Silver State North Solar Project | |
Country: | United States |
Location: | Clark County |
Coordinates: | 35.6267°N -115.3533°W |
Status: | O |
Commissioned: | May 7, 2012 |
Owner: | First Solar |
Solar Type: | Flat-panel PV fixed tilt |
Ps Site Area: | 600 acres |
Ps Electrical Capacity: | 60 MWp, 50 MWAC |
Ps Electrical Cap Fac: | 27.0% (average 2013-2019) |
Ps Annual Generation: | 118 GW·h, 197 MW·h/acre |
Silver State North Solar Project is a 60 MWp (50 MWAC) photovoltaic power station near Primm, Nevada.[1]
Year | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2012 | 7,098 | 12,992 | 12,472 | 10,838 | 8,975 | 9,177 | 10,877 | 8,345 | 6,968 | 87,742 | ||||
2013 | 8,305 | 8,986 | 10,653 | 11,677 | 12,326 | 12,064 | 10,338 | 10,750 | 10,247 | 10,808 | 7,992 | 8,102 | 122,248 | |
2014 | 8,318 | 8,463 | 11,022 | 11,075 | 12,119 | 11,952 | 10,525 | 10,906 | 10,874 | 10,720 | 8,893 | 4,925 | 119,792 | |
2015 | 7,504 | 9,171 | 10,788 | 11,778 | 11,041 | 11,441 | 10,804 | 11,125 | 10,543 | 9,340 | 8,966 | 7,325 | 119,826 | |
2016 | 6,454 | 9,727 | 10,252 | 10,212 | 11,825 | 11,440 | 11,766 | 11,036 | 10,636 | 9,560 | 8,253 | 6,385 | 117,546 | |
2017 | 4,846 | 5,386 | 9,296 | 10,235 | 11,455 | 12,081 | 11,687 | 12,843 | 12,105 | 11,777 | 7,671 | 7,225 | 116,607 | |
2018 | 5,601 | 7,183 | 9,200 | 11,486 | 12,147 | 14,225 | 12,117 | 12,253 | 11,786 | 9,240 | 7,223 | 5,592 | 118,054 | |
2019 | 5,993 | 6,558 | 9,072 | 10,733 | 11,376 | 12,529 | 12,652 | 12,319 | 10,539 | 10,224 | 6,977 | 4,712 | 113,676 | |
Average Annual Production (years 2013–2019) ---> | 118,250 |