Argentine Interconnection System Explained

The Argentine Interconnection System (Spanish: Sistema Argentino de Interconexión, SADI) is a wide area synchronous grid that links the regional networks of all Argentinian provinces, with the exception of Tierra del Fuego. It is also connected to the power grids of several neighboring countries.[1] [2] [3] [4]

The network is 20296km (12,611miles) long, of which 14197km (8,822miles) represent 500 kV power lines.[5] These power lines are operated by Transener.[6]

History

The interconnection system began by including transmission lines and substations built by AyEE, HIDRONOR and others constructed by private initiative. Those lines primarily linked the generation centers distributed along the country with the major consumption center in the Greater Buenos Aires area.[7]

In 1947, the General Direction of Water and Electric Power was created by presidential decree, with the task of planning, construction and operation of electrical power plants, transmission lines and substations.[8] [9] [10]

In 1960, Act 15336 (Electric Energy Law) is approved, recognizing a "National Interconnection Network" that would integrate all the country's regional networks. This would change the jurisdiction of those networks from a provincial to a national control. This new national network would be controlled by a new organism to be created, the Federal Council of Electric Power, under the national Energy & Fuel Secretary structure.[11]

This new organism would have representatives of the central government as well as the provinces and the City of Buenos Aires, intending to unify criteria and not only satisfy the interests of Buenos Aires.

In 1991, the State Reform law brought privatization for the energy companies, creating a new regulatory framework for the energy and utilities sector. This would be included in the 24065 Act, which created the Wholesale Energy Market and the National Electricity Regulatory Entity (ENRE).[12] It also creates a new public entity to regulate the Interconnection, the National Cargoes Dispatch (DNDC), which would incorporate in 1002 in the form of a sociedad anónima (a private corporation) with the name Compañía Administradora del Mercado Mayorista Eléctrico Sociedad Anónima (CAMMESA).[13]

Main figures

According to the 2019 annual report by CAMMESA, that year the network showed the following figures:

Energy Demand by Region!Region!Annual Demand (in GWh)!Share %
Greater Buenos Aires48,55337.7%
Littoral15,63812.1%
Buenos Aires Province14,90311.6%
Center (Cordoba and San Luis Provinces)11,2408.7%
Northwest10,2067.9%
Northeast9,2947.2%
Cuyo8,0506.2%
Patagonia (excl. Río Negro and Neuquén)6,0784.7%
Comahue (La Pampa, Río Negro and Neuquén)4,9433.8%
Total128,905100%
Energy generation by heat source!Heat Source!Plant Type!Annual Power (in MW)
HydraulicHydropower10,812
Fossil fuelCombined cycle11,245
Natural Gas Turbine7,396
Steam Turbine4,251
Diesel1,653
NuclearNuclear1,755
Renewable EnergyWind Power1,609
Solar Energy439
Renewable hidraulic498
Biogas44
Biomass2

International links

The system connects to several neighboring countries:

2019 Blackout

See main article: 2019 Argentina, Paraguay and Uruguay blackout. On 16 June 2019, a large-scale power outage struck most of Argentina, all of Uruguay, and parts of Paraguay. It was caused by an operational misbehavior from Transener, a transmission lines operator in Argentina.[15] [16]

A short circuit which lowered demand, caused an excess of power generation in the grid, a lack of synchronization of power plants, loss of balance, and a low frequency in the network, triggering massive automatic disconnections from the grid. This caused a blackout that, in a matter of 30 seconds, came to affect 50 million users in the continent.[15]

External links

References

  1. Web site: Oieni. Antonio. 11 May 2016. De exportar a importar. 2020-08-10. El Tribuno. Salta. es.
  2. News: 10 December 1997. La Argentina y Chile estarán integradas eléctricamente. es-AR. La Nación. Buenos Aires.
  3. Web site: Interconexión Eléctrica Regional UCL. 2020-08-10. Pontifical Catholic University of Chile.
  4. News: 30 December 1999. Segunda conexión eléctrica entre la Argentina y Brasil. es-AR. La Nación. 9 August 2020.
  5. Web site: 12 June 2020. Informe anual 2019. 2019 Annual report. 2020-08-10. portalweb.cammesa.com. Compañía Administradora del Mercado Mayorista Eléctrico Sociedad Anónima. es-AR.
  6. Web site: The Argentine Electricity Sector. 2020-08-10. Pampa Energia. en-US.
  7. Gayo. Ricardo J.. August 2009. Sistema Interconectado Nacional (SIN) en 500 kV. Petrotecnia. es-AR. Argentine Institute of Oil and Gas (IAPG).
  8. Web site: 24 February 1947. Decreto N° 3967/47. 3967/47 decree. 2020-08-10. mepriv.mecon.gov.ar. Argentina Executive. es-AR.
  9. Web site: 19 April 1947. Decreto N° 9932/47. 9932/47 decree. 2020-08-10. mepriv.mecon.gov.ar. Argentina Executive. es-AR.
  10. Villulla. Carlos Alberto. 2012. Análisis del Sistema Argentino de Interconexión. PDF. Anales de la Facultad de Ciencias Jurídicas y Sociales. es-AR. National University of La Plata. 42. 0075-7411.
  11. Web site: 15 September 1960. LEY 15.336. 15.336 Act. 2020-08-10. mepriv.mecon.gov.ar. Argentina Executive. es-AR.
  12. Web site: 16 January 1992. LEY 24.065 - REGIMEN DE LA ENERGIA ELECTRICA. 24065 Act - Electric energy regime. 2020-08-10. mepriv.mecon.gov.ar. Argentina Executive. es-AR.
  13. Web site: 10 July 1992. Decreto 1192 / 1992. 1192 / 1992 Decree. 2020-08-10. Argentina.gob.ar. Argentina Executive. es-AR.
  14. Web site: 1 November 2018. ANDE restablece venta de energía eléctrica a la República Argentina. ANDE (Paraguay). es-PY.
  15. News: Spaltro. Santiago. 4 June 2020. A un año del apagón, no hubo multas para Transener y otras eléctricas. es-AR. A year after the blackout, no fines for Transener and other electric companies. El Cronista.
  16. Web site: 3 July 2019. REUNIÓN DE LA COMISIÓN DE MINERÍA, ENERGÍA Y COMBUSTIBLES. Hearing of the mining, energy and fuels commission. Argentine Senate. es-AR. 10 August 2020. 11 September 2020. https://web.archive.org/web/20200911145730/https://www.senado.gob.ar/upload/31052.pdf. dead.