MW (max. planned) |
Plant Annual Gen: | 7,421 GW·h |
Website: | Subansari (Lower) Project |
The Subansiri Lower Dam, officially named Subansiri Lower Hydroelectric Project (SLHEP), is an under construction gravity dam on the Subansiri River in North Eastern India. It is located 2.3km (01.4miles) upstream of Subansiri River on Arunachal Pradesh. Described as a run-of-the-river project by NHPC Limited, the Project is expected to supply 2,000 MW of power when completed. The project has experienced several problems during construction to include landslides, re-design and opposition.
By early 2019, work had stalled on both of the two major dam projects in the Assam region, the Dibang and the Lower Subansiri.[2] The project construction resumed from October 15, 2019, after the clearance by National Green Tribunal.[3] The remaining work of radial gates was expected to be completed after the monsoon season and electricity generation was expected to begin by the end of Financial Year 2023-24.
Subansiri Lower Dam bridge | |
Carries: | vehicles |
Width: | 1500NaN0 |
Length: | 1500NaN0 |
The concrete gravity dam is designed to be 116m (381feet) tall, measured from the river bed and 210m (690feet) from the deepest foundation. Its length will be 2840NaN0 and the dam will have a structural volume of 22500000NaN0. The reservoir created by the dam will have a gross storage capacity of 1.37km3, of which 0.44km3 can be used for power generation or irrigation. At normal level, the reservoir's surface will cover 33.50NaN0. The surface powerhouse, located on the right bank, will contain eight 250 MW Francis turbine generators using 86 m design head out of 91 m gross head available.[1] [4]
There will be eight horse shoe shaped head race tunnels, each being 9.5m (31.2feet) in diameter and having a length from 608m-1168mm (1,995feet-3,832feetm). There will be eight horse Shoe shaped surge tunnels, each being 9.5m (31.2feet) in diameter and having length from 400m-485mm (1,300feet-1,591feetm). There will be eight horse shoe/circular shaped penstocks with varying diameters of 7m-9.5mm (23feet-31.2feetm) and lengths of168m-190mm (551feet-620feetm). The tail race channel, which will transfer water discharged by the turbines back to the river, is 206m (676feet) wide and 35m (115feet) long.[4]
When complete, the hydroelectric generators will begin generating 500 MW of electricity, gradually increasing to 2000 MW. [5]
Construction of Subansiri Lower Project involves many challenges. These include land not being available when construction was scheduled to commence, a limited annual construction time because of monsoons (from mid-April to mid-October), the need to handle high flood flows and poor rock conditions. The design of the dam has undergone drastic and repeated revisions that have affected the schedule and planning of the construction work.[6]
In December 2003 the contract to build the dam and its associated structures was awarded to a consortium of Boguchandgesstroy, Soyuzgidrosptsstry and Soma Enterprise Ltd. Due to difficulties acquiring land around the site, construction could not begin in earnest until 13 months after the contract was awarded. Unexpected geological conditions at the dam site led to landslides and slower tunnel excavation. By November 2007, the river was successfully diverted and in April of the next year, the foundation was clear for construction. Before the foundation was fully prepared it was discovered that bedrock was reached 100NaN0 sooner than expected. This led to an alteration in the dam's design for stability. While the dam was being re-designed, concrete was placed over the foundation to protect it from the upcoming monsoon floods as the cofferdams stood a good chance of not protecting the foundation from the strong floods. The re-design was completed in October 2008 and soon after the foundation was once again cleared. In May 2009, work was suspended because of the monsoon season and re-commenced in November of that year.[6]
As of November 2011, the dam reached an elevation of 138m (453feet), just below the spillway elevation of 145m (476feet). On 16 December 2011, construction equipment was halted by protests.[7]
The construction cost has gone up by about 1,200 crore owing to forced suspension of work since December 2011. NHPC has already spent about 6,600 crore, according to a status report prepared by the company.[8]
By mid-2023, the elevation of the dam had reached 210m above sea level.[9]
In October 2023, another landslide impacted construction, as part of a hill collapsed into the reservoir, blocking a tunnel and stopping water flowing into the Subansiri river.[10]
Some environmental impacts unique to very large dams will result from completion of the Subansiri Project, both upstream and downstream of the dam site. These impacts will include ecosystem damage and loss of land.
The reservoir of the Subansiri Project will submerge a 47km (29miles) length of the Subansiri river and occupy 37.5km240km2 which includes Himalayan subtropical pine forests, Himalayan subtropical broadleaf forests, part of the Tale Valley Wildlife Sanctuary, an elephant corridor and some subsistence agriculture fields.[11]
Thirty eight families will be displaced if the dam is completed, according to official data.[12]
The project has met stiff resistance from several groups including All Assam Students’ Union and the Krishak Mukti Sangram Samiti, who are apprehensive about safety and the project’s downstream impact.[8]