Sha Tin to Central Link explained

Sha Tin to Central Link
Chinese: 沙田至中環線
Type:Heavy rail
System:MTR
Locale:Districts

Kowloon City, Yau Tsim Mong, Wan Chai, Central and Western

Start:
End:
Stations:
  • 8 (phase 1)
  • 2 (phase 2)
Open:Tuen Ma line:
  • (Tai Wai-Kai Tak)
  • (Kai Tak-Hung Hom)
East Rail line: (Hung Hom-Admiralty)
Close:West Rail line:
Owner:KCR Corporation
Operator:MTR Corporation
Depot:Tai Wai, Hung Hom, Pat Heung
Stock:SP1900 EMU, Hyundai Rotem EMU, CRRC Changchun EMU
Linelength Km:17
Map State:collapsed
Timeline of the Sha Tin to Central Link
Date Event
1960s Predecessor East Kowloon line was proposed by British consultant Freeman, Fox, Wilbur Smith & Associates
2000 Sha Tin to Central Link first appeared in the government document Railway Development Strategy 2000
2002 KCRC won its bid to build SCL, building an independent line from Tai Wai to Central West
2005 KCRC modified its 2002 plan, making East Kowloon portion of the line join Ma On Shan Rail at Tai Wai and West Rail at Hung Hom. The East Rail would extend to Central West
MTRC submitted a new proposal: extending Kwun Tong Line to Whampoa, and building a new independent line from Tai Wai to Central West (similar to KCRC 2002 plan)
2006 MTR–KCR merger was confirmed. Non-binding memorandum of understanding signed by government and MTRC. Yet, SCL would be built in accordance to KCRC 2005 plan, while Kwun Tong line extension would also be constructed
2007 MTR–KCR merger
2008 MTRC announced a revised proposal, fully funded by government
2012 Executive Council approved and construction began
2015 First rolling stock for East West line arrived in Hong Kong
2016 Kwun Tong line extension commence
11-kilometre tunnel of East West line was fully broken through
2018Whistleblowing on poor construction quality at the Hung Hom stationA Commission of Inquiry is appointed by Chief Executive of HKSAR government
2019Commencement of whole SCL postponedSCL (Phase 1) split into Tuen Ma line First Phase and Second Phase due to construction quality of Hung Hom station. The name "Ma On Shan line" is made obsolete as it began operating as "Tuen Ma line phase 1".
2021Tuen Ma line begins full operation. The name "West Rail line" is made obsolete as it was fully absorbed by Tuen Ma line.
2022The East Rail Line extension begins full operations, and all Metro Cammell EMUs of it has retired.
The Sha Tin to Central Link (abbreviated SCL;) was an expansion project of the MTR public transport network in Hong Kong. It was divided into two sections and expanded the network’s heavy rail lines.

The first section, named "Tuen Ma line (Phase 1)”, runs from Tai Wai station in the New Territories to Hung Hom station in Kowloon. The Tai Wai–Hung Hom segment connected the Ma On Shan line and West Rail line, forming the new Tuen Ma line. Operation of the Tai Wai to Kai Tak section began on 14 February 2020.[1] The opening of the section from Kai Tak to Hung Hom was delayed and opened on 27 June 2021.[2] [3]

In anticipation of the Tuen Ma line, the existing Kwun Tong line was extended from its previous terminus at Yau Ma Tei to Whampoa station. This extension includes the new Ho Man Tin station to provide interchange with the Tuen Ma line. The Kwun Tong line extension was opened on 23 October 2016.[4] While it was done in conjunction with the Sha Tin to Central Link, it is not considered a direct component of the project.

The second section (Phase 2) extended the East Rail line from Hung Hom in Kowloon to Admiralty on Hong Kong Island via a newly constructed station at Exhibition Centre. It opened on 15 May 2022.[5]

History

The proposed route of the Sha Tin to Central Link roughly follows the scheme of the original East Kowloon line, which was proposed in the late 1960s but was not constructed. The Shatin to Central Link was included as one of the Priority Railway Schemes in the Hong Kong government's Railway Development Strategy 2000.[6]

On 25 June 2002, the government announced that the Kowloon-Canton Railway Corporation (KCRC) had won its bid against the MTR Corporation (MTRC) to build and operate the Shatin to Central Link. The route was originally planned to go from Tai Wai station to Central West station (proposed to be located under the Mid-Levels), as an extension of the then-under-construction KCR Ma On Shan Rail (now the Ma On Shan line).

The KCRC announced modifications to the proposal in 2005, with the East Kowloon portion of the line joining KCR Ma On Shan Rail at Tai Wai and KCR West Rail (now the West Rail line) at Hung Hom, with the cross-harbour portion joining KCR East Rail (now the East Rail line) at Hung Hom. Mong Kok Station (now Mong Kok East) would have been relocated, joining a new tunnel to a deeper Hung Hom station platform connecting to the cross-harbour section. Additionally, stations at Tsz Wan Shan and Whampoa Garden were removed from the proposal; the areas would instead have been served by people movers from other stations. However, the KCRC's proposal had not yet been finalised.

At the same time, the MTRC submitted a new proposal to the government. According to the proposal, the Kwun Tong line would be extended from Yau Ma Tei station to Whampoa station (as the KCRC had decided to omit Whampoa Garden station from its proposal), and the route of the SCL would follow the KCRC's original proposal instead of the 2005 modified proposal. An underground train depot would have been built beneath the passenger terminal of the former Kai Tak International Airport, adjacent to Prince Edward Road East in Kowloon City; however, under the Kai Tak redevelopment plan released by the government in October 2006, the depot would have to be constructed somewhere else.[7]

MTR–KCR merger plan

On 11 April 2006, MTRC signed a non-binding memorandum of understanding with the government of Hong Kong, the owner of KCRC, to merge the operations of the territory's two railway networks. According to the memorandum, the MTRC-owned MTR lines will be fully integrated with the Shatin to Central Link, which will be part of the MTR system. The government also intended to choose the KCRC's modified proposal to build the railway, that is, extending the current East Rail line to Hong Kong Island. However, final decisions were not made before conducting further studies on the proposal with the MTRC.

The new proposal was announced jointly by both companies on 12 July 2007,[8] before the merger of the two rail networks on 2 December that year. Under this proposal, the depot for the Sha Tin to Central Link would have been built underneath the former Tai Hom Village site between Kai Tak and Diamond Hill stations. The people movers were omitted; Causeway Bay North station was also removed from the proposal due to potential adverse effects on road traffic during construction.

 Stations of previous proposals 
KCRC proposal (2002)KCRC revised proposal (2005)MTRC proposal (2005)KCRC–MTRC proposal (2007)
Ma On Shan Rail East Kowloon Extension

East Rail Cross-harbour Extension

Shatin to Central Link

Kwun Tong line extension

East–West line

North–South line

Kwun Tong line extension

Legend

The MTRC announced a revised proposal on 11 March 2008. The government would fund all of the required for construction.[9] The Executive Council approved the construction cost of HK$79.8 billion in March 2012[10] [11] and construction began on 22 June 2012.[12] Under the final proposal, the former Hung Hom Freight Yard adjacent to Hung Hom station will be converted into stabling sidings for Sha Tin to Central Link trains, and new access tracks will be constructed to link the Sha Tin to Central Link with the former Hung Hom Freight Yard.[13] Central South station was excluded in the modified plan, as no suitable sites had been found.[14] One station at Hin Keng (just south of Tai Wai) was added to the proposal afterwards,[15] to alleviate congestion at Tai Wai station.

Expected commencement

The original commencement date of Phase 1 was 2018; Phase 2 was expected to be completed in 2020 or 2021. Some of the construction work of Phase 2 has followed the completion of Wan Chai Reclamation Phase 2 and Central–Wan Chai Bypass, as there are overlaps between station and tunnels.[16] In November 2014, Secretary for Transport and Housing Anthony Cheung revealed that the project would be delayed by at least another 11 months, caused by archaeological Work at To Kwa Wan station (now renamed as Sung Wong Toi station), and extra enabling works at Exhibition Centre station for topside development. At that time, the authority submitted a document to the Legislative Council, stating Phases 1 and 2 would be completed in 2019 and 2021 respectively.[17]

However, the opening was delayed again due to construction quality problems at Hung Hom station. In January 2020, Secretary for Transport & Housing Frank Chan announced the "Tuen Ma line Phase 1" would be open on 14 February 2020, the rest of the Tuen Ma line would open on 27 June 2021, and the MTR expects the opening of the East Rail line extensions by June or July 2022, but is subject to change.[18]

On 3 May 2022, MTR officially announced that the East Rail Line extension would open on 15 May 2022.

Hung Hom station scandal

In 2018, a whistleblower leaked information to the Hong Kong media stating that the construction quality at the Hung Hom station was substandard. Namely, the threaded steel bars that were supposed to link to each other were cut so that they would fit into couplers without actually connecting to the full extent.[19]

This raised concerns that the platform is not as strong as it was designed to be. Although initially denying the allegations, the MTR and the contractor Leighton Asia[20] later confirmed them, and proposed a plan to open up the concrete at some areas of the stations to inspect the construction quality.

The investigation also revealed further incidents of substandard work and missing construction records. For example, 40% of Request for Inspection and Survey Checks forms for the northern approach tunnels are missing.[21]

Construction and facility enhancement

New railway lines and track

The 11-kilometre tunnel of the East-West Corridor was fully broken through in August 2016.[22]

As of February 2017, construction and tunnel boring is underway for the sections between the Exhibition Centre station and Causeway Bay, and between Causeway Bay and Kowloon. MTRC has set up an Immersed Tube Tunnel Casting Yard at the site of the former Shek O Quarry at the south side of the Hong Kong Island to pre-assemble sections of the tunnel tubes, which will be then transported by sea and immersed in place.[23] [24] As June 2017, the first Immersed Tube Tunnel units was installed in Victoria Harbour, marking the beginning of constructing the fourth harbour-crossing railway tunnel in Hong Kong. 11 tube tunnel units in total will be constructed and placed for the harbour crossing section.[25] [26]

New signalling systems and station facilities

Both of the new corridors will receive new signalling systems as part of the Sha Tin to Central Link project. The technology, known as communications-based train control (CBTC), will minimise train intervals while complying with existing and future infrastructure, such as platform doors/gates.The East West Corridor are now using SelTrac CBTC supplied by Thales. This is an updated, more modern version of the Seltrac IS technology already installed on the West Rail line, Ma On Shan line, and Kowloon Southern Link. New on-board computers are being retrofitted to the existing SP1900 trains as part of their modifications to form 8-car trains, supplemented with newly acquired 8-car trains delivered with the new computer already installed. All stations on the Ma On Shan line have also received half-height platform gates in conjunction with the upgrade, and new underground stations will have full-height platform doors installed.

The North South Corridor will have the TBL train protection and Alstom's ATO system in use on the current East Rail line including the Lok Ma Chau Spur Line replaced with Trainguard MT CBTC supplied by Siemens.[27] (AWS used by intercity trains on the East Rail line is not expected to be affected.) At the same time, all platforms would be modified and equipped with half-height platform gates (full-height doors on the new underground stations) to provide level boarding and minimize the gap with the train. Refurbishment and expansion work on platforms and stations will also be carried out.[28]

Admiralty, Diamond Hill and Hung Hom stations, all of which are major interchanges following full opening of the new lines, have been expanded or relocated to cater to increased demand.

New rolling stock

See also: MTR CRRC Changchun EMU, MTR Hyundai Rotem EMU and SP1900 EMU. The East West Corridor will operate using a combination of both new and existing rolling stock, while the North South Corridor will have its existing rolling stock fully replaced with new stock.

New community facilities

Tsz Wan Shan station was removed from the 2007 final proposal due to its depth. Because of this, pedestrian facilities with lifts, travellers and covered walkways will be built for the Tsz Wan Shan community, connecting with Diamond Hill station.[37]

On Hong Kong Island, Wan Chai Swimming Pool and Harbour Road Sports Centre were both re-provisioned on alternate sites, as the original buildings were demolished to make way for Exhibition Centre station.[38]

Hongkong Post's International Mail Centre in Hung Hom was also demolished to make way for the line. It was rebuilt in Kowloon Bay and renamed the Central Mail Centre.

Route

From the preexisting Ma On Shan line at Tai Wai station, the Tuen Ma line will continue southwards on an embankment to Hin Keng station, and then head southeast in tunnel towards Kowloon. After Diamond Hill station, the line will turn southwest and continue in tunnel through Ma Tau Chung and To Kwa Wan towards Hung Hom station, interchanging with the Kwun Tong line extension at Ho Man Tin along the way. At Hung Hom, the East West Corridor will connect to the preexisting West Rail line just south of its new platforms at the station and interchange with the East Rail line.

The East Rail line extension will connect to the East Rail line north of Hung Hom station, adjacent to the southern portal of the tunnel under Princess Margaret Road (Tunnel 1A); and will enter a tunnel to new platforms at Hung Hom station, interchanging with the Tuen Ma line. The line will then traverse under Victoria Harbour, through an immersed tube tunnel (Contract 1121), largely parallel to the Cross-Harbour Tunnel to its west, and then continue in tunnel westwards from the New Causeway Bay Typhoon Shelter to Exhibition Centre and Admiralty stations.

The Kwun Tong line extension, an associated project completed in late 2016, is a southeast extension of the Kwun Tong line from Yau Ma Tei station to Ho Man Tin station, where there will be an interchange to the Tuen Ma line. The line then continues under Wuhu Street and Tak on Street to a single dead-end platform at Whampoa station.[39]

Stations

Livery and nameDistrictConnectionsOpening date
Tuen Ma line
Tuen Ma line to Wu Kai Sha
Kai TakKowloon City14 February 2020
Sung Wong Toi27 June 2021
To Kwa Wan
Ho Man Tin23 October 2016
Hung HomYau Tsim Mong
Through Train services to Mainland China
30 November 1975
relocated on 20 June 2021
Tuen Ma line to Tuen Mun
East Rail line extension
East Rail line to Lo Wu or Lok Ma Chau
Hung HomYau Tsim Mong
Through Train services to Mainland China
30 November 1975
relocated on 15 May 2022
Exhibition CentreWan Chai (North Island line; under planning)15 May 2022
AdmiraltyCentral and Western, and
12 February 1980
Kwun Tong line extension
Kwun Tong line to Tiu Keng Leng
Yau Ma TeiYau Tsim Mong31 December 1979
Ho Man TinKowloon City23 October 2016
Whampoa

Naming

Initially, Sung Wong Toi station was named To Kwa Wan station, and To Kwa Wan station was named Ma Tau Wai station.[40] This naming arrangement was met with dissatisfaction from the nearby community, as geographically, the former To Kwa Wan station was not considered part of To Kwa Wan. As a result, MTR made adjustments to the naming, which was announced during the 2017 Panel on Transport of the Legislative Council.[41]

Notes and References

  1. Web site: Partial opening of scandal-hit Sha Tin-Central MTR link set for Valentine's Day, Hong Kong transport minister reveals . South China Morning Post . 17 January 2020 . 17 January 2020 . 17 January 2020 . https://web.archive.org/web/20200117055413/https://www.scmp.com/news/hong-kong/transport/article/3046511/partial-opening-scandal-hit-sha-tin-central-mtr-link-set . live .
  2. Web site: LCQ1: Construction Works at and near Hung Hom Station Extension under Shatin to Central Link Project . Legislative Council . 3 June 2020 . 3 June 2020 . 3 June 2020 . https://web.archive.org/web/20200603045207/https://www.info.gov.hk/gia/general/202006/03/P2020060300359.htm . live .
  3. Web site: Progress Update on the Construction of the Shatin to Central Link . MTR Corporation . 5 June 2020 . 12 August 2020 . 28 October 2020 . https://web.archive.org/web/20201028210419/https://www.legco.gov.hk/yr19-20/chinese/panels/tp/tp_rdp/papers/tp_rdp20200605cb4-730-2-ec.pdf . live .
  4. Web site: MTR Updates Construction Progress on SIL(E) and KTE Railway Projects . . 2014-06-12 . 19 June 2016 . 20 February 2018 . https://web.archive.org/web/20180220151825/http://www.mtr.com.hk/eng/corporate/file_rep/PR-14-051-E.pdf . live .
  5. Web site: MTR – Shatin to Central Link – Project Details – Programme. MTR Corporation. 2016-04-27. 24 April 2016. https://web.archive.org/web/20160424061018/http://www.mtr-shatincentrallink.hk/en/project-details/programme.html. live.
  6. Web site: Review and Update of the Railway Development Strategy 2000 – Executive Summary. September 2014. Highways Department of the Government of Hong Kong. 1 July 2016. 9 May 2016. https://web.archive.org/web/20160509083301/http://www.hyd.gov.hk/en/publications_and_publicity/publications/review_and_update_railway_development_strategy_2000_es/doc/es_e.pdf. live.
  7. "Diamond Hill eyed for train depot", The Standard, 13 November 2006.
  8. http://www.legco.gov.hk/yr06-07/chinese/panels/tp/tp_rdp/papers/tp_rdp0716cb1-2058-1-c.pdf
  9. News: 政府全資374億建沙中線(A4). Ming Pao. 12 March 2008.
  10. Web site: 行會拍板港鐵沙中綫上馬 (lit. Executive Council has approved Sha Tin to Central Link.). Sing Tao Daily. 28 March 2012. 2012-03-29. 3 May 2019. https://web.archive.org/web/20190503064326/http://hk.news.yahoo.com/%E8%A1%8C%E6%9C%83%E6%8B%8D%E6%9D%BF%E6%B8%AF%E9%90%B5%E6%B2%99%E4%B8%AD%E7%B6%AB%E4%B8%8A%E9%A6%AC-220934578.html. live.
  11. Web site: Gazettal of Shatin to Central Link. Press releases. Hong Kong Government. 19 November 2014. 26 November 2010. 24 September 2015. https://web.archive.org/web/20150924052056/http://www.info.gov.hk/gia/general/201011/26/P201011260298.htm. live.
  12. Web site: http://info.gov.hk/gia/general/201206/22/P201206220603.htm. zh:政務司司長出席沙中線動工典禮致辭全文. Hong Kong Government News Archives. zh. 22 June 2012. 27 June 2012. 23 June 2012. https://web.archive.org/web/20120623230604/http://www.info.gov.hk/gia/general/201206/22/P201206220603.htm. live.
  13. Web site: MTR – Shatin to Central Link – FAQ. MTR Corporation. https://web.archive.org/web/20151226024251/http://www.mtr-shatincentrallink.hk/en/faq/. 26 December 2015. 18 June 2014.
  14. News: 政府全資374億建沙中線(A4). Ming Pao. 2008-03-12.
  15. Web site: MTR – Shatin to Central Link – Project Details – Alignment. mtr-shatincentrallink.hk. MTR Corporation. https://web.archive.org/web/20160320231945/http://www.mtr-shatincentrallink.hk/en/project-details/alignment.html. 20 March 2016. 19 June 2016.
  16. News: 沙田至中環線工程的最新進展. Legislative Council. 31 March 2016. 13 November 2016. 13 November 2016. https://web.archive.org/web/20161113180100/http://www.legco.gov.hk/yr15-16/chinese/panels/tp/tp_rdp/papers/tp_rdp20160627cb4-1136-3-c.pdf. live.
  17. News: 港鐵沙中綫通車日期需延遲約一年 . . 2015-03-04 . 13 November 2016 . 2 April 2015 . https://web.archive.org/web/20150402160236/http://rthk.hk/rthk/news/expressnews/20150304/news_20150304_55_1081624.htm . live .
  18. News: New rail line to open. 18 July 2019. news.gov.hk. 25 October 2019. 25 October 2019. https://web.archive.org/web/20191025072442/https://www.news.gov.hk/eng/2019/07/20190718/20190718_175608_397.html. live.
  19. http://www.mtr-shatincentrallink.hk/pdf/multimedia-gallery/report/report_20181205_e.pdf
  20. Web site: MTR admits construction 'deviations' at Hung Hom station expansion, but insists no proof of steel bar cutting. 25 December 2018.
  21. Web site: Gov't to inspect other Shatin to Central Link MTR construction sites amid string of engineering scandals. 31 January 2019. 9 July 2019. 23 January 2023. https://web.archive.org/web/20230123102315/https://hongkongfp.com/2019/01/31/govt-inspect-shatin-central-link-mtr-construction-sites-amid-string-engineering-scandals/. live.
  22. News: 11-km East-West Corridor tunnel of the Shatin to Central Link broken through. 8 September 2016. MTR Corporation. 19 September 2016. 19 September 2016. https://web.archive.org/web/20160919154900/http://www.mtr-shatincentrallink.hk/pdf/multimedia-gallery/press/09092016_pr_e.pdf. live.
  23. http://www.mtr-shatincentrallink.hk/pdf/multimedia-gallery/publication/newsletter/hki_newsletter_29092015_e.pdf
  24. Web site: MTR – Shatin to Central Link – Construction – Temporary Works Areas & Construction Facilities . 3 March 2017 . 17 February 2017 . https://web.archive.org/web/20170217203438/http://www.mtr-shatincentrallink.hk/en/construction/temp-work.html . dead .
  25. http://www.mtr-shatincentrallink.hk/pdf/multimedia-gallery/press/20062017_pr_e.pdf First Tunnel Unit for Shatin to Central Link Cross-Harbour Tunnel Successfully Installed in Victoria Harbour
  26. https://www.facebook.com/mtrhk/videos/10159017264700151/ Immersing Diary#3 – Under the sea
  27. Web site: SCL Major Contracts Awarded. MTR. 29 October 2017. 26 October 2019. https://web.archive.org/web/20191026104128/http://www.mtr-shatincentrallink.hk/en/construction/major-contracts-awarded.html. live.
  28. Web site: MTR Service Update. 「 沙田至中環綫 」第一期. VJMEDIA. 29 October 2017. zh. 22 February 2015. 29 October 2017. https://web.archive.org/web/20171029165504/http://www.vjmedia.com.hk/articles/2015/02/22/100383/sclphase1/. live.
  29. Web site: Shatin to Central Link (SCL). Railway Technology. 2016-06-26. 1 July 2016. https://web.archive.org/web/20160701212804/http://www.railway-technology.com/projects/shatin-to-central-link-scl/. live.
  30. Web site: MTR – Shatin to Central Link – Construction – New Trains. 2016-03-20. https://web.archive.org/web/20160320171021/http://www.mtr-shatincentrallink.hk/en/construction/new-trains.html. 20 March 2016. dead. 2016-06-26.
  31. News: MTR orders trains and signalling for Shatin – Central Link. Barrow. Keith. 19 December 2012. International Railway Journal. 28 July 2015. 13 February 2018. https://web.archive.org/web/20180213135244/http://www.railjournal.com/index.php/asia/mtr-orders-trains-and-signalling-for-shatin-%E2%80%93-central-link.html?channel=000. dead.
  32. News: New Trains and Signalling System for the future Shatin to Central Link. 14 December 2012. MTR (Press Release). 28 July 2015. 7 May 2016. https://web.archive.org/web/20160507045446/http://www.mtr-shatincentrallink.hk/pdf/en/multimedia-gallery/press/14122012_pr_e.pdf. live.
  33. Web site: 2nd MTR shipment successful delivery. 19 December 2015. Pioneer Logistics Group. 4 October 2016. 5 October 2016. https://web.archive.org/web/20161005105651/http://www.pioneer-group.hk/news-1-c8mf/ilirby1i19/2nd-MTR-shipment-successful-delivery. dead.
  34. Web site: Review and Update of the Railway Development Strategy 2000 – Executive Summary. September 2014. Highways Department of the Government of Hong Kong. 1 July 2016. 9 May 2016. https://web.archive.org/web/20160509083301/http://www.hyd.gov.hk/en/publications_and_publicity/publications/review_and_update_railway_development_strategy_2000_es/doc/es_e.pdf. live.
  35. Web site: SP1900. MTR Service Update. 10 November 2017. 23 January 2023. https://web.archive.org/web/20230123102329/https://www.facebook.com/login/?next=https%3A%2F%2Fwww.facebook.com%2Fmtrupdate%2Fposts%2F1043905192287091. live.
  36. Web site: New trains for SCL. MTR. 10 November 2017. 20 March 2016. https://web.archive.org/web/20160320171021/http://www.mtr-shatincentrallink.hk/en/construction/new-trains.html. dead.
  37. Web site: Shatin to Central Link – Improvement Works on Pedestrian Link Facilities in Tsz Wan Shan. MTR. 30 October 2017. Oct 2013. 8 December 2017. https://web.archive.org/web/20171208093908/http://www.mtr-shatincentrallink.hk/pdf/multimedia-gallery/publication/leaflet/wts_tws_leaflet102013.pdf. live.
  38. Web site: Progress Update. MTR. 30 October 2017. 19 November 2017. https://web.archive.org/web/20171119085022/http://www.mtr-shatincentrallink.hk/en/construction/progress-update.html#tabs-2. live.
  39. Web site: MTR – Kwun Tong Line Extension > Project Details > Key Information. mtr-kwuntonglineextension.hk. MTR Corporation. https://web.archive.org/web/20160619093513/http://www.mtr-kwuntonglineextension.hk/en/project/information.html. 19 June 2016. 19 June 2016.
  40. Web site: 「 沙田至中環綫 」第一期 (Chinese: Sha Tin to Central Link phrase 1). 22 February 2017. 29 October 2017. 29 October 2017. https://web.archive.org/web/20171029165504/http://www.vjmedia.com.hk/articles/2015/02/22/100383/sclphase1/. live.
  41. Web site: 港鐵沙中線「土瓜灣」站變「宋皇臺」站? 港鐵:內部參考未落實. 黃. 雅盈. 24 September 2017. 27 November 2017. 23 January 2023. https://web.archive.org/web/20230123102318/https://www.hk01.com/%E7%A4%BE%E6%9C%83%E6%96%B0%E8%81%9E/121358/%E6%B8%AF%E9%90%B5%E6%B2%99%E4%B8%AD%E7%B7%9A-%E5%9C%9F%E7%93%9C%E7%81%A3-%E7%AB%99%E8%AE%8A-%E5%AE%8B%E7%9A%87%E8%87%BA-%E7%AB%99-%E6%B8%AF%E9%90%B5-%E5%85%A7%E9%83%A8%E5%8F%83%E8%80%83%E6%9C%AA%E8%90%BD%E5%AF%A6. live.