Steenbras Power Station Explained

Steenbras Power Station
Location Map:Cape Town#Western Cape#South Africa
Location Map Caption:Map of South Africa showing the location of Steenbras Power Station
Location Map Alt:34°09'08.0"S 18°53'43.0"E
Coordinates:-34.1522°N 18.8953°W
Country:South Africa
Location:City of Cape Town, Western Cape
Purpose:P
Status:O
Opening:1979
Owner:City of Cape Town
Operator:City of Cape Town
Dam Crosses:Steenbras River
Plant Turbines:4 x 45 MW
Plant Annual Gen:~250 GWh

The Steenbras Power Station, also Steenbras Hydro Pump Station, is a 180 MW pumped-storage hydroelectric power station commissioned in 1979 in South Africa. The power station sits between the Steenbras Upper Dam and a small lower reservoir on the mountainside below. It acts as an energy storage system, by storing water in the upper reservoir during off-peak hours and releasing that water to generate electricity during peak hours. The City of Cape Town uses the power station for load balancing and to mitigate against loadshedding caused by the South African energy crisis.[1] This power station is reported to be the first pumped-storage hydroelectric power station to be built on the African continent.[2]

Location

The Steenbras Upper Dam impounds the Steenbras River at an altitude of approximately 375 metres in the Hottentots Holland Mountains, upstream of the original Steenbras Dam (which is not part of the hydroelectric scheme). The Steenbras Power Station and the scheme's lower reservoir are situated on the lower slopes of the mountain at an altitude of approximately 100 metres, close to the town of Gordon's Bay and 50km (30miles) to the south-east of central Cape Town. A series of tunnels connects the upper reservoir to the power station.

Operation

The power station is operated by the Electricity Department of the City of Cape Town.[3] It consists of four hydroelectric turbines, each rated at 45 MW, for a total capacity of 180 MW. During peak hours, water from the upper reservoir is used to turn the turbines to generate clean energy.[2] During off-peak hours (from 11pm until 7am), the same hardware, this time functioning as electric pumps, uses electricity purchased from the national grid to pump water from the lower reservoir back into the upper reservoir. The process is repeated, as the need arises and as hydrodynamic capacity allows.[2]

The output of the power station is generally constrained by the capacity of the lower reservoir. At maximum output the station can run for about twelve hours before the lower reservoir is full; in practice it is typically run for four to five hours a day. In winter, which is the rainy season in that part of South Africa, if the upper reservoir is sufficiently full, water can be released from the lower reservoir to the Faure water treatment works instead of being pumped back up.[4]

See also

External links

Notes and References

  1. Web site: . How the City of Cape Town managed to avoid Stage 6 load shedding thanks to hydroelectric scheme . 30 Jun 2022 . Victoria O'Regan and Onke Ngcuka . 1 June 2022 . Johannesburg, South Africa.
  2. Web site: Steenbras Plant Ready To Provide Alternative Energy . Cape Costal Homes/City Country Homes South Africa (CCH South Africa) . 3 May 2019 . CCH South Africa . 1 July 2022 . Cape Town, South Arica.
  3. Web site: . About Steenbras Dams . 1 July 2022 . City of Cape Town . 1 July 2022 . Cape Town, South Africa.
  4. Web site: Journals.co.za . December 2015 . Water and Energy: Hydropower – Keeping The Lights On In The Mother City . The Water Wheel . 1 July 2022 . Cape Town, South Africa.