SacRT light rail explained

SacRT light rail
Owner:Sacramento Regional Transit District
Locale:Sacramento, California
Transit Type:Light rail
Lines:3
Stations:53[1]
Daily Ridership:
Annual Ridership:
Train Length:2 cars[2] [3]
System Length:42.9miles
Top Speed:55mph

The SacRT light rail system serves the Sacramento, California area. It is operated by the Sacramento Regional Transit District (SacRT) and has 42.91NaN1 of network comprising three main lines on standard gauge tracks, 53 stations, and a fleet of 96 vehicles. With an average of weekday daily boardings as of, the SacRT light rail system is the fifteenth busiest in the United States.

History

Origins

The Sacramento Regional Transit District (also known as simply SacRT) began planning for a light rail system in the mid-1980s, after the successful opening of the San Diego Trolley in 1981 and amid a surge in light rail construction in mid-sized cities nationwide (Buffalo, Denver, Portland, and San Jose also built systems at the same time).[4] The first line of the light rail system opened on March 12, 1987. Originally branded as RT Metro,[5] [6] the new line linked the northeastern and eastern corridors which both parallel Interstate 80 and Route 50 respectively with Downtown Sacramento.[7] More specifically, the "starter line" ran between Watt/I-80 and Butterfield stations.[8] The line from Butterfield to the Western Pacific line ran on the former Sacramento Valley Railroad. The right of way between Q and R Streets running from 10th to 17th Streets was a former Western Pacific Railroad branch.[9] The line between downtown and Arden Way employed city streets, then turned on a former Western Pacific spur.[10] At the Southern Pacific right of way, the line turned to parallel it for a few miles before transitioning into the median of Interstate 80.

As light rail ridership increased, RT continued to expand the light rail system. In 1993, two infill stations were added on the existing RT Metro line: 39th Street and 48th Street. In September 1998, the line was extended from Butterfield station to Mather Field/Mills station.

Sometime in the late 1990s, the RT Metro branding quietly fell into disuse. It is now simply known as the SacRT light rail system.

Expansion

In September 2003, Sacramento Regional Transit opened the first phase of the South Line (now called the Blue Line), which was a 6.3miles extension to South Sacramento. In June 2004, the Gold Line extended from the Mather Field/Mills station to Sunrise Boulevard, and on October 15, 2005, a 7.4miles extension from the Sunrise station to the city of Folsom was opened.[11] In December 2006, the final leg of the Amtrak/Folsom project was extended by 0.7miles, to the downtown Sacramento Valley Station, connecting light rail with Amtrak inter-city and Capitol Corridor services as well as local and commuter buses.[12]

The system continued expanding in the next decade when RT completed the initial phase of the Green Line to 7th & Richards in 2012. The second phase of the line is planned to reach to the Sacramento International Airport.[13] Later in August 2015, RT extended the Blue Line south to Cosumnes River College.[14]

Sacramento RT Light Rail ridership peaked at 16.8 million rides in 2008 but has declined to 9.7 million rides in 2018, a drop of 42% during that period.[15]

System

Lines

Sacramento's light rail system operates 42.9 miles (69.0 km) of light rail on three rail lines, serving 53 stations. It connects Downtown Sacramento with River District, North Sacramento, South Sacramento, East Sacramento, Rancho Cordova, and Folsom.

Line namedata-sort-type="number" scope="col" rowspan="2" StationsTermini
Western/NorthernEastern/Southern
28Watt/I-80
27Sacramento ValleyHistoric Folsom
77th & Richards/Township 913th Street

Hours and frequency

Light rail service operates from as early as 4:00 am to as late as midnight. Blue and Gold Line trains operate daily with service every 15 minutes during the day and every 30 minutes during the early morning and late nights. However, Gold Line trains east of Sunrise station operate every 30 minutes all day.[16] Green Line trains only operate on weekdays and run every 30 minutes throughout the day.[17] [18]

Stations

See main article: List of SacRT light rail stations. The 53 stations along the network are open-air structures featuring passenger canopies for protection from adverse weather. Twenty-six stations offer bus transfer services and 22 have park-and-ride lots with a total of 10,113 available parking spaces.

The busiest stations in the system by average daily boardings/alightings are: 16th Street (6,800), University/65th (3,000), Cosumnes River College (2,900), and 29th Street (2,900).[19]

Works of public art included at several stations were developed as part of the RT Public Art Program, and represent an array of media including, mosaics, sculptures, metalwork and murals. Each was commissioned to incorporate an identity and sense of place unique to the neighborhood surrounding the station.[20]

Rolling stock

The LRV fleet is composed of cars from two different builders: 36 from Siemens–Duewag U2A, some of which have been in use since the RT opened and 40 newer ones delivered in 2003 from Construcciones y Auxiliar de Ferrocarriles (CAF). Sacramento RT plans to retire the U2A fleet starting in the summer of 2024 as a fleet of Siemens S700 low-floor light rail vehicles enter service. The agency has ordered 45 S700 LRVs, and has options to purchase up to 76 if additional funding is secured.[21] [22] [23]

NumbersBuiltManufacturerModelNotes
3511912American Car CompanyCalifornia carRestored historic electric streetcar, used for special events
1011262619851986SiemensDuewagU2ATo be withdrawn from operation starting by the summer of 2024
1271361019901991
2012404020022003CAFS/200
301-3202019851987Urban Transportation Development CorporationALRVEx-VTA. Acquited in 2015, retired in 2022.
401-4454520222024SiemensS700Delivery to be completed by the end of 2024 and start to enter into service by summer 2024.[24] [25]

Former rolling stock

RT previously operated 20 Urban Transportation Development Corporation (UTDC) ALRV cars. These LRVs were built between 1985 and 1987 for the Santa Clara Valley Transportation Authority (VTA). After being withdrawn from use by VTA, they were purchased by RT and refurbished by Siemens in 2015.[26] [27] In RT service, they carried fleet numbers 301 through 320. They were withdrawn from use in 2022 as "despitethe extensive refurbishment and several ongoing maintenance contracts, the UTDC LRVs have failed to operate consistently in revenue service."[28]

System projects

Low-floor modernization project

Sacramento Light Rail system is over 30 years old, and its existing train cars and stations are aging. SacRT is currently modernizing the system, including new trains, station platforms, and increased services. The construction work will continue for five years until 2027. RT recently bought 45 new low-floor Siemens vehicles, that allow passengers to directly enter trains at nearly floor level instead of walking up stairs.[29] Those new trains recently started a rigorous three-step testing process in early 2023.[30]

The system's station platforms on the Blue and Gold Lines are currently being raised to eight inches (20 cm) above the top of the rail to allow a small bridge plate (on the new trains) to be used to load passengers who require it. However, the five stations constructed after 2006 were already designed for low-floor vehicles and will not require modification. As of November 2023, those new trains will go into service in the summer of 2024. RT raises platforms in two phases, with half (two car lengths) of a platform (generally four car lengths) taken out of service during construction.

Another component of the project will improve service to four stations in the Folsom area, which are currently the only ones with 30-minute service intervals during the day. To increase frequency to every 15 minutes, a second track will be added between Park Shore Drive and Bidwell Street to allow more trains to pass through in both directions. Since the second track passes through Glenn station, a new second platform will be built there. Construction began on January 2, 2024.[31]

Green Line to Sacramento International Airport

The Green Line extension to Sacramento International Airport will extend service 12 miles (19.3 km) to the airport via the Natomas neighborhood.[13] [32] The line would extend northwest from the existing Green Line terminus at the 7th & Richards / Township 9 station. The plan to extend light rail to the airport has been in the works since early 1990s and is the project most requested by residents of the Sacramento region.[33] The agency has completed preparing the draft environmental impact report for the project.[34]

The project, estimated at nearly $1 billion, would be the costliest in RT's history and securing funding has been a challenge. Transportation officials most recently proposed funding the project with a half-cent sales tax increase in Sacramento County, but the measure was narrowly defeated in November 2016.

Downtown Riverfront Streetcar

See main article: Sacramento Streetcar.

While originally under the jurisdiction of a separate agency, RT is also planning the Downtown Riverfront Streetcar project to expand service to West Sacramento. The new streetcar route would run on a short 1.5miles segment to West Sacramento across the Tower Bridge. The project, while branded as a streetcar service, would share a portion of the light rail tracks to connect to Sacramento Valley Station and is planned to use the same Siemens S700 vehicles as the light rail service.[35]

See also

Notes and References

  1. Web site: June 2015 . RT Fact Sheet . September 9, 2015 . Sacramento Regional Transit District.
  2. Web site: SacRT Question and Answer Session .
  3. Web site: LRFactSheet – Sacramento Regional Transit District . https://web.archive.org/web/20240329153037/https://www.sacrt.com/services/LRFactSheet.aspx/ . March 29, 2024 .
  4. Web site: Minister . R. David . Clarke . David J. . March 30, 1982 . Factors to Consider in Designing a Joint Bus-Light Rail Transit Mall . Transportation Research Board.
  5. News: March 22, 1987 . Connections: Sacramento Light Rail & Bus Schedules . 2 . The Sacramento Bee.
  6. News: March 16, 1987 . RT Metro Light Rail Timetable . Sacramento Regional Transit District.
  7. Web site: SacRT History . May 2, 2019 . www.sacrt.com.
  8. Web site: October 13, 1999 . Light Rail map . dead . https://web.archive.org/web/19991013063112/http://sacrt.com/Service_Info/Routes_Schedules/Current/maps/R514.gif . October 13, 1999 . May 2, 2019 . Sacramento Regional Transit District.
  9. News: Depster . Doug . 19 October 1983 . Light-Rail Delays Could Raise Costs . The Sacramento Bee . 19 . . 24 October 2023 . Newspapers.com.
  10. News: Dempster . Doug . December 28, 1982 . New Light-Rail Controversy . 12 . . 24 October 2023 . Newspapers.com.
  11. Web site: . Folsom Line . November 25, 2023.
  12. Web site: . Folsom Amtrak . November 25, 2023.
  13. Web site: Home . dead . https://web.archive.org/web/20160513223917/http://www.greenline2airport.com/ . May 13, 2016 . May 2, 2019 . Green Line 2 Airport . en-US.
  14. RT Celebrates Grand Opening of Blue Line to Cosumnes River College Light Rail Extension . August 22, 2015 . December 4, 2018 . Sacramento Regional Transit District.
  15. Web site: Sacramento Regional Transit District (Sacramento RT) . March 14, 2019 . National Transit Database.
  16. Web site: 507 - GOLD LINE Train . 2023-11-13 . www.sacrt.com.
  17. Web site: Services – Sacramento Regional Transit District . July 8, 2024 . Sacramento Regional Transit District . en-US.
  18. Web site: July 2021 . SacRT System Fact Sheet . February 14, 2022 . Sacramento Regional Transit District.
  19. Web site: July 2021 . SacRT System Fact Sheet . February 14, 2022 . Sacramento Regional Transit District.
  20. Web site: Art on Track – Station Art Along Light Rail. Sacramento Regional Transit District. February 2, 2010. dead. https://web.archive.org/web/20100103101747/http://sacrt.com/documents/brochures/StationArt.pdf. January 3, 2010.
  21. SacRT Purchases New Low-Floor Light Rail Vehicles . April 22, 2020 . Sacramento Regional Transit . April 24, 2020.
  22. News: Arrington . Debbie . July 6, 2020 . SacRT trains to get low-profile upgrade: Sacramento-built light rail vehicles part of system-wide modernization . en . Chico News & Review Spotlight . August 22, 2020.
  23. Web site: October 10, 2023 . Sacramento Regional Transit adds to order for Siemens light rail equipment . October 10, 2023 . Trains.com.
  24. Web site: Light Rail Modernization Project Sacramento Regional Transit District .
  25. https://www.sacrt.com/apps/sacrt-orders-nine-additional-low-floor-light-rail-vehicles/
  26. Web site: February 2008 . Sacramento Regional Transit Light Rail Fact Sheet . January 23, 2007 . Sacramento Regional Transit.
  27. Siemens-refurbished light rail vehicles to begin operating on new Sacramento Regional Transit line . September 8, 2015 . November 3, 2016 . https://web.archive.org/web/20161104030509/http://news.usa.siemens.biz/press-release/mobility/siemens-refurbished-light-rail-vehicles-begin-operating-new-sacramento-region . November 4, 2016 . Siemens USA.
  28. Web site: Alba . Carmen . APPROVING THE SALE OF 3 SURPLUS URBAN TRANSPORTATION DEVELOPMENT CORPORATION LIGHT RAIL VEHICLES TO THE U.S DEPARTMENT OF HOMELAND SECURITY, TRANSPORTATION SECURITY ADMINISTRATION . Sacrt.com . Sacramento Regional Transit . 3 July 2024.
  29. Web site: SacRT Awarded $45 Million by FTA for New Light Rail Vehicles – Sacramento Regional Transit District .
  30. Web site: Light Rail Modernization: New Low-Floor Light Rail Vehicles – Sacramento Regional Transit District . 2023-11-26 . en-US.
  31. Web site: Construction Begins in January 2024 for Folsom 15-Minute Light Service Project – Sacramento Regional Transit District . 2023-11-26 . en-US.
  32. Web site: Sacramento RT website: "Green Line to the Airport". https://web.archive.org/web/20120527183657/http://www.sacrt.com/dna/index.html. dead. May 27, 2012.
  33. News: When will Sacramento get light rail to the airport? Not soon . Bizjak . Tony . January 7, 2015 . The Sacramento Bee . July 10, 2018 . 0890-5738.
  34. Web site: SacRT Initiatives . October 15, 2019 . April 15, 2021.
  35. Web site: Sacramento Downtown Riverfront Streetcar Project. April 24, 2022. May 15, 2024. Sacramento Regional Transit.