The signalling system used on the railway network in Finland comprises color-light signals and fixed signs, used together with the Automatic Train Control system ATP-VR/RHK (an EBICAB 900 system better known as JKV, Finnish: junakulunvalvonta).
The main signal can have any of the following aspects:
If a main signal doesn't protect any switches or the speed restriction on a diverging route is the same as straight route, the signal doesn't need to show the Proceed 35 aspect and therefore the yellow bottom light may be absent. The two lamp version of the old system has the lights reversed, i.e. red at the top and green at the bottom.
The distant signal is located at least 1200m (3,900feet) before the main signal.It may also be located in the same post with a main signal, below it. In this combined arrangement, whenever the main signal shows a stop aspect, the distant signal doesn't show any aspect at all.
A distant signal can have any of the following aspects:
Note: Although the green light of the old system distant signal used in Helsinki area is named Expect Proceed aspect, the next main signal may in fact be showing the Proceed 35 aspect. Therefore, the driver has to act as if the signal aspect is indeed Expect 35.
A block signal can show any of the following three aspects:
Aspect | Meaning | ||
---|---|---|---|
Stop | The signal must not be passed. | ||
Proceed, expect stop | The signal may be passed. The next main or block signal is showing a Stop aspect. | ||
Proceed | The next main or block signal is showing a permitting aspect. The following two blocks are not occupied. |
Block signals are being replaced by combinations of main and distant signals, and no new block signals will be installed.
A dwarf signal is used for controlling shunting movements. It can have any of the following aspects:
Aspect | Meaning | ||
---|---|---|---|
Stop | The signal must not be passed. | ||
Proceed with caution | The signal may be passed, but the track may be occupied by cars or another train. | ||
Signal cancelled | The signal may only be passed by the unit that has a permission to do shunting or track work. |
A dwarf signal may also be placed in conjunction with a main signal. If the main signal shows any other aspect than Stop, the dwarf signal shows the Proceed with caution aspect.
Bridge signals are small signals used to display the orientation of a moveable bridge. They can have any of the following aspects:
Aspect | Meaning | ||
---|---|---|---|
Stop | The bridge is open and the signal must not be passed. | ||
Signal cancelled | The bridge is closed and the signal may be passed. | ||
Proceed | The bridge is closed and the signal may be passed. This signal is no longer used. |
Repeaters are sometimes used to repeat the aspect of the main signal in the Helsinki area in places where the main signal is not clearly visible.
Aspect | Meaning | |
---|---|---|
The main signal is showing the Stop aspect. | ||
The main signal is showing some Proceed aspect. The train can be moved to the main signal. |
The Helsinki Metro signals differ from those used by the railways.
Some aspects may be shown using a signal with only three lights, pictured on the right.
Aspect | Meaning | ||
---|---|---|---|
Stop | The signal must not be passed. Forced stopping magnet is active. | ||
Proceed | The signal may be passed with the maximum allowed speed. | ||
Proceed 35 | The signal may be passed. Speed limit after the signal is 35km/h. The train may enter a diverging track through a switch. | ||
Coupling | The signal may be passed, but the track may be occupied or is an ending track. Speed limit after the signal is 20km/h. | ||
Exception | Drive at driver's responsibility. Forced stopping magnet is active. Speed limit after the signal is 35km/h. |
Aspect | Meaning | ||
Expect other than Proceed | The next main signal is showing one of the aspects Stop, Proceed 35 or Coupling. | ||
Expect Proceed | The next main signal is showing the Proceed aspect. |