State Route 99 tunnel explained

SR 99 tunnel
Location:Seattle, Washington, U.S.
Coordinates:47.6103°N -122.3447°W
Status:Open
Start:South Dearborn Street
47.5965°N -122.3357°W
End:Harrison Street
47.6205°N -122.3447°W
Operator:Washington State Department of Transportation
Toll:$1.20 to $4.70
Construction:2013–2017
Length:9270feet[1] [2]
Lanes:4
Speed:45mph
Height:15feet
Width:52feet

The State Route 99 tunnel, also known as the Alaskan Way Viaduct replacement tunnel, is a bored highway tunnel in the city of Seattle, Washington, United States. The 2miles, double-decker tunnel carries a section of State Route 99 (SR 99) under Downtown Seattle from SoDo in the south to South Lake Union in the north.

Since the 2001 Nisqually earthquake, the replacement of the Alaskan Way Viaduct had been the source of much political controversy demonstrating the Seattle process. Options for replacing the viaduct, which carried 110,000 vehicles per day, included replacing it with a cut-and-cover tunnel or a bored tunnel, replacing it with another elevated highway, or eliminating it while modifying other surface streets and public transportation. The current plan emerged in 2009 when government officials agreed to a deep-bore tunnel.

Construction began in July 2013 using "Bertha", at the time the world's largest-diameter tunnel boring machine. After several delays, tunnel boring was completed in April 2017, and the tunnel opened to traffic on February 4, 2019.

Description

The SR 99 tunnel is a single tube that measures 9270feet long and 52feet wide, carrying a double-decker highway that is 32feet wide and has two lanes in each direction.[3] [4] [5] Each deck has two 11feet lanes, an 8feet west shoulder, and a 2feet east shoulder.[6] The decks are designed with banks of two degrees in turns and four-degree grades to facilitate designed speeds of 50mph.[7] [8] Below the highway decks are utility lines and mechanical spaces for the tunnel's ventilation, lighting, and fire suppression systems.[9]

The tunnel has 15 emergency refuge areas located every 650feet with escape routes that lead to the north and south portals. Variable message signs and emergency phones are also located throughout the entire tunnel.[8] The tunnel is monitored by over 300 security cameras that are fed into a WSDOT traffic control center in Shoreline that can dispatch incident response teams.[7] [10] In the event of a fire, a set of fiber optic cables in the ceiling would sense heat and activate sprinklers.[11] A set of large fans located in the two portal operations buildings would then force smoke out through a set of 40feet ventilation shafts.[7] [12] The tunnel also has repeaters for cell phone and FM radio service; WSDOT can override the latter for emergency broadcasts.[5] [10]

Route

The tunnel begins south of Downtown Seattle in the SoDo neighborhood, adjacent to the Port of Seattle's container ship terminal and the city's two outdoor sports stadiums, Lumen Field and T-Mobile Park. SR 99 enters the tunnel after passing Royal Brougham Way and an interchange with Alaskan Way at South Dearborn Street located adjacent to the south maintenance area and ventilation shaft.[13] An additional set of ramps connect to South Royal Brougham Way and Colorado Avenue South, which terminates a block south at South Atlantic Street. The tunnel carries two lanes of southbound traffic on its upper deck and two lanes of northbound traffic on its lower deck,[6] and functions as a complete bypass of Downtown Seattle with no intermediate exits; it has a posted speed limit of 45mph.[6]

The tunnel travels northwesterly under Pioneer Square and Downtown Seattle, generally following 1st Avenue.[13] It reaches its deepest point at Virginia Street, approximately 211feet below street level, and begins its turn north through parts of Belltown and the Denny Triangle.[14] The tunnel emerges at a portal located west of Aurora Avenue and north of Harrison Street, adjacent to a tunnel operations building. SR 99 continues onto Aurora Avenue and crosses over Mercer Street, while an onramp allows access to the tunnel from 6th Avenue and an offramp carries tunnel traffic to Republican Street in South Lake Union.[6] [13]

Tolls

The SR 99 tunnel is tolled with a variable rate that changes based on time of the day, number of vehicle axles, and payment method. Tolls are collected electronically, with a lower rate for Good to Go pass users and a higher rate for scanned plates that are sent a bill in the mail.[15] Tolling began on 9 November 2019, with the rate for two-axle vehicles set at $1.20 to $2.70 for Good to Go users and $3.20 to $4.70 for pay-by-mail users.[16] [17] The start of tolling was delayed by several months due to vendor issues and the viaduct demolition running behind schedule.[18] Toll collection is expected to yield $22 million in annual revenue, which will cover 6 percent of the construction costs of the tunnel megaproject and its debts; the toll-collection vendor will be paid $16 million for system setup and $29 million over a five-year period.[19] Beginning in 2022, the toll rates will increase by three percent annually with approval from the state transportation commission.[20]

Planning history

Viaduct and earthquake risks

See main article: Alaskan Way Viaduct.

The Alaskan Way Viaduct was a double-decked elevated freeway that ran along Elliott Bay on the Downtown Seattle waterfront and, until January 11, 2019, when it was permanently closed, carried a section of State Route 99 (SR 99). It first opened to traffic on April 4, 1953, to provide a vehicular bypass of downtown for U.S. Route 99, the predecessor of SR 99; it connected with the Battery Street Tunnel, which opened the following year, and several downtown ramps that were completed years later.[21] The viaduct and tunnel cost $18 million to construct (equivalent to $ in dollars) and severed the waterfront from the rest of downtown.[22] [23]

The viaduct remained the primary north–south highway in Downtown Seattle until the construction of Interstate 5 (I-5) in the late 1960s. Weekday traffic volumes on the viaduct averaged around 110,000 vehicles per day in the mid-2000s, approximately half of equivalent sections on I-5.[24] [25] Calls to replace the viaduct and build a waterfront promenade surfaced as early as the late 1960s and early 1970s, increasing after the halted demolition of the Pike Place Market.[21] The viaduct runs above the surface street, Alaskan Way, from S. Nevada Street in the south to the entrance of Belltown's Battery Street Tunnel in the north, following previously existing railroad lines.

The 1989 Loma Prieta earthquake destroyed the similarly designed Cypress Street Viaduct in Oakland, California, with the loss of 42 lives.[26] The 2001 Nisqually earthquake damaged the viaduct and its supporting Alaskan Way Seawall and required the Washington State Department of Transportation (WSDOT) to invest US$14.5 million in emergency repairs. Experts gave a 1-in-20 chance that the viaduct could be shut down by an earthquake within the following decade.[27] After the Nisqually earthquake, the viaduct was closed twice a year for WSDOT to conduct inspections of the structure.[28] Those inspections discovered continuing settlement damage. In 2005, a group of researchers and faculty from the University of Washington urged political officials to close the viaduct within a two-year timeframe.[29]

Options and political debate

Several replacement proposals were developed. Many Seattle leaders, including then-Mayor Greg Nickels and state and city transportation officials, favored building a tunnel. Plans for a six-lane, "cut-and-cover" double-decker tunnel were developed.[30] The tunnel was envisioned to solve not only the viaduct's traffic limitations and safety problems, but also to allow better uses for the waterfront real estate, including parks, housing, and retail developments. While future development of the Alaskan Way real estate corridor may provide tax revenue for the city, many state lawmakers objected to the cost of the proposed six-lane tunnel. One criticism compared the plan to Boston's Big Dig project, which was said to illustrate the schedule and budget challenges of a large cut-and-cover tunnel. Proponents responded that the Seattle proposal was significantly smaller in scale than the Big Dig.

Another proposal aimed to replace the current viaduct with another elevated structure with updated seismic standards. This new viaduct would be larger, 12feet wide lanes with new shoulders on both sides, compared to the structure it would replace, which had no shoulders and lanes as narrow as in places. The on and off ramps at the northern and southern portion of the viaduct would remain the same with an additional full intersection at South Atlantic Street and South Royal Brougham Way. The First Avenue off ramp would be removed. The plan included a complete replacement of the sea wall. It was estimated to cost $2.8 billion and take 10–12 years to construct.[31] Many prominent leaders and organizations opposed the elevated structure and believed this was a unique opportunity to remove the viaduct and connect downtown Seattle to the waterfront. Former Governors Dan Evans and Gary Locke, former U.S. Senator Slade Gorton,[32] and the American Institute of Architects[33] recommended against rebuilding the viaduct.

WSDOT evaluated five proposals in 2003–2004 and decided that the six-lane cut-and-cover tunnel was the preferred alternative. Rebuilding the viaduct was retained as a backup plan.[34]

However, due to the costs and scope of the project, other options were still being discussed in the local media. A proposal to remove the viaduct and replace it with surface street and transit improvements was backed by former King County Executive Ron Sims,[35] the People's Waterfront Coalition, and the Congress for the New Urbanism.[36] Proponents of this plan offered examples of successes in removing highways in other cities. They envisioned the waterfront becoming a pedestrian-friendly neighborhood with a mix of commercial, retail, and public park spaces. Traffic needs would be addressed through modifications to existing streets, I-5, and public transit; they argued that these modifications would be desirable in any event. Proponents further argued that this plan had the potential to improve the tourist economy, create jobs, and encourage a denser and more residential downtown through the offering of a generous waterfront park.[37] The total cost of removal of the viaduct, repairing the seawall, and improvements to I-5 and existing streets was unofficially estimated to be $1.6 billion. In 2006, Seattle City Council member Peter Steinbrueck noted, "While the mayor's first choice is the tunnel, he supports the City Council's resolution that designates a surface and transit alternative as a backup."[38]

In response to concerns about the cost of the originally proposed tunnel construction, the city council created a scaled-down, four-lane hybrid tunnel option. This would have combined the smaller tunnel with surface transit improvements to address traffic needs. The tunnel's 14feet shoulders would be used as an extra travel lane each way during periods of high demand. Transit service would be increased during peak commuter periods. Cars entering and exiting from Elliott and Western Avenues would each have a dedicated lane. Third Avenue would become a permanent transit corridor. The cost estimate for the four-lane tunnel was $3.4 billion.[39] On February 13, 2007, Governor Christine Gregoire rejected the tunnel hybrid option, saying that a WSDOT review showed the tunnel proposal "does not meet state and federal safety standards." Of particular concern was that the use of shoulders as traffic lanes during peak traffic times would leave no additional lanes for emergency access.[40] However, several of the viaduct "stakeholders committee" brought on board to advise the city indicated that the tunnel option should remain on the table.[41]

State and city officials deadlocked in late 2006 over whether to build an elevated structure (the state's preference) or a hybrid tunnel (the city's preference). Governor Gregoire stated "no action" was not an option for the viaduct.[42] The state government called for an advisory ballot on March 13, 2007, for Seattle residents, which was supported by the city council. The advisory ballot allowed Seattleites to vote on whether they supported a surface-tunnel hybrid and whether they supported an elevated structure.[43] Voters rejected both options, with the surface-tunnel hybrid getting only 30% support and the elevated structure only 43%.[44]

Mayor Mike McGinn, elected in 2009 and opposed to highway expansion, joined other tunnel opposition groups to refer city council-approved agreements about the tunnel to the voters as a citizen's referendum.[45] The referendum was initially blocked by a lawsuit from the city, but was pared down to one aspect of the city's approval for the project and placed on the August 2011 ballot.[46] [47] Under the ruling, the referendum would only challenge one section of the original 140-page City Council ordinance that approved agreements over street use, utilities, design and liability for the tunnel following completion of the project's ongoing environmental review process. The referendum vote approved the City Council's actions by 58 percent on August 16, 2011.[48] The Federal Highway Administration completed its analysis of the project's final EIS and issued its record of decision with WSDOT later that month, allowing pre-construction activities to begin.[49]

Bored tunnel selection

In January 2008, as debate on its replacement continued, Governor Gregoire announced that the State of Washington would take down the viaduct in 2012.[50] On January 12, 2009, the state of Washington, King County, the city of Seattle, and the Port of Seattle revealed that they had agreed to replace the viaduct with a bored tunnel.[51] On March 4, 2009, the state senate passed a bill endorsing the tunnel option.[52] On May 12, 2009, Governor Gregoire signed Senate Bill 5768, authorizing $2.8 billion in state funds for a possible deep-bore tunnel.

Disparate factions, ranging from some environmentalists to some industrialists, criticized the tunnel decision.[53] A business owner argued that the restrictions on hazardous cargo through the tunnel would restrict movement of freight through downtown, though hazardous cargo is already prohibited from the Battery Street Tunnel and the viaduct at peak hours.[54] Similarly, another argued that surface traffic would increase, which would cause further problems to downtown freight transport. A chairman of a local Sierra Club chapter argued that the large investment in automobile transport did not take into account global warming concerns.

Design and funding

The approved design is a four-lane, 2miles long bored tunnel. The tunnel has a south portal in SoDo, near Lumen Field, and a north portal in South Lake Union, east of Seattle Center. The route goes beneath Pioneer Square, the central business district of Downtown, and Belltown.

The project is estimated to cost US$3.29 billion, with $2.8 billion coming from the state and federal governments to cover the tunnel boring and a new interchange in SoDo.[55] The replacement project also includes the following projects and funding sources:

WSDOT began part of the larger project in 2008, while the replacement debate was still on-going, by repairing some of the viaduct columns.[58]

The $80 million tunnel boring machine (TBM) Bertha was created for this project by Hitachi Zosen Corporation near Osaka, Japan. The 326feet, 6700short ton TBM was disassembled into 40 pieces and shipped to Seattle, where it was reassembled in the launch pit near the south end of the future tunnel.[59] From there, the record-breaking 57.5feet diameter borer would move in 6.5feet increments toward the north end.[60] [61]

WSDOT nicknamed the TBM "Bertha" after Seattle's first female mayor, Bertha Knight Landes. This name was chosen from names submitted by kindergarten through 12th grade students for a naming competition.[62]

Construction

The primary construction contractor was Seattle Tunnel Partners (STP). The initial phase of demolition and removal of the viaduct began on October 21, 2011, to prepare the southern portal. Only a southern portion of the viaduct was removed at that time; the viaduct along the central waterfront remained open for traffic until the tunnel was complete.[63] [64]

Boring of the tunnel with the 57.5feet diameter "Bertha," at the time the world's largest-diameter tunnel-boring machine, began on July 30, 2013,[65] [66] and at the time was expected to be completed in 14 months.[67] After three weeks of drilling, the project was estimated to be two weeks behind schedule; problems with fiberglass near the front of the drill and a labor dispute with a local longshoreman's union were blamed.[68] Work was halted on December 6, 2013 after the machine overheated and shut down [69] approximately 1083feet into the planned 9270adj=midNaNadj=mid route. Investigations later revealed the seal system that protects the machine's main bearing had been damaged. Three days prior to stopping, the machine mined through a hollow, 8-inch steel well-casing and pipe used to measure groundwater in 2002 around Alaskan Way, which was drilled as part of the planning phases of the project.[70] The unexpected discovery of the pipe was blamed by the contractor for the work stoppage in litigation, but STP later admitted to its knowledge of the pipe's location prior to the start of tunnel boring.[71] This delay lasted for more than two years as the workers had to dig a 120feet vertical shaft down to Bertha's cutting head to repair it. Settling was discovered in Pioneer Square that may be related to this additional excavation.[72]

Tunnel boring had resumed on December 22, 2015.[73] [74] The tunnel boring was halted 23 days later on January 14, 2016, after a 30adj=midNaNadj=mid sinkhole developed on the ground in front of the machine, causing Governor Jay Inslee to halt drilling until the contractors can perform a root cause analysis to show that the machine can be run safely.[75] Even though contractors filled the hole with of material, the ground above the tunnel-boring machine continued to sink, according to the Washington State Department of Transportation. The tunneling restriction was lifted on February 23, 2016, and tunneling resumed that day.[76] Bertha passed under the Alaskan Way Viaduct in early May, closing the roadway for 11 days as the machine had 15feet of vertical clearance under the structure's pilings.[77] On April 4, 2017, the tunnel boring machine broke through to the recovery pit on the north end of the tunnel, completing the excavation process.[78] The boring machine was dismantled and removed from the site over the next four months.[79]

Dirt produced by tunnel construction was sent to fill a CalPortland quarry in nearby Port Ludlow.[80] In July 2016, WSDOT estimated that the tunnel would be completed and open to traffic in early 2019. An estimated $223 million in cost overruns were reported as a result of the two-year stoppage.[81] The delay in construction caused by Bertha's stall cost the state government $60 million in extra costs that were granted by a budget increase from the legislature. The damage to the tunnel boring machine itself was estimated at $642 million, which became the center of a legal dispute between WSDOT and STP.[82] Fragments of the steel well casing struck in December 2013 and cited as a possible cause of Bertha's breakdown were stored as evidence at the construction site and subsequently went missing in 2014.[83] Detailed journal entries kept by the tunnel contractor's deputy project manager between December 2013 and February 2014 also went missing.[84] In December 2019, a jury in Thurston County awarded $57.2 million in damages to WSDOT and found that the state government was not liable to cover STP's claimed repair costs of $300 million.[85]

Opening

Seattle Tunnel Partners announced that work was substantially complete on the tunnel in October 2018.[86] The viaduct closed permanently on January 11, 2019.[87] Following the closure of the viaduct, sections of SR 99 were closed to traffic for three weeks to allow for the excavation of buried tunnel ramps at the north and south portals, as well as other preparations. The closure was widely expected to cause increased traffic congestion, and local government agencies responded by implementing expanded transit service and making other transportation changes to accommodate the displaced drivers. Despite the predicted traffic congestion, commute times for the Seattle area were not significantly above average, with many commuters opting for public transit, remote work, or bicycling to work.[88] On February 2, 2019, the downtown tunnel and sections of the viaduct and Battery Street Tunnel were opened to pedestrians as part of a community celebration and festival that was attended by 100,000 people. The celebrations included an 8K run, temporary art exhibits, food trucks, street performances, interactive exhibits, and an official ribbon-cutting ceremony.[89] [90] The following day, a bicycle race was held on the viaduct and in the new tunnel, with 12,000 participants.[91] The state government also spent $4.4 million on billboards and advertisements on television and buses to market the new tunnel.[92]

The tunnel opened to northbound vehicular traffic at 11 p.m. on February 3 and southbound traffic at 12:15 a.m. on February 4.[93] Other ramps and roads associated with the tunnel project, including an extension of Alaskan Way to Terminal 46 and the Harrison Street crossing were opened;[94] the lone exception was the northbound offramp from SR 99 to Dearborn Street, which opened on February 19.[95] The first full day of tunnel operations saw lower traffic volumes, with only 22,145 vehicle trips, due to an ongoing snowstorm, as well as confusion at the left-side exits.[96] [97] Within days, reports of smoke and haze within the tunnel prompted WSDOT to investigate possible faults in the exhaust ventilation system.[98] Within months of opening, tunnel usage had increased to over 70,000 trips per weekday and a weekly volume just under 500,000 trips by late March 2019.[99] [100] Tolls were waived for the first few months of operations and began to be collected on November 9, 2019.[101] WSDOT measured traffic before and after the start of tolling and reported a 26 percent decline in average weekday volumes in the tunnel, with no noticeable spike on nearby I-5.[102] Higher volumes have been observed on Alaskan Way and other surface streets, especially during peak periods.[103]

In 2019, WSDOT began filling in the Battery Street Tunnel, because the 1952 cut-and-cover tunnel did not meet modern safety standards, was expensive to maintain, and was made redundant by the Alaskan Way tunnel.[104] [105]

See also

Further reading

External links

Notes and References

  1. Web site: Tunneling toward a new SR 99; The SR 99 tunnel route (map) . . December 8, 2012 . https://web.archive.org/web/20121210035623/http://www.wsdot.wa.gov/Projects/Viaduct/About/Tunneling . December 10, 2012 . live .
  2. Web site: Follow Bertha . Washington State Department of Transportation . December 25, 2018.
  3. News: Porterfield . Elaine . May 2017 . Tunnel Vision: A 360 Look at Bertha Underground . . December 25, 2018.
  4. News: May 2017 . Tunneling into the numbers . Washington State Department of Transportation . December 30, 2018.
  5. News: Lindblom . Mike . Baruchman . Michelle . January 31, 2019 . Highway 99 tunnel opens next week. Here are answers to your questions about the project . The Seattle Times . January 31, 2019.
  6. News: Lindblom . Mike . November 19, 2018 . When does the viaduct close? How much is the tunnel toll? Your guide to Seattle's Highway 99 project . . December 25, 2018.
  7. News: Lindblom . Mike . April 16, 2017 . Inside the Highway 99 tunnel: Bertha's done digging, but the roadway work rolls on . B1 . The Seattle Times . December 25, 2018.
  8. Web site: Seattle's new SR 99 tunnel . Washington State Department of Transportation . December 25, 2018.
  9. News: April 4, 2017 . Life after Bertha: Focus shifts from mining to other tunnel work . Washington State Department of Transportation . December 25, 2018.
  10. News: Martin . Casey . January 30, 2019 . Here's why it's safe to drive through the new tunnel . KUOW . January 31, 2019.
  11. News: Minnick . Benjamin . March 28, 2018 . A trip inside our new 'smart' tunnel . . December 25, 2018.
  12. News: Schlosser . Kurt . August 31, 2018 . Seattle tunnel's high-tech ventilation system designed to keep air fresh deep below ground . . December 25, 2018.
  13. Web site: January 2017 . Traveling on the new SR 99 corridor . Washington State Department of Transportation . December 25, 2018.
  14. Web site: July 2016 . Tunneling toward a new SR 99 corridor . Washington State Department of Transportation . December 25, 2018.
  15. News: Lindblom . Mike . April 18, 2018 . Highway 99 tunnel tolls could range from $1 to $2.25, depending on time of day . The Seattle Times . December 25, 2018.
  16. Web site: SR 99 Tunnel Toll Rates . Washington State Department of Transportation . July 21, 2023.
  17. News: October 16, 2018 . SR 99 tunnel toll rates will range from $1 to $2.25 in Seattle . KING 5 News . December 25, 2018.
  18. News: Lindblom . Mike . June 12, 2019 . Highway 99 tunnel users won't have to pay tolls until sometime this fall . The Seattle Times . June 12, 2019.
  19. News: Lindblom . Mike . November 12, 2019 . How is your Highway 99 toll money spent? A big chunk goes to collecting the tolls . The Seattle Times . November 20, 2019.
  20. Web site: October 2018 . SR 99 Tunnel Toll Rate Setting . Washington State Transportation Commission . February 9, 2019.
  21. News: Lange . Larry . March 9, 2007 . Would a new viaduct be 'bigger and uglier'? . B1 . . December 26, 2018.
  22. Web site: State of Washington, Department of Transportation (WSDOT), Alaskan Way Viaduct, Seattle, WA (1950-1959) . Pacific Coast Architecture Database . December 25, 2018.
  23. News: Diltz . Colin . November 22, 2018 . Seattle has changed: See the Alaskan Way Viaduct under construction in the 1950s . A1 . . December 25, 2018.
  24. Web site: Ott . Jennifer . December 19, 2011 . Alaskan Way Viaduct, Part 4: Replacing the Viaduct . . December 26, 2018.
  25. Web site: Is most of the traffic using the viaduct today going to downtown or through downtown? . WSDOT . December 8, 2012 . https://web.archive.org/web/20130427122459/http://www.wsdot.wa.gov/Projects/Viaduct/Contents/Item/Display/144 . April 27, 2013 . live .
  26. Web site: Cypress Viaduct Freeway . dead . https://web.archive.org/web/20090707140502/http://home.pacbell.net/hywaymn/Cypress_Viaduct_Freeway.html . July 7, 2009 .
  27. Web site: Dutiful Servant, Brutal Barrier: The Viaduct at a Crossroads . Pacific Northwest . The Seattle Times . April 7, 2002 . Ross . Anderson . December 8, 2012 . https://web.archive.org/web/20160304000615/http://community.seattletimes.nwsource.com/archive/?date=20020407&slug=pviaduct07 . March 4, 2016 . live .
  28. Web site: Viaduct Inspections . Washington State Department of Transportation . 2018 . https://web.archive.org/web/20180906092354/http://www.wsdot.wa.gov/Projects/Viaduct/About/ViaductInspections . September 6, 2018 . October 11, 2018.
  29. News: Shut down the viaduct . March 2, 2006 . Scott . Miles . David R. . Montgomery . Bill . Beyers . The Seattle Times . December 8, 2012 . https://web.archive.org/web/20121008111126/http://seattletimes.com/html/opinion/2002837776_viaduct02.html . October 8, 2012 . live .
  30. Web site: Alaskan Way Viaduct In-depth . Seattle Channel . December 8, 2012 . dead . https://web.archive.org/web/20121228222304/http://www.seattlechannel.org/issues/viaduct.asp . December 28, 2012 . (See the "Background" tab in particular.)
  31. Web site: WSDOT Viaduct Alternatives Information . https://web.archive.org/web/20061026053920/http://www.wsdot.wa.gov/Projects/Viaduct/Alternatives.htm . October 26, 2006 . WSDOT.
  32. News: Gilmore . Susan . December 12, 2006 . Opposition to viaduct addressed to Gregoire . Seattle Times . https://web.archive.org/web/20181012051134/https://www.seattletimes.com/seattle-news/opposition-to-viaduct-addressed-to-gregoire/. October 12, 2018. October 11, 2018.
  33. News: Bennett . Sam . Tunnel to replace Alaskan Way Viaduct in Seattle . Daily Journal of Commerce . Portland, OR . January 14, 2009 . Newspaper Source Plus.
  34. Book: Alaskan Way Viaduct Replacement Project: Final Environmental Impact Statement . Appendix B: Alternatives Description and Construction Methods . July 2011 . WSDOT . December 11, 2012 . https://web.archive.org/web/20140710094449/http://data.wsdot.wa.gov/publications/viaduct/AWVFEIS-AppendixB.pdf . July 10, 2014 . live .
  35. News: Gregoire nixes surface option for viaduct . February 19, 2007 . KOMONews.com . AP . December 7, 2012 . https://web.archive.org/web/20160304063245/http://search.komonews.com/blankpage?page=details&pid=5941281&id=88354175 . March 4, 2016 . live .
  36. Web site: Seattle's Alaskan Way Viaduct . Congress for the New Urbanism . December 8, 2012 . https://web.archive.org/web/20130107064716/http://www.cnu.org/highways/seattle . January 7, 2013 . dead .
  37. Web site: Stop the Insanity . The Stranger . Dominic . Holden . March 16, 2011 . August 1, 2013 . https://web.archive.org/web/20130728110404/http://www.thestranger.com/seattle/stop-the-insanity/Content?oid=7200124 . July 28, 2013 . live .
  38. News: Climate's Right For Fresh Viaduct Plan . Peter . Steinbrueck . October 10, 2006 . The Seattle Times . December 8, 2012 . https://web.archive.org/web/20120826005417/http://community.seattletimes.nwsource.com/archive/?date=20061010&slug=steinbrueck10 . August 26, 2012 . live .
  39. News: Garber . Andrew . Young . Bob . Gilmore . Susan . Nickels' backing for 4-lane "tunnel lite" gets cool reception . February 7, 2019 . The Seattle Times . January 17, 2007.
  40. News: State says no tunnel; mayor still wants vote . https://archive.today/20130202222454/http://seattletimes.com/html/localnews/2003571128_viaductreport14m0.html . dead . February 2, 2013 . February 14, 2007 . Andrew . Garber . Susan . Gilmore . Mike . Lindblom . The Seattle Times .
  41. News: City, county, state agree on tunnel to replace viaduct . The Seattle Times . January 12, 2009 . Andrew . Garber . Mike . Lindblom . Emily . Heffter . dead . https://web.archive.org/web/20121013133922/http://seattletimes.com/html/localnews/2008619010_webviaduct12m.html . October 13, 2012 .
  42. News: Tunnel option off table for viaduct replacement . January 17, 2007 . Seattle Post-Intelligencer . Chris . McGann . Melissa . Santos . Larry . Lange . December 8, 2012 . https://web.archive.org/web/20121015084440/http://www.seattlepi.com/local/transportation/article/Tunnel-option-off-table-for-viaduct-replacement-1225701.php . October 15, 2012 . live .
  43. News: Viaduct vote set; state may ignore it . The Seattle Times . March 7, 2007 . Bob . Young . dead . https://web.archive.org/web/20080706041118/http://seattletimes.nwsource.com/html/politics/2003533235_viaductvote20m.html . July 6, 2008 .
  44. Web site: King County Election Results (Mar. 13 special election) . King County . March 27, 2007 . December 8, 2012 . https://web.archive.org/web/20120823013319/http://your.kingcounty.gov/elections/200703/res.htm . August 23, 2012 . live .
  45. News: Yardley . William . August 19, 2011 . Seattle, After Decade of Debate, Approves Tunnel . A13 . The New York Times . December 23, 2018.
  46. News: Thompson . Lynn . Lindblom . Mike . May 21, 2011 . Judge: Anti-tunnel measure going on August ballot . A1 . The Seattle Times . February 4, 2019.
  47. Web site: Referendum 1 (August 2011). King County Elections. February 4, 2019.
  48. News: August 17, 2011 . Voters backing Seattle tunnel; fight may finally be over . A1 . The Seattle Times . February 4, 2019.
  49. News: Gutierrez . Scott . August 23, 2011 . SR 99 deep bore tunnel gets federal approval . Seattle Post-Intelligencer . December 23, 2018.
  50. News: Gregoire: 'Watch me' tear down the viaduct . January 3, 2008 . Seattle Post-Intelligencer . Chris . McGann . December 8, 2012 . https://web.archive.org/web/20121015084457/http://www.seattlepi.com/local/transportation/article/Gregoire-Watch-me-tear-down-the-viaduct-1260638.php . October 15, 2012 . live .
  51. News: Andrew . Garber . Tunnel in place of viaduct: A deal, but how to pay? . The Seattle Times . January 13, 2009 . dead . https://web.archive.org/web/20090115000109/http://seattletimes.nwsource.com/html/localnews/2008621043_viaduct13m.html . January 15, 2009 .
  52. News: Senate passes bill to replace viaduct with tunnel . March 4, 2009 . Andrew . Garber . The Seattle Times . March 5, 2009 . https://web.archive.org/web/20101112071836/http://blog.seattletimes.nwsource.com/politicsnorthwest/2009/03/04/senate_passes_bill_to_replace.html . November 12, 2010 . dead .
  53. News: Mike . Lindblom . Sara Jean Green . Gregoire announces tunnel plans; car-tab taxes might help pay for it . The Seattle Times . January 13, 2009 . dead . https://web.archive.org/web/20090115232433/http://seattletimes.nwsource.com/html/localnews/2008622393_webviaduct13m.html . January 15, 2009 .
  54. Web site: Alaskan Way Viaduct: Will there be restrictions on freight using the tunnel?. wa.gov. August 3, 2015. https://web.archive.org/web/20150912180250/http://www.wsdot.wa.gov/Projects/Viaduct/Contents/Item/Display/156. September 12, 2015. live.
  55. Web site: Alaskan Way Viaduct: Budget . WSDOT . February 5, 2019.
  56. Web site: Will tolling cause diversion? . December 26, 2013 . WSDOT . https://web.archive.org/web/20140712103641/http://www.wsdot.wa.gov/Projects/Viaduct/Contents/Item/Display/493 . July 12, 2014 . live .
  57. Web site: Advisory Committee on Tolling and Traffic Management (2011–present) . December 26, 2013 . WSDOT . https://web.archive.org/web/20140214230559/http://www.wsdot.wa.gov/projects/viaduct/Library/Meetings/ACTTM . February 14, 2014 . live .
  58. Web site: Seattle Tunnel Partners . December 1, 2015 . Seattle Tunnel Partners monthly schedule: November 2015 . Washington State Department of Transportation . December 27, 2015 . https://web.archive.org/web/20151228040445/http://www.wsdot.wa.gov/Projects/Viaduct/Media/Default/-NewDocuments/Schedule/STP_Schedule_November_2015.pdf . December 28, 2015 . live .
  59. Robinson, Patrick . September 7, 2012 . Seattle Deep Bore Tunnel Tour Sept. 6, 2012 . West Seattle Herald . December 1, 2016 . https://web.archive.org/web/20160425055801/https://www.youtube.com/watch?v=s0NF_9EkKFE . April 25, 2016 . live .
  60. Web site: Digging an Enormous Tunnel Under Downtown Seattle . Popular Mechanics . August 30, 2012 . Tim . Newcomb . December 9, 2012 . https://web.archive.org/web/20121105061605/http://www.popularmechanics.com/technology/engineering/extreme-machines/digging-the-worlds-widest-tunnel-under-downtown-seattle-12203389 . November 5, 2012 . live .
  61. News: Engineering Projects Will Transform Seattle, All Along the Waterfront . The New York Times . December 4, 2012 . Kirk . Johnson . February 26, 2017 . https://web.archive.org/web/20161109183149/http://www.nytimes.com/2012/12/05/us/projects-to-transform-seattle-all-along-the-waterfront.html . November 9, 2016 . live .
  62. Web site: SR 99 tunneling machine tweets her name: Bertha . WSDOT . December 10, 2012 . dead . https://web.archive.org/web/20141110124014/http://www.wsdot.wa.gov/News/2012/12/10_sr99_tunnel-machine-name.htm . November 10, 2014 .
  63. News: Gutierrez . Scott . Alaskan Way Viaduct closure, demolition begin . Seattle Post-Intelligencer . October 22, 2011 . July 16, 2012 . https://web.archive.org/web/20111117133912/http://www.seattlepi.com/local/transportation/article/Countdown-to-the-Alaskan-Way-Viaduct-closure-2228936.php#page-1 . November 17, 2011 . live .
  64. Web site: When will the viaduct be demolished? . December 10, 2014 . WSDOT . https://web.archive.org/web/20150417155611/http://www.wsdot.wa.gov/Projects/Viaduct/Contents/Item/Display/486 . April 17, 2015 . live .
  65. Bertha starts digging: tunneling underway in Seattle. July 30, 2013. Washington State Department of Transportation. Yerkan. KaDeena. December 5, 2015. live. https://web.archive.org/web/20151208144140/http://www.wsdot.wa.gov/News/2013/07/30_SR99BerthaStartsDigging.htm. December 8, 2015.
  66. News: Bertha's excavation mission beginning under downtown. Lindblom. Mike. July 30, 2013. The Seattle Times. December 5, 2015. https://web.archive.org/web/20151215184355/http://www.seattletimes.com/seattle-news/bertharsquos-excavation-mission-beginning-under-downtown/. December 15, 2015. live.
  67. News: Bertha takes first bite of new Seattle tunnel. Esser. Doug. July 31, 2013. July 31, 2013. https://web.archive.org/web/20130803103138/http://www.komonews.com/news/local/Bertha-takes-first-bite-of-new-Seattle-tunnel-217761601.html. August 3, 2013. live. KOMO.
  68. News: Huge tunneling machine off to painfully slow start . August 27, 2013 . The Seattle Times . Mike . Lindblom . dead . https://web.archive.org/web/20131228200658/http://seattletimes.com/html/localnews/2021696892_99tunnelxml.html . December 28, 2013 .
  69. News: Insurance lawyers' new findings increase arguments in case of Bertha machine breakdown. Lindblom. Mike. August 19, 2017. The Seattle Times. August 19, 2017. https://web.archive.org/web/20170819190049/http://www.seattletimes.com/seattle-news/transportation/insurance-lawyers-new-findings-increase-arguments-in-case-of-bertha-machine-breakdown/. August 19, 2017. live.
  70. News: What's blocking Bertha: a long steel pipe. Lindblom. Mike. January 3, 2014. The Seattle Times. January 4, 2014. https://web.archive.org/web/20140104212538/http://blogs.seattletimes.com/today/2014/01/whats-blocking-bertha-a-huge-steel-pipe/. January 4, 2014. live.
  71. News: Bad news: Bertha is damaged. Lindblom. Mike. February 7, 2014. The Seattle Times. February 7, 2014. https://web.archive.org/web/20150324161828/http://www.seattletimes.com/seattle-news/bad-news-bertha-is-damaged/. March 24, 2015. live.
  72. News: In Seattle, a Sinking Feeling About a Troubled Tunnel. Johnson. Kirk. December 9, 2014. The New York Times. February 26, 2017. https://web.archive.org/web/20160314090948/http://www.nytimes.com/2014/12/10/us/in-seattle-a-sinking-feeling-about-a-troubled-tunnel.html. March 14, 2016. live.
  73. Bertha tunnels into next phase of testing. December 22, 2015. Washington State Department of Transportation. Newborn. Laura. December 27, 2015. live. https://web.archive.org/web/20151227032856/http://www.wsdot.wa.gov/News/2015/12/22_berthatunneling.htm. December 27, 2015.
  74. News: Bertha back on the move after 2 years of delays. Lindblom. Mike. December 22, 2015. The Seattle Times. December 27, 2015. https://web.archive.org/web/20160105182306/http://www.seattletimes.com/seattle-news/transportation/bertha-restarts-after-two-years-of-delays/. January 5, 2016. live.
  75. News: Lindblom . Mike . January 14, 2016 . Inslee orders tunnel dig halted as soil sinks above Bertha . The Seattle Times . January 15, 2016 . https://web.archive.org/web/20160206214846/http://www.seattletimes.com/seattle-news/transportation/inslee-orders-bertha-tunneling-stopped-after-sinkhole-forms/ . February 6, 2016 . live .
  76. Web site: Feb. 23 project update: Seattle Tunnel Partners resumes mining. February 23, 2016. https://web.archive.org/web/20160223220618/http://www.wsdot.wa.gov/Projects/Viaduct/library/advisories-and-updates/mining-operations-resume-on-tuesday. February 23, 2016. live. February 23, 2016.
  77. News: Demay . Daniel . May 11, 2016 . Viaduct closure ends, Bertha to make pit stop . Seattle Post-Intelligencer . July 20, 2016 . https://web.archive.org/web/20160714080739/http://www.seattlepi.com/local/transportation/article/Viaduct-closure-ends-Bertha-to-make-pit-stop-7423291.php . July 14, 2016 . live .
  78. News: Lindblom . Mike . April 4, 2017 . Bertha's breakthrough just 'halftime' for tunnel project . The Seattle Times . April 4, 2017 . https://web.archive.org/web/20170404171927/http://www.seattletimes.com/seattle-news/transportation/sense-of-history-builds-as-tunnel-machine-bertha-inches-toward-daylight/ . April 4, 2017 . live .
  79. Web site: Alaskan Way Viaduct - Goodbye Bertha: Final piece of the tunneling machine removed from tunnel. wsdot.wa.gov. WSDOT. December 15, 2017. https://web.archive.org/web/20171215111212/http://www.wsdot.wa.gov/Projects/Viaduct/library/advisories-and-updates/goodbye-Bertha-removed. December 15, 2017. live.
  80. Web site: Where will the dirt from tunneling go?. WSDOT. https://web.archive.org/web/20131219030645/http://www.wsdot.wa.gov/Projects/Viaduct/Contents/Item/Display/499. December 19, 2013. live. December 26, 2013.
  81. News: Bertha's woes grind on: more delay, higher cost for Highway 99 tunnel. Lindblom. Mike. July 21, 2016. The Seattle Times. July 21, 2016. https://web.archive.org/web/20160722130447/http://www.seattletimes.com/seattle-news/berthas-woes-grind-on-more-delay-higher-cost-for-highway-99-tunnel/. July 22, 2016. live.
  82. Web site: Mikkelsen . Drew . Missing evidence questioned in trial over Seattle tunnel boring machine breakdown . KING 5 News . February 23, 2019 . January 9, 2019.
  83. Web site: Johnson . Graham . Dispute over missing evidence in Bertha breakdown goes to court . KIRO 7 News . February 23, 2019 . January 9, 2019.
  84. Web site: Johnson . Graham . Pipe pieces at center of Bertha breakdown lawsuit are missing . KIRO 7 News . February 23, 2019 . December 14, 2018.
  85. News: Lindblom . Mike . December 13, 2019 . Contractor ordered to pay Washington state $57M over tunnel-boring machine Bertha's big stall . The Seattle Times . https://web.archive.org/web/20221022194949/https://www.seattletimes.com/seattle-news/transportation/wsdot-notches-another-legal-win-over-highway-99-tunnel-cost-overruns-after-bertha-hit-pipe/ . October 22, 2022 . December 13, 2019.
  86. News: November 1, 2018 . Seattle tunnel opening celebration set for February 2-3 . KING 5 News . November 1, 2018.
  87. News: Permanent closure of Alaskan Way Viaduct delayed until January. Lindblom. Mike. September 17, 2018. The Seattle Times. September 18, 2018. https://web.archive.org/web/20180917204001/https://www.seattletimes.com/seattle-news/transportation/permanent-closure-of-alaskan-way-viaduct-delayed-until-january/. September 17, 2018. live.
  88. News: Gutman . David . January 24, 2019 . 'The cars just disappeared': What happened to the 90,000 cars a day the viaduct carried before it closed? . The Seattle Times . February 2, 2019.
  89. News: Gutman . David . February 2, 2019 . 'A huge achievement': Pedestrians swarm Seattle as viaduct comes down, tunnel set to open . The Seattle Times . February 2, 2019.
  90. News: Guevara . Natalie . Martin . Genna . February 2, 2019 . Making history: Thousands gather to celebrate opening of new SR-99 tunnel . Seattle Post-Intelligencer . February 2, 2019.
  91. News: Sundell . Allison . February 2, 2019 . Thousands celebrate Seattle tunnel opening with weekend festivities . KING 5 News . February 4, 2019.
  92. News: Lindblom . Mike . January 24, 2019 . Washington state spending $4.4 million to market the Highway 99 tunnel . The Seattle Times . March 3, 2019.
  93. News: Sundell . Allison . February 4, 2019 . Seattle tunnel open to traffic both directions . KING 5 News . February 4, 2019.
  94. News: February 4, 2019 . SR 99 tunnel now open to traffic . Washington State Department of Transportation . February 4, 2019.
  95. News: Lindblom . Mike . February 18, 2019 . Highway 99's northbound offramp in Sodo opens Tuesday morning . The Seattle Times . February 18, 2019.
  96. News: Lindblom . Mike . February 4, 2019 . Low traffic means an easy launch of the Highway 99 tunnel under Seattle . The Seattle Times . February 4, 2019.
  97. News: February 6, 2019 . Over 22,000 trips taken through Seattle's SR 99 tunnel on opening day . KING 5 News . February 6, 2019.
  98. News: Johnson . Graham . February 6, 2019 . WSDOT looking at systems in new SR 99 tunnel after smoke, haze . KIRO 7 News . February 6, 2019.
  99. Web site: Newborn . Laura . How's traffic in Seattle's SR 99 tunnel? . WSDOT Blog . Washington State Department of Transportation . April 7, 2019 . April 5, 2019.
  100. News: Lindblom . Mike . May 14, 2019 . Traffic in new Highway 99 tunnel nearly matches last year's viaduct use . The Seattle Times . May 15, 2019.
  101. News: January 30, 2019 . State Route 99 tunnel toll-free for first few months . KING 5 News . February 2, 2019.
  102. News: December 9, 2019 . What's happened to traffic since SR 99 tunnel tolling started . WSDOT Blog . Washington State Department of Transportation . December 18, 2019.
  103. News: Kostanich . Kara . November 20, 2019 . Where SR99 tunnel drivers are diverting to avoid the new toll . KOMO News . December 18, 2019.
  104. Web site: What will happen to the Battery Street Tunnel?. WSDOT. https://web.archive.org/web/20131219025222/http://www.wsdot.wa.gov/Projects/Viaduct/Contents/Item/Display/485. December 19, 2013. live. December 26, 2013.
  105. Web site: Filling and sealing the Battery Street Tunnel . WSDOT.