Line 7 (Mumbai Metro) Explained

Line 7 (Red Line)
Type:Rapid transit
System:Mumbai Metro
Status:Operational (extension under construction)
Locale:Mumbai, Maharashtra, India
Stations:14
Daily Ridership:212,000 (July 2023)[1]
Owner:MMRDA
Character:Elevated
Depot:Charkop (temporary)
Bhayandar (planned)
Stock:BEML
Linelength Km:16.5
Tracks:2
Linenumber:7
Electrification:25 kV 50 Hz AC overhead line
Map Name:Line 7 map
Map State:collapsed

Line 7 (Red Line) of the Mumbai Metro is a rapid transit metro line in the city of Mumbai, Maharashtra, India. When completed, the 30.08km (18.69miles) line will connect Bhayander with the Chhatrapati Shivaji Maharaj International Airport with 24 stations. The line is mostly elevated except for the 2.49km (01.55miles) underground twin tunnels at its southern terminus.

A section of the line from Dahisar East to Aarey was opened on 2 April 2022, and another section from Aarey to Gundavli in Andheri (East) was inaugurated on 19 January 2023. An under construction 11.386 km section of Line 7, from Bhayander to Dahisar, is part of Red Line 9. A southward extension to the airport is also currently under construction.

The line is served by six-car trains, manufactured by Bharat Earth Movers Limited, with a headway of 10 minutes. Line 7 currently uses Line 2's depot at Charkop, due to an issue acquiring land for a depot. Services currently operate between Gundavali and (on Line 2) via Dahisar East.

Planning

An metro line connecting Andheri East and Dahisar East was proposed as Line 7 in the original Mumbai Metro master plan unveiled by the Mumbai Metropolitan Region Development Authority (MMRDA) in 2004.[2] In June 2015, the MMRDA proposed building Line 7 as part of a plan to build 6 new metro lines at a total estimated cost of .[3] The MMRDA approved the detailed project report for Line 7 in August 2015. The report proposed a elevated line between Andheri East and Dahisar East at an estimated cost of .[4]

Over the course of two weeks in March–April 2017, Mumbai residents saved nearly 4,000 plants growing on dividers and along the Western Express Highway that had not been marked for replanting by metro authorities. Residents replanted these trees in their own housing societies, as well as at schools and other locations. Nearly 210 people and over 40 housing societies participated in the initiative coordinating their efforts through WhatsApp messages.[5]

In April 2017, the Ministry of Civil Aviation approved the transfer of 40 acres of land in Dahisar for the construction of the metro depot.[6] [7] The Airports Authority of India and the MMRDA signed a formal agreement on 24 April 2017.[8] In June 2017, the Maharashtra Government transferred three plots of land at Aarey Colony, measuring a total of 20,387 sqm (5.03 acres), to the MMRDA for a labour camp and a casting yard for Line 7, and a centralised operation centre for the metro system.[9] In November 2021, the MMRDA cancelled the plan to build the line's depot at Dahisar and instead proposed building the depot for Line 7, and its extensions, at Rai Murdhe in Bhayandar.[10]

In February 2020, MMRDA metropolitan commissioner R.A. Rajeev stated that Line 7 would be identified as the Red Line.[11] A study by World Resources Institute (WRI) India, published in May 2021, estimated that Line 7 and Line 2A had the potential to create 1.1 million jobs in the city.[12]

Extensions

See also: Line 9 (Mumbai Metro). In February 2017, the MMRDA announced that the DMRC was preparing a detailed project report (DPR) on a proposed extension of Line 7 from Dahisar to Bhayander, via Mira Road.[13] The extension would have 9 stations, with an inter-station distance of . The line would run parallel to the Surat-Dahisar Highway, then turn left at Kashi Mira Junction, before passing through Mira Road-Bhayander, and terminating at Golden Nest Circle in Bhayander. The project is estimated to cost .[14] [15] [16] In March 2017, the MMRDA stated that the DMRC was conducting a feasibility study to extend the line to Terminal 2 of the Chhatrapati Shivaji Maharaj International Airport.[17]

The extensions to Mira-Bhayander and the airport were officially announced by Chief Minister Fadnavis on 30 March 2017.[18] [19] [20] The alignment for the extension from Andheri to Chhatrapati Shivaji Maharaj International Terminus was approved by the State Cabinet on 12 April 2017.[21] In June 2018, the MMRDA stated that it had decided to terminate the proposed extension at the international airport and not extend it to the domestic terminal due to technical challenges. As the metro extension is proposed to be underground it would have to be constructed below or above Line 3 which also passes under the airport.[22] Line 7A is long including a underground twin tunnel.[23] The extension is partially elevated, running parallel to the Western Express Highway and Sahar Elevated Road, and goes underground just ahead of the vehicular underpass of Sahar Elevated Road.[24] The Maharashtra Cabinet approved the implementation of both extensions in September 2018.[25] [26]

History
SectionExtension dateTerminiLengthStations
Line 7[27] 2 April 202210.7km (06.6miles)10
19 January 20235.8km (03.6miles)4
Line 7AUnder Construction3.42km (02.13miles)2
Dahisar EastCSMIA International19.92km (12.38miles)16

Depot and Line 2 link

The depot for Line 7 was originally proposed to be located at Dahisar.[28] However, land acquisition for the Dahisar depot was delayed by litigation filed in 2016. In 2020, the MMRDA proposed using the depot at Charkop to serve both Line 2 and Line 7 by building a ring metro line to connect the two corridors. The MMRDA utilized an empty plot of land located after Ovaripada station on Line 7 to build pillars for the link connecting the two lines.[29] [30] Line 2 of the Mumbai Metro connects Dahisar East with Andheri West. In November 2021, the MMRDA cancelled the plan to build the depot at Dahisar and instead proposed building the depot for Lines 7, 7A and 9 at Rai Murdhe in Bhayandar.[31] The MMRDA received 59.63 hectares of land at Dongri from the state government in August 2023.[32]

Line 2 and Line 7 were both commissioned on 2 April 2022, with services operating between Aarey and via Dahisar East. Both lines were extended on 19 January 2023, providing circular service between Gundavali and via Dahisar East.[33] The Charkop depot currently serves as the depot for Line 2 and Line 7. The under construction Mandale depot will be used to serve Line 2 once completed.[34]

Construction

The bhoomipujan ceremony for Line 7 was performed by Prime Minister Narendra Modi during his visit to Mumbai on 11 October 2015.[35] Line 7 was implemented through the engineering, procurement and construction (EPC) model.[36] The MMRDA invited bids for the project in December 2015.[37] Tendering for the design and construction of the corridor was split into 3 packages. The first package included an elevated viaduct and 5 elevated stations – Andheri East, Shankarwadi, JVLR Junction, Mahanand and new Ashok Nagar. The second package included an elevated viaduct and 6 elevated stations – Aarey, Dindoshi, Pathan Wadi, Pushpa Park, Bandongri and Mahindra & Mahindra, and an elevated viaduct and 5 elevated stations – Magathane, Devipada, National Park, Ovaripada and Dahisar East. A total of 16 companies expressed interest, and 9 bids were submitted. In April 2016, the MMRDA awarded contracts to Simplex Infrastructure, J Kumar Infraprojects, and Nagarjuna Construction Company for the first, second and third packages respectively. The project is estimated to cost .[38] [39] The contract awarded to Simplex Infrastructure was worth .[40]

Construction work on the corridor began on 8 August 2016. The contractors were expected to complete construction of the corridor and all 14 stations within 30 months from the day of commencement of work.[41] On 18 February 2017, MMRDA officials stated that 15% of piling, pile caps and pier work on the corridor had been completed.[42] By the end of April 2017, 25% of piling work, 60% of barricading work and 77% of the soil testing for pier foundation had been completed.[43] Line 7 stations were built on a single pier, unlike the three piers used to support stations on Line 1. The single pier design was chosen to facilitate the construction of smaller stations and reduce the amount of land occupied on the Western Express Highway which could obstruct traffic flow.[44]

On 14 March 2017, the Mumbai High Court temporarily stayed all construction activities at Metro 7's casting yard in Bandra Reclamation. The Court was hearing a PIL filed by Mohammed Furqan Ali Mohammed Qureshi who alleged that the site of the casting yard had been reserved by the Brihanmumbai Municipal Corporation (BMC) for use as a Sunni Muslim cemetery.[45] [46] Piling work in Kandivli resulted in a gas pipeline bursting on 29 March 2017. The damage to the Mahanagar Gas pipeline resulted in temporary disruptions in the supply of CNG to Kandivli, Borivli, Dahisar, Mira Road and Bhayander.[47] [48] Mahanagar Gas began repairing the pipeline on the evening of 31 March, and completed the work by the following evening.[49] The BMC accused Nagarjuna Construction Company of illegally operating an unlicensed concrete ready mix plant at its casting yard in April 2017.[50]

The MMRDA announced that construction of viaducts would begin in April 2017. The agency had completed construction of piers on several sections of the corridor, and the viaducts will be built at locations where pier caps have been built. The first viaduct was constructed in the section between JVLR to Mahanand. Construction of all pier caps along the corridor will be completed by the end of 2017.[51] [52] The first U-girder, the concrete structure on which metro tracks are laid, was launched near Pathanwadi Junction in Malad on 2 May 2017.[53] In total, Metro 7 required 1,400 U-girders.[54] Work on erecting the U-girders, as well as disposal and dumping of muck generated from underground work was done only between 11:30 pm and 6:00 am. During this period, multi-axle trailers transported U-girders weighing 170 tonne from the casting yard in Bandra to the location where it is to be erected. The trailer had to move slowly to avoid causing imbalance to the heavy load which can result in toppling, and took roughly two hours to complete the journey. Lifting the girder and attaching it to the pier caps was also a difficult process and was carried out at night time. Traffic diversions were placed around the launching site to reduce the possibility of accidents. Officials erected an average of two girders every day.[55]

The MMRDA issued notices to all three contractors working on the project on 11 August 2017 over the "poor progress" of work. The agency stated that the although contractors were required to deploy 600 workers each, Simplex had only deployed 320, J Kumar Infraprojects had deployed 395, and NCC had deployed 318 labourers. The MMRDA had also issued a similar notice on 4 July 2017.[56] By August 2017, about 600-700 metres of each package had been constructed, 63 piers and 22 girders had been erected, and barricades had been placed on 67% of the entire route.[57] Track laying work on the line began in June 2019.[58] The first escalator on Line 7 was installed at Bandongri station in August 2019.[59]

In January 2020, the MMRDA terminated the contract awarded to Simplex Infrastructure for the first package over delay in completing the work. The next month, the agency invited bids to replace Simplex. The work was split into two tenders including one for a 6.25km viaduct and another to complete work on 4 stations. In July 2020, the MMRDA awarded a and contract to J Kumar Infraprojects and Nagarjuna Construction Company respectively to complete the work.[60] The MMRDA also encashed a bank guarantee of provided by Simplex.[61] Simplex had completed around 75% of work at the time its contract was terminated.[62]

MMRDA metropolitan commissioner R.A. Rajeev stated in September 2020 that almost 80% of construction work had been completed.[63] The MMRDA began conducting pre-trials on the rolling stock at the Charkop depot in February 2021.[64] The MMRDA announced that electrification of the line had been completed on 26 May, and the first trial runs were conducted from 31 May.[65] [66] The MMRDA began a dynamic test and trial run on the 20 km stretch between Dhanukarwadi and Aarey (including a portion of Line 2) on 19 June.[67] The stretch between Dhanukarwadi and Aarey received provisional approval from the Research Designs and Standards Organisation (RDSO) in January 2022.[68] The Commissioner of Metro Rail Safety (CMRS) began inspecting the line in February 2022.[69]

A section of Line 7 from Dahisar East to Aarey (along with the section of Line 2 from Dhanukarwadi to Dahisar East) was opened on 2 April 2022. Chief Minister Uddhav Thackeray flagged off the first train at 4pm in the presence of Deputy Chief Minister Ajit Pawar, Urban Development Minister Eknath Shinde, NCP chief Sharad Pawar and the Leader of Opposition in the Legislative Council, Pravin Darekar. The line opened for public service from 8pm, with services operating between Aarey and Dahanukarwadi (on Line 2) via Dahisar East.[70]

The remaining section of Line 7 from Goregaon East to Gundavali received approval from the RDSO in October 2022.[71] The CMRS began inspecting the line in December 2022.[72] The final section of the line (along with the final section of Line 2A from Dhanukarwadi to Andheri West) was inaugurated on 19 January 2023 by Prime Minister Narendra Modi.[73] [74]

Line 7A

Line 7A is a southward extension of Line 7 to Chhatrapati Shivaji Maharaj International Airport, with 2 stations. The section includes a elevated stretch and long twin tunnels. The MMRDA awarded the construction contract to J. Kumar Infrastructure. Work on the extension began in March 2020.[75] Around 25% of the work on the airport extension was completed by November 2022.[76]

Tunneling work began on 1 September 2023.[77] The twin tunnels are located at depths ranging between 6 metres and 20 metres to ensure a smooth transition with the elevated section of the line.[78] Two tunnel boring machines (TBM) were utilized to build the tunnels. Tunneling work is expected to be completed by December 2024.

Current status for Line 7A

Sr. No. Name of WorkStatus for year 2021[79]
1 March 20211 May 20211 June 20212 August 202130 September 2021
1Survey Work100%
2Barricading board fixing15%27%30%
3Soil Investigation Works86%89%92%
4Utility Identification Works28%29%32%
5 Piling Works19%
Test Pile100%
6Working Pile22%
7Pile cap9%

Stations

Line 7 has 14 operational stations, with two more stations under construction.

Red Line 7
Station Name[80] OpeningConnectionsLayout
EnglishMarathi
1दहिसर पूर्व 2 April 2022 (Under Construction)
(Under Construction)
Elevated
2ओवरीपाडा 2 April 2022 None Elevated
3राष्ट्रीय उद्यान 2 April 2022 None Elevated
4देवीपाडा 2 April 2022 None Elevated
5मागाठाणे 2 April 2022 None Elevated
6पोईसर 2 April 2022 None Elevated
7आकुर्ली 2 April 2022 None Elevated
8कुरार 2 April 2022 None Elevated
9दिंडोशी 2 April 2022 None Elevated
10आरे 2 April 2022 None Elevated
11गोरेगाव पूर्व 19 January 2023 None Elevated
12जोगेश्वरी पूर्व 19 January 2023 (Under Construction) Elevated
13मोगरा 19 January 2023 None Elevated
14गुंदवली 19 January 2023 Elevated
15विमानतळ वसाहतUnder ConstructionNoneElevated
16छ. शि. म. आं. वि. ट-२Under Construction (Under Construction)
and (Proposed)
Underground

Cost

Line 7 is estimated to cost .[81] The Asian Development Bank (ADB) will provide 43-48% of the total project cost through a loan at an interest rate of 1.4%. The Government of Maharashtra is the guarantor for the loan. On 2 March 2019, the Union Ministry of Finance stated that it signed a $926 million loan agreement with the ADB to fund the construction of Line 2 and Line 7. This was the single largest infrastructure loan ever extended by the ADB. The funds will be used to procure 63 six-car trainsets and for signaling and safety systems on both corridors.[82]

The proposed extension of Line 7 from Dahisar to Bhayander (called Line 9) is estimated to cost, and the underground extension to the International Airport shall cost an additional .[83]

The MMRDA allotted to the DMRC to implement and commission rolling stock, signalling and telecommunication work for the Metro 2A and Metro 7 corridors on 26 November 2016.[84] [85] [86]

Infrastructure

Rolling stock

BEML was awarded a contract to supply 378 metro cars (63 trainsets) for Line 7 and Line 2 in November 2018.[87] An additional 126 metro cars (21 trainsets) were ordered from BEML to cater to metro extensions.[88] All trainsets were manufactured at BEML's Rail Coach Factory in Bangalore, Karnataka. The rakes are capable of driverless operation making them the first driverless metro trains to be made in India.[89] BEML began manufacturing the coaches on 29 July 2019,[90] built the first metro coach in 75 days and unveiled it in September 2019.[91] The first trainset arrived in Mumbai on 28 January 2021.[92]

Each trainset is made up of 6 coaches with a total passenger capacity of 1,660 and dense crush load capacity of 2,092. The trainset is 3.2 metres wide, made of stainless steel and each coach has 4 doors on each side. The rake employs a regenerative braking system.[93]

Signalling

Line 7 utilises the Alstom Urbalis 400 communications-based train control (CBTC) signalling system. Alstom was awarded a EUR90 million contract to supply the signalling and telecommunications systems for Mumbai Metro Line 2 and Line 7, as well as Pune Metro's Purple Line and Aqua Line in April 2019.[94] [95]

Power

Line 7 is electrified at 25 kV 50 Hz AC, with power provided via an overhead catenary. The MMRDA signed an agreement with Adani Electricity Mumbai Limited to supply electricity to Line 7 and Line 2A on 2 December 2022. Around 120 million units is required to power both lines.[96] [97] MMRDA plans to install solar panels on the roofs of 13 stations on Line 7 to generate 2,000 kW of power.[98]

Fare collection

A consortium of Indian company Datamatics and Italian company AEP Ticketing solutions S.R.L was awarded a contract to implement the automated fare collection system for Line 7 and Line 2 in February 2019.[99] [100] [101]

From 1 May 2023, a 25% discount on ticket fare was implemented for senior citizens (over 65 years), disabled persons, and students up to Class 12.[102]

Foot overbridges

The MMRDA plans to build 14 foot overbridges on Line 7 to enhance connectivity for commuters. The overbridges will be constructed in three phases.[103] The first foot overbridge at Gundavali station was completed on 29 November 2022.[104]

Notes and References

  1. Web site: Two Mumbai Metro lines report record single-day ridership of 2.14 lakh amid heavy rain . cnbctv18.com . 30 September 2023 . en . 20 July 2023.
  2. Web site: Mmrda – Projects – Mumbai Metro Rail Project . dead . https://web.archive.org/web/20120319164955/http://202.54.119.40/projects_metro_rail.htm . 19 March 2012 . 12 March 2014 . Mmrdamumbai.org.
  3. Web site: 2015-06-16 . Over 130 km of Metro lines to criss-cross city by 2020 . 2023-07-09 . The Indian Express . en.
  4. Web site: MMRDA sanctions Rs 35,400 cr for 118 km Mumbai metro network Andheri East and Dahisar East. Business Standard . 9 July 2023.
  5. News: Anthony . Hepzi . 5 April 2017 . Mumbaikars save 4,000 plants on WEH from Metro axe . en . The Hindu . 6 April 2017.
  6. News: 25 April 2017 . Aviation ministry nod for Metro car depot in Dahisar - Times of India . The Times of India . 3 May 2017.
  7. Web site: 24 April 2017 . Study of building height restrictions near Mumbai airport soon Latest News & Updates at Daily News & Analysis . 3 May 2017 . dna.
  8. Web site: 2017-04-23 . Airports authority to give land for Metro-7 car shed at Dahisar in Mumbai . 2023-07-10 . Hindustan Times . en.
  9. Web site: 2017-06-15 . Three plots at Mumbai’s Aarey Milk Colony allotted for Andheri East-Dahisar Metro-7 corridor . 2023-07-10 . Hindustan Times . en.
  10. Web site: 2021-11-18 . Mumbai: MMRDA changes location of 2 Metro depots . 2023-07-10 . The Indian Express . en.
  11. Web site: 2020-02-29 . Metro-2A will be Yellow line, 7 to be Red . 2023-07-09 . Hindustan Times . en.
  12. Web site: 2021-03-24 . Metro lines 2A, 7 have potential to create 1.1 million jobs: Study . 2023-07-09 . Hindustan Times . en.
  13. Web site: Bidding for Metro 10 line to start later this year Latest News & Updates at Daily News & Analysis. dna. 24 March 2017. 22 March 2017.
  14. News: Mira-Bhayander to be connected with Metro. The Times of India. 25 February 2017 . 25 February 2017.
  15. Web site: Plans to extend metro stations to Bhayander may be implemented soon. dna. 25 February 2017. 25 February 2017.
  16. Web site: Dahisar metro extension work to begin in December 2017. Asian Age. 25 February 2017. 25 February 2017.
  17. News: Metro VII may extend to domestic airport - Times of India. The Times of India. 22 March 2017 . 24 March 2017.
  18. Web site: Maharashtra government to extend Mumbai Metro corridors to Mira-Bhayandar Latest News & Updates at Daily News & Analysis. dna. 30 March 2017. 30 March 2017.
  19. Web site: Will extend Metro network to Mira-Bhayandar and airport: Maha CM Devendra Fadnavis. Hindustan Times. 30 March 2017. en. 30 March 2017.
  20. Web site: Metro to extend to Mira-Bhayander and airport: Chief Minister Devendra Fadnavis. The Indian Express. 30 March 2017. 30 March 2017.
  21. Web site: Naik. Yogesh. State clears extension of Metro 7 up to Terminal 2. Mumbai Mirror. 13 April 2017. 12 April 2017.
  22. Web site: 2018-07-10 . Mumbai Metro 7 will not be extended to domestic terminal . 2023-07-10 . Hindustan Times . en.
  23. Web site: 2023-09-05 . Tunneling work begins on Mumbai Metro’s Line 7A . 2023-11-03 . The Indian Express . en.
  24. Web site: 2023-09-05 . Mumbai Metro 7A: Twin Tunnel Stretch Construction Begins . 2023-11-03 . Mumbai Live . en.
  25. Web site: Maha Cabinet clears Metro 7-A, 9 lines . The Asian Age . 9 October 2018 . 12 September 2018.
  26. Web site: Mumbai To Get Two New Metro Lines . NDTV.com . 9 October 2018.
  27. Web site: Metro Line - 7 Mumbai Metropolitan Region Development Authority . 2023-11-03 . mmrda.maharashtra.gov.in.
  28. Web site: 2020-02-10 . Charkop Car Depot To Now House Metro 7 and 2-A . 2023-07-09 . Mumbai Live . en.
  29. Web site: Rao . Shashank . Obstacles in getting car shed at Dahisar gives birth to a semi-circular metro line . 2023-07-09 . Mumbai Mirror . en.
  30. Web site: 2020-09-04 . Work on Mumbai Metro lines 2A, 7 delayed, likely to start operation by Jan 2022 . 2023-07-09 . The Indian Express . en.
  31. Web site: 2021-11-18 . Mumbai: MMRDA changes location of 2 Metro depots . 2023-07-10 . The Indian Express . en.
  32. Web site: 2023-08-11 . Government transfers vital land for depots of two metro lines . 2023-11-04 . Hindustan Times . en.
  33. Web site: 2023-01-14 . PM Narendra Modi to inaugurate Mumbai Metro Lines 2A, 7 today: All you need to know . 2023-07-09 . The Indian Express . en.
  34. Web site: 2022-12-28 . Metro Line 2A to use Charkop depot till work on Line 2B & Mandale depot is completed . 2023-07-09 . The Indian Express . en.
  35. News: 5 January 2017 . MMRDA invites civil work bids for two Metro projects . The Times of India . live . 10 February 2017 . https://web.archive.org/web/20170212043828/http://timesofindia.indiatimes.com/city/mumbai/mmrda-invites-civil-work-bids-for-two-metro-projects/articleshow/56341075.cms . 12 February 2017.
  36. News: Mishra. Lalatendu. Work on Mumbai Metro 7 to start by September. The Hindu. 4 May 2016. 10 February 2017. en.
  37. News: 2015-12-16 . MMRDA invites bids for Andheri-Dahisar metro line . The Economic Times . 2023-07-10 . 0013-0389.
  38. Web site: www.ETRealty.com . Simplex Infra, JKumar, NCC to develop Mumbai's Metro-7 corridor - ET RealEstate . 2023-07-10 . ETRealty.com . en.
  39. News: Nandgaonkar . Satish . 18 April 2016 . MMRDA awards contracts for Andheri-Dahisar metro . en . The Hindu . 10 February 2017.
  40. Web site: 2020-02-29 . Days after MMRDA removes contractor: Three bidders in race for Metro line 7 construction . 2023-07-10 . The Indian Express . en.
  41. News: Metro VII work begins today, may hit WEH traffic | Mumbai News - Times of India. The Times of India. 7 August 2016 .
  42. News: Mishra. Lalatendu. Metro 7 contractors told to speed up work. The Hindu. 18 February 2017. 19 February 2017. en.
  43. Web site: Northbound WEH lanes to be shut at night. Asian Age. 3 May 2017. 3 May 2017.
  44. Web site: 2018-01-02 . Mumbai Metro-7 line to have 14 stations along Western Express Highway . 2023-07-10 . The Asian Age.
  45. Web site: Stay on metro casting yard at Bandra. Asian Age. 16 March 2017. 15 March 2017.
  46. Web site: Bombay High Court stalls Metro 7 work over burial ground Free Press Journal. Free Press Journal. 16 March 2017.
  47. Web site: Metro work damages gas pipeline, accident averted. The Indian Express. 30 March 2017. 30 March 2017.
  48. Web site: Pipeline bursts, gas supply to Mumbai's western suburbs hit. Hindustan Times. 30 March 2017. en. 29 March 2017.
  49. Web site: Mumbai: Repair of MGL gas pipeline puncture to begin today. dna. 4 April 2017. 31 March 2017.
  50. Web site: Dhupkar . Alka . 16 April 2017 . Ready mix concrete plant for Metro 7 is illegal: BMC . 2023-07-10 . Mumbai Mirror . en.
  51. Web site: Within 10 months, Metro 7 moves to second stage of construction. The Indian Express. 4 April 2017. 4 April 2017.
  52. News: Metro VII piers work to begin next week - Times of India. The Times of India. 6 April 2017 . 6 April 2017.
  53. Web site: In pics: CM puts Mumbai's Metro 7 on right track; western express highway opens after 5 hours. Hindustan Times. 3 May 2017. en. 3 May 2017.
  54. Web site: 7 May 2017 . Hoping to open Mumbai Metro 7 by 2019, Maharashtra to invite bids for coaches . 8 May 2017 . Hindustan Times . en.
  55. Web site: Metro takes up toughest task at night. The Indian Express. 5 July 2017. 25 June 2017.
  56. Web site: 2017-08-19 . MMRDA issues notices to Mumbai Metro 7 contractors for ‘poor progress’ . 2023-07-10 . Hindustan Times . en.
  57. Web site: 2017-08-18 . Western Express Highway: Barricades for Metro 7 construction to be removed by next monsoon . 2023-07-10 . The Indian Express . en.
  58. Web site: 2019-06-18 . Work on track: MMRDA starts laying rail lines for Metro 2A, 7 . 2023-07-09 . Hindustan Times . en.
  59. News: 2019-08-13 . First escalator of Metro 7 installed . en-IN . The Hindu . 2023-07-10 . 0971-751X.
  60. Web site: 2020-07-10 . Contractor expelled, MMRDA gives Metro-7 works at higher costs . 2023-07-10 . Hindustan Times . en.
  61. News: 2020-02-04 . MMRDA terminates contracts for Metro Line 2B over delays . en-IN . The Hindu . 2023-07-10 . 0971-751X.
  62. News: 2020-05-16 . Mumbai: Two new contractors appointed for balance civil works on Metro Line 7 . The Times of India . 2023-07-10 . 0971-8257.
  63. Web site: 2020-09-11 . Mumbai Metro 2A, 7 trials to start from Jan 14 . 2023-07-09 . The Indian Express . en.
  64. Web site: 2021-02-25 . MMRDA begins pre-trials for Mumbai’s Metro trains . 2023-07-09 . Hindustan Times . en.
  65. Web site: May 26, 2021 . MMRDA to conduct test run for two elevated Metro lines next week . 2023-07-09 . Mumbai Mirror . en . IANS.
  66. Web site: 2021-06-01 . Mumbai: Trial run for Metro Line 2A and 7 flagged off . 2023-07-10 . The Indian Express . en.
  67. Web site: 2021-06-20 . Mumbai: Dynamic trial run begins on Metro corridors 2A and 7 . 2023-07-09 . The Indian Express . en.
  68. Web site: 2022-01-29 . Mumbai: Metro corridors 2A, 7 get RDSO provisional certificate . 2023-07-09 . The Indian Express . en.
  69. Web site: 2022-02-20 . Mumbai: CMRS starts inspection of Phase 1 of Metro corridors 2A and 7 . 2023-07-09 . The Indian Express . en.
  70. Web site: 2022-04-03 . Mumbai: Phase 1 of Metro Line 2A and 7 opened for public . 2023-07-09 . The Indian Express . en.
  71. Web site: 2022-10-13 . Mumbai’s Metro Line 2A, 7 clear designs & standards testing . 2023-07-09 . The Indian Express . en.
  72. Web site: 2022-11-30 . Supervision of Mumbai Metro Lines 2A and 7 by Commission of Metro Rail Safety underway . 2023-07-09 . The Indian Express . en.
  73. News: 2023-01-19 . PM Narendra Modi inaugurates Mumbai Metro lines 2A and 7; what you need to know about the new routes . The Economic Times . 2023-07-09 . 0013-0389.
  74. Web site: Livemint . 2023-01-18 . PM Modi to inaugurate Mumbai Metro Rail Lines 2A and 7 on 19 January. 10 points . 2023-07-09 . mint . en.
  75. News: 5 March 2020 . Mumbai: Work on second underground Metro line 7A begins . . 15 May 2020.
  76. Web site: Mumbai: Here is latest update of more than dozen Metro projects in the city . 2023-07-10 . Free Press Journal . en.
  77. Web site: Mumbai Metro 7A Update: Tunnelling Work Begins For Line Connecting CSMIA And Gundavali . 2023-11-03 . Free Press Journal . en.
  78. Web site: 2023-09-05 . Mumbai Metro 7A: Twin Tunnel Stretch Construction Begins . 2023-11-03 . Mumbai Live . en.
  79. Web site: Mumbai Metropolitan Region Development Authority - Metro Line - 9. 2021-05-02. mmrda.maharashtra.gov.in.
  80. Web site: Line 7-Project Features-Stations . MMRDA . 2017-06-07.
  81. Web site: 2020-12-06 . MMRDA approves cost hike for two packages of Mumbai Metro-7, but says overall cost won’t be hit . 2023-07-10 . Hindustan Times . en.
  82. Web site: Asian Development Bank To Lend $926 Million For Mumbai Metro Rail Project . 14 March 2019 . NDTV.com.
  83. Web site: 12 April 2017 . State clears extension of Metro 7 up to Terminal 2 . 7 June 2017 . Mumbai Mirror.
  84. News: 26 November 2016 . Consultant for MTHL finalized . The Times of India . 26 November 2016.
  85. Web site: 26 November 2016 . Mumbai Trans-Harbour Link: MMRDA approves appointment of general consultants . 26 November 2016 . The Indian Express.
  86. Web site: 25 November 2016 . General consultant appointed for MTHL project . 26 November 2016 . dna.
  87. Web site: Shah . Narendra . 2018-11-23 . BEML bags Rs.3,015 Crore Contract for Mumbai Metro Corridor . 2023-07-09 . Metro Rail News . en-US.
  88. Web site: 2019-08-01 . Mumbai: Manufacturing of coaches commences for Metro Lines 2A, 2B and 7 . 2023-07-09 . Mid-day . en.
  89. Web site: BEML delivers first India-made driverless metro cars to Mumbai Metro . 2023-07-09 . domain-b.com.
  90. Web site: 2019-07-30 . BEML starts work on Mumbai metro cars . 2023-07-10 . Deccan Herald . en.
  91. Web site: 2019-09-08 . Mumbai Metro gets first ‘Make in India’ driverless metro cars with bi-cycle parking facility; details here . 2023-07-09 . Financialexpress . en.
  92. Web site: 2021-01-28 . Mumbai: 1st rake for Metro-2A arrives; CM to unveil it on Friday . 2023-07-09 . Hindustan Times . en.
  93. Web site: BEML bags Rs3,015-cr order for Mumbai Metro Corridor . 2023-07-09 . domain-b.com.
  94. Web site: 2019-04-01 . Alstom to provide state-of-the-art signalling system for Mumbai Metro and Pune Metro . 2023-07-09 . Financialexpress . en.
  95. Web site: Alstom bags Rs 700 crore contracts from Mumbai, Pune metros . Construction Week . 9 July 2023.
  96. Web site: 2022-12-02 . Adani to supply power for MMRDA’s two new metro lines . 2023-07-09 . Hindustan Times . en.
  97. Web site: Adani Electricity to power Mumbai Metro Lines 2A & 7 connecting Andheri to Dahisar . 2023-07-09 . Free Press Journal . en.
  98. Web site: 2023-05-04 . Metro stations on Lines 2A, 7, Charkop depot to soon have rooftop solar panels . 2023-11-03 . The Indian Express . en.
  99. Web site: Release . Press . Datamatics wins AFC System contract for Mumbai Metro Line 2A, 2B & 7 . www.datamatics.com . en.
  100. Web site: Mahale . Ajeet . MMRDA finalises firm for AFC on 3 Metro lines . The Hindu . 5 December 2022 . en-IN . 7 February 2019.
  101. News: Datamatics Wins Automated Fare Collection Contract for Mumbai Metro Line 2A, 2B and 7 . Business Standard India . 5 December 2022 . 8 February 2019. Press Trust of India .
  102. News: 2023-04-29 . Mumbai: 25% fare concession on Metro 2A and 7 for senior citizens, divyang persons and students from May 1 . The Economic Times . 2023-11-03 . 0013-0389.
  103. Web site: 2023-03-30 . Metro 7 to get 14 FOBs to facilitate commuters . 2023-11-03 . The Indian Express . en.
  104. Web site: Mumbai: MMRDA completes 58m-long FOB linking 2 metro lines in 15 days . 2023-11-03 . Free Press Journal . en.