Ressano Garcia Thermal Power Station Explained

Ressano Garcia Thermal Power Station
Coordinates:-25.4617°N 32.0053°W
Country:Mozambique
Location:Ressano Garcia, Moamba District, Maputo Province
Owner:Electricidade de Moçambique & Sasol
Status:O
Th Fuel Primary:natural gas
Ps Electrical Capacity:175MW
Commissioned:February 2016

Ressano Garcia Thermal Power Station is a 175MW natural gas-fired thermal power plant located in the town of Ressano Garcia in the Maputo Province of Mozambique.[1]

Location

The power station is located in the town of Ressano Garcia, in the Moamba District of Maputo Province. This is in extreme southwestern Mozambique, adjacent to the international border with South Africa. Ressano Garcia sits across the border from the town of Komatipoort, in Mpumalanga Province, South Africa, approximately 96km (60miles), northwest of the city of Maputo, the capital of Mozambique. The coordinates of the power station are 25°27'42.0"S, 32°00'19.0"E (Latitude:-25.461667; Longitude:32.005278).

Overview

The power station is jointly owned by (a) Electricidade de Moçambique, the Mozambican electricity utility monopoly company and (b) Sasol New Energy, a 100 percent subsidiary of Sasol Limited, a South Africa-based chemical and energy conglomerate. The table below illustrates the shareholding in the power station, as of January 2021.[2]

Ressano Garcia Thermal Power Station Stock Ownership! Rank !! Name of Owner !! Percentage Ownership
1 Electricidade de Moçambique (EDM)
2 Sasol New Energy
Total

The power station uses natural gas, sourced from Mozambican gas fields, conveyed to the plant via the Temane–Secunda Gas Pipeline that transports the gas from Temane, in the Mozambican gas fields, to Secunda in South Africa.[2]

Construction

The engineering, procurement and construction (EPC) contract was awarded to Gigawatt Mozambique, SA, a subsidiary of South African-based Gigajoule Group, a company that develops, operates and invests in sustainable energy projects in Southern Africa.[3] [4]

The power station was designed to have maximum capacity of 350 megawatts. Since 2015, it has been gradually, progressively built and expanded to reach capacity of 175 megawatts. As of August 2020, US$280 million had been invested so far to that stage, including US$200 spent on construction.

Operation

The power station sells the energy it produces to the national utility company, Electricidade de Moçambique, under a 25-year power purchase agreement. The natural gas that the plant burns to produce the electricity, is supplied by Matola Gas Company, another subsidiary of the Gigajoule Group. The electricity supplies (a) the city of Maputo (b) Maputo Province and (c) some is sold to the Southern African Power Pool. Plans are underway to expand the power station to 350 megawatts.[4]

In December 2017, the power station was re-financed to the tune of US$189 million. The table below identifies the sources of funds for the refinance:[5] [6]

Ressano Garcia Thermal Power Station Refinance! Rank !! Lender !! Loan in US Dollars !! Percentage
1 55.0 million
2 Emerging Africa Infrastructure Fund21.0 million
3 21.0 million
4 42.0 million
5 50.0 million
Total 189.0 million

Change in ownership

In December 2020, Sasol Limited, the minority shareholder in this power station, signed binding paperwork, transferring its 49 percent shareholding to Azura Power Limited of Nigeria, for consideration of US$145 million. The transaction is subject to regulatory approval in Mozambique and is subordinate to first right of refusal (pre-emption rights) by the majority shareholder, EDM.[7] [8]

See also

External links

Notes and References

  1. Web site: Gigawatt Moçambique inaugurates power plant at Ressano Garcia . 22 February 2016 . Macauhub.com . 5 January 2021 . Macauhub.
  2. Web site: . Ressano Garcia Thermal Power Plant: A Loan To Support Power Generation In Mozambique . 7 September 2017 . Proparco . 5 January 2021 . Paris, France.
  3. Web site: Gigajoule Group . Gigajoule Group's Background . January 2021 . Gigajoule Group . 6 January 2021 . Centurion, South Africa.
  4. Web site: Our Power Plant . January 2021 . Gigajoule Group . Gigajoule Group . 6 January 2021 . Centurion, South Africa.
  5. Web site: January 2021 . Refinance of Ressano Garcia Thermal Power Station . Private Infrastructure Development Group (PIDG) . 6 January 2021 . PIDG . London, United Kingdom.
  6. Web site: 22 January 2018 . IFC Supports EDM and Sasol in Mozambique Power Project Financing . International Finance Corporation (IFC) . 6 January 2021 . IFC . Washington DC, United States.
  7. Web site: Club of Mozambique . Sasol to sell stake in Mozambique power plant to Azura Power . 21 December 2020 . Club of Mozambique . Maputo.
  8. Web site: Mozambique: Sasol Pulling Out of Ressano Garcia Power Station . 23 December 2020 . Mozambique Information Agency . 6 January 2021 . Maputo.