San Isabel Solar Energy Center | |
Coordinates: | 37.3675°N -104.4678°W |
Country: | United States |
Location: | Las Animas County, Colorado |
Status: | O |
Construction Began: | March 2016 |
Commissioned: | December 2016 |
Cost: | US$60 million |
Owner: | PSEG Solar Source |
Operator: | juwi O&M Group |
Solar Type: | Flat-panel PV single-axis tracking |
Ps Site Area: | 250acres |
Ps Electrical Capacity: | 37.9 MWp, 30 MWAC |
Ps Electrical Cap Fac: | 27.4 (average 2017-2019) |
Ps Annual Generation: | 72.0 GW·h, 288 MW·h/acre |
The San Isabel Solar Energy Center is a 30 megawatt (MWAC) photovoltaic power station in Las Animas County, Colorado located about 20 miles north of the city of Trinidad. The electricity is being sold to Tri-State Generation and Transmission (aka Tri-State) under a 25-year power purchase agreement.[1] [2] [3] It is the second solar project, following the Cimarron Solar Facility in year 2010, to be added to the utility cooperative's renewables portfolio.
The facility occupies about 250 acres of semi-arid shortgrass prairie on the Colorado south-eastern plains, about 10 miles east of the base of the Rocky Mountains. It uses 120,960 polycrystalline silicon panels (Model SN-72cell: rated 310 Wp, ~16% efficiency) that the manufacturer, S-Energy, claims are less susceptible to potential-induced degradation.[4] [5] The panels are mounted in rows onto single-axis trackers to optimize electricity production throughout the day.
The project was developed, constructed, and continues to be operated by Boulder-based juwi Inc., the U.S. subsidiary of the German renewable energy company juwi AG.[6] Construction began in March 2016 and employed about 400 workers, with Nesco serving as contractor for the civil structures.[7] Commercial operation began in December 2016, with a dedication ceremony on July 14, 2017.[8] The project was financed, and is owned by PSEG Solar Source, a subsidiary of New Jersey's Public Service Enterprise Group. The completed facility cost about US$60 million.
On January 11, 2019 Tri-State and juwi announced their development plan for the 100 MW Spanish Peaks Solar Project, which would be sited adjacent to San Isabel Solar Energy Center. Under their plan, juwi will continue to develop the project and Tri-State would buy the electricity under a 15-year contract. A construction start is being targeted for year 2022, with completion in 2023. If funded, it may be the fourth solar project, following the Alta Luna Solar Facility in 2017, to be added to Tri-State's renewables portfolio.[9] [10]
Year | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2016 | 4,287 | 4,287 | |||||||||||
2017 | 2,678 | 4,172 | 5,837 | 6,443 | 7,596 | 8,232 | 7,140 | 5,975 | 5,005 | 5,927 | 3,781 | 3,882 | 66,668 |
2018 | 4,262 | 5,251 | 7,453 | 7,157 | 7,785 | 8,406 | 7,710 | 7,526 | 6,795 | 4,630 | 4,398 | 4,044 | 75,417 |
2019 | 4,326 | 5,451 | 6,380 | 6,596 | 7,396 | 7,830 | 8,006 | 7,685 | 7,433 | 5,556 | 3,940 | 3,452 | 74,051 |
2020 | 4,553 | 4,415 | 7,081 | 7,437 | 8,465 | 7,871 | 7,489 | 7,738 | |||||
Average Annual Production (years 2017-2019) : | 72,045 | ||||||||||||
Average Capacity Factor (years 2017-2019) : | 27.4% |