Spain-Morocco interconnection | |
Country: | Spain, Morocco |
Direction: | north–south |
Start: | Tarifa |
Through: | Strait of Gibraltar |
Finish: | Fardioua |
Partners: | Morocco’s National Office of Electricity, Red Eléctrica de España |
Est: | 1997 |
Type: | subsea cable |
Current Type: | AC |
Length Km: | 59 |
Capacity: | 800 MW |
Ac Voltage: | 400 kV |
Spain-Morocco interconnection is a submarine power cable between Tarifa terminal in Spain and Fardioua terminal in Morocco. The purpose of the cable is to connect energy infrastructure between Europe and Africa.[1] [2]
The Spain-Morocco interconnection includes two 400 kV lines, commissioned in 1997 and 2006 that have a combined power of 800 MW and consisting of seven cables: three for each circuit, plus one for reserve.[3]
The two countries are planning to extend the network building a third 400-kV link with a 700 MW capacity. The cost of the project is expected to be $169 million, shared equally between Spain and Morocco.[4]