Stuttgart–Wendlingen high-speed railway explained

Stuttgart–Wendlingen high-speed railway
Native Name:Neubaustrecke Stuttgart–Wendlingen
Native Name Lang:de
Linenumber:4813[1]
Linelength:~25.21NaN1
Electrification:15 kV/16.7 Hz AC overhead catenary
Tracks:2
Maxincline:2.8%[2]
Speed:250abbr=onNaNabbr=on
Locale:Baden-Württemberg, Germany
Map State:https://en.wikipedia.org/w/index.php?title=Stuttgart%E2%80%93Wendlingen_high-speed_railway&action=edit#

The Stuttgart–Wendlingen high-speed railway is an under construction German high-speed line being built as part of the Stuttgart 21 project. It runs from Stuttgart Hauptbahnhof via the Filder Tunnel to the Filder plain and from there to the Neckar valley at Wendlingen, where it runs on to the Wendlingen–Ulm high-speed line. It is part of the Paris-Bratislava corridor as defined by the European Union.

The line will connect the new Filder station via the Airport Loop, and another line will connect to the existing airport station.

The design speed of the approximately 25.2 km line is mostly 250abbr=onNaNabbr=on. As of 2023, it is planned to enter in commercial service in December 2025 (one year delay compared to the expectation from 2017).[3] [4] [5]

Route

The line runs from Stuttgart station to the south through the 9,468 metre long Filder Tunnel and surface southwest of Stuttgart-Plieningen near Stuttgart Airport and the A8 autobahn. It then runs to the east parallel with the A8 on its north side for about 10 kilometres to the Denkendorf service area. Between Denkendorf and Neuhausen the line runs under the A 8 in a 768 m long Denkendorf Tunnel and then runs parallel with it on its south side to the southeast. On the western abutment of the Neckar Bridge at Wendlingen the line becomes the proposed Wendlingen–Ulm high-speed line.

Notes and References

  1. DB Projekt GmbH Stuttgart 21 (ed.): Umgestaltung des Bahnknotens Stuttgart: Ausbau- und Neubaustrecke Stuttgart – Augsburg. Bereich Stuttgart–Wendlingen mit Flughafenanbindung. Planfeststellungsabschnitt 1.2 Fildertunnel. Bau-km 0.432 – km 10,030
    Übersichtshöhenplan Gleisplanung, km 0,432 ... 2,191
    . Plan of November 2001, released on 10 December 2001, Anlage 2.6 of the zoning decision, sheet 1 of 4, plan established by order of the Federal Railway Office, Karlsruhe/Stuttgart branch.
  2. H. Dieterle . Stuttgart 21 – Ein Jahrhundertprojekt auf dem Weg zur Realisierung . Tiefbau . 9. 1998 . 614–620 . PDF. 6 January 2017. de. Alt URL
  3. https://www.bahnprojekt-stuttgart-ulm.de/projekt/ueberblick/projektstatus/ "Bahnprojekts Stuttgart-Ulm, Projektstatus"
  4. Stuttgart 21 wird wohl eine Milliarde Euro teurer – und ein Jahr später fertig . Der Spiegel . 29 November 2017 . Michael Kröger . 6 January 2018. de.
  5. Woche der Wahrheit für Stuttgart 21 . Der Spiegel . 12 December 2017 . Claus Hecking . Gerald Traufetter . 6 January 2018. de.