Qingyuan Pumped Storage Power Station
Coordinates:23.7364°N 112.8621°W
Country:China
Location:Qingyuan, Qingxin District, Guangdong Province
Status:O
Construction Began:2008
Opening:2015
Operator:China Southern Power Grid Company
Res Name:Qingyuan Upper
Res Capacity Total:11798000m2
Lower Res Name:Qingyuan Lower
Lower Res Capacity Total:14953200m2
Plant Pumpgenerators:4 x 320 MW Francis pump turbines
Plant Hydraulic Head:502.7m (1,649.3feet)
Plant Capacity:1,280 MW

The Qingyuan Pumped Storage Power Station is a 1,280 MW pumped-storage hydroelectric power station about 20km (10miles) northwest of Qingyuan in Qingxin District, Guangdong Province, China. Construction on the project began in October 2008. The upper reservoir began impounding water in March 2013 and the first generator and all four generators were commissioned by 30 November 2015.[1]

The power station operates by shifting water between an upper and lower reservoir to generate electricity. The lower reservoir is located on Qin River and the upper reservoir is located in a valley above the west side of the lower reservoir. During periods of low energy demand, such as at night, water is pumped from Qingyuan Lower Reservoir up to the upper reservoir. When energy demand is high, the water is released back down to the lower reservoir but the pump turbines that pumped the water up now reverse mode and serve as generators to produce electricity. The process is repeated as necessary and the plant serves as a peaking power plant. It is operated by China Southern Power Grid Company.[2] At full load, it can last 9.1 hours of power generation.

Reservoir

The lower reservoir is created by a 75.9m (249feet) tall and 279m (915feet) long rock-fill dam on the Pan Wen River. It can withhold up to 14953200m2 of water, of which 10580800m2 can be pumped to the upper reservoir. The upper reservoir is created by a 54m (177feet) tall and 214m (702feet) long rock-fill dam. It can withhold up to 11798000m2 of water, of which 10544600m2 can be used for power production. Water from the upper reservoir is sent to the underground power station down near the lower reservoir through a 1753m (5,751feet) long headrace/penstock pipe. The power station contains four 320 MW Francis pump turbines. The difference in elevation between the upper and lower reservoir affords a hydraulic head (water drop) of 502.70NaN0.[3]

Accidents

Six workers were killed while excavating a tunnel on 19 November 2012.[4]

See also

Notes and References

  1. News: Qingyuan Pumped Storage Power Plant put into operation. 16 February 2016. GD China News. 30 November 2015. zh.
  2. Web site: Qingyuan Pumped Storage Power Station . Guangdong Hydropower Planning & Design Institute . 19 December 2013 . 23 July 2014.
  3. Web site: Qingyuan Pumped Storage Power Station General layout . Guangdong Provincial Electric Power Survey and Design Institute of Water Conservancy . 23 July 2014 . zh.
  4. Web site: Guangdong Qingyuan Pumped Storage Power Station accident occurred six deaths . Caixin . 20 November 2012 . 23 July 2014 . zh.