The Savage Tooele Railroad is a shortline railroad under construction along the former Western Pacific Railroad Warner Branch, to the Lakeview Business Park in Grantsville, Utah. The railroad is approximately 11 miles long.[1] Authorization from the Surface Transportation Board to build the railroad was given in April 2024.[2]

History

The Western Pacific Railroad originally built the Warner Branch (also referred to as the "Tooele Branch" in some timetables) in 1917 to connect the Western Pacific to the Tooele Valley Railway, accessing the traffic from the International Smelting and Refining Company plant in Tooele, Utah.[3] [4] An interchange with the Tooele Army Depot was built in 1943 providing further traffic along the branch.[3] Following the merger between the Western Pacific Railroad and the Union Pacific Railroad the branch would be deemed surplus, and was largely abandoned. Rails were removed from Tooele to the unincorporated community of Marshall, Utah in 2003.[3] A significant portion of the right of way on the Tooele to Grantsville portion of the Warner Branch exists presently as the Mid-Valley Trail.[5] [6]

In 2020, the Romney Group (owned by Josh Romney, son of Utah senator Mitt Romney) and NorthPoint Development broke ground on the Lakeview Business Park, north of the Utah Motorsports Campus.[7] The Savage Tooele Railroad was founded as a common carrier railroad under parent company Savage (who operate the nearby Savage Bingham and Garfield Railroad in Salt Lake County) to restore and operate the Warner Branch to the business park and filed an appeal in 2021 with the Surface Transportation Board to begin construction of the railroad line.[2] [8] The project was backed by Utah governor Spencer Cox and representatives John Curtis and Chris Stewart, but concerns were raised by the Environmental Protection Agency due to the railroad's proximity to wetlands near the Great Salt Lake.[9] Tooele County agreed to replace a segment of the Mid-Valley Trail right of way with a bypass segment, to clear the right of way for the Savage Tooele Railroad.[10] Motions to begin construction on the railroad were denied in 2021 and 2022, pending the completion of an environmental report which was finished in 2024, after a draft environmental report had been issued in 2023.[8] [11] [12]

In February 2024, the STB granted permission to the Union Pacific Railroad to restore the upper portion of the Warner Branch to service for interchange with the Savage Tooele Railroad.[13] BNSF Railway had appealed for lengthier STB proceedings to allow access to interchange with the Savage Tooele Railroad via trackage rights, however currently the STB has denied this appeal.[14] [13] Permission was granted by the STB for the Savage Tooele Railroad to begin construction from its connection with the Union Pacific to the Lakeview Business Park in April that year.[2] The railroad will also serve the Twenty Wells Project associated with the Utah Inland Port in Grantsville, Utah.[15] Residents of Erda, Utah and Utah Physicians for a Healthy Environment jointly filed a petition for reconsideration with the Surface Transportation Board opposing the railroad in early May, citing impacts the Lakeview Business Park and railroad would bring to the surrounding area, which the railroad described as a position "without merit".[16]

Notes and References

  1. Web site: STB Approves Construction of New Utah Short Line . . April 11, 2024 . railfan.com . White River Productions . April 11, 2024.
  2. Web site: Savage Tooele Railroad Company-Construction and Operation Exemption-Line of Railroad in Tooele County, Utah . . April 5, 2024 . federalregister.gov . Federal Register . April 8, 2024.
  3. Web site: Western Pacific Branches in Utah . Strack . Don . December 5, 2023 . utahrails.net . Utah Rails . April 8, 2024.
  4. Book: . June 17, 1934 . Eastern Division Timetable Western Pacific . . Western Pacific Railroad . 6.
  5. Web site: SPECIAL WARRANTY DEED (Rail Trail) . . March 21, 2007 . tooeleco.org . Tooele County . April 8, 2024.
  6. Web site: Mid-Valley Trail . . . tooelecountytrails.com . Tooele Transcript Bulletin . April 8, 2024.
  7. Web site: NorthPoint, Romney Group unveil over $1B business park in Grantsville, Utah . Maqbool . Abdul . December 10, 2020 . spglobal.com . S&P Global . April 8, 2024.
  8. Web site: Analysis: Regulatory overkill stunts potential of proposed Utah rail project . Stephens . Bill . October 16, 2023 . Trains.com . Kalmbach Media . April 8, 2024.
  9. Web site: Powerful Utah politicians back Tooele rail spur, but see why EPA and others are wary . Larsen . Leia . February 8, 2022 . sltrib.com . Salt Lake Tribune . April 8, 2024.
  10. Web site: Rail Train Indemnification Agreement . . March 8, 2021 . tooeleco.org . Tooele County . April 8, 2024.
  11. Web site: STB Issues Final Environmental Assessment for Proposed New Rail Line in Tooele County, Utah . . March 1, 2024 . stb.gov . Surface Transportation Board . April 8, 2024.
  12. Web site: Federal regulators issue draft environmental report for proposed Utah rail spur . Stephens . Bill . October 2, 2023 . Trains.com . Kalmbach Media . April 8, 2024.
  13. Web site: STB approves UP request to restore service on Utah rail line . . February 16, 2024 . progressiverailroading.com . Progressive Railroading . April 8, 2024.
  14. Web site: BNSF tells regulators that UP aims to block interchange access to proposed Utah short line . Stephens . Bill . December 14, 2023 . Trains.com . Kalmbach Media . April 8, 2024.
  15. News: Gillie . Tim . April 10, 2024 . Rail line approved . Tooele Transcript Bulletin . Tooele, Utah . April 10, 2024.
  16. Web site: Neighbors and environmental advocates file petition to reconsider building new Tooele rail line . Cabrera . Alixel . May 2, 2024 . utahnewsdispatch.com . Utah News Dispatch . May 3, 2024.