Location:Oranjestad, Aruba
Status:O
Construction Began:2020
Commissioned:June 2022
Owner:Water – En Energiebedrijf Aruba N.V.
Th Fuel Primary:diesel fuel
Ps Units Operational:6
Ps Electrical Capacity:102

The RECIP IV Power Station is a diesel fuel power station in Oranjestad, Aruba.

History

In December 2018, the contract to construct the power station was awarded to Wärtsilä.[1] The construction of the power station started in 2020.[2] The power station was then commissioned in June 2022.[3]

Technical specifications

The power station has six generating units with a total installed generation capacity of 102 MW.[3]

See also

Notes and References

  1. Web site: 21 December 2018. Wärtsilä Smart Power Generation plant to support Aruba's move to renewable energy. Wärtsilä. 20 December 2023.
  2. Web site: 2 October 2020. Overall emissions reduced with new 102 MW electrical plant. Croon Caribe. 20 December 2023.
  3. Web site: Energy Production History. WEB N.V.. 20 December 2023.