The Qingshui Geothermal Power Plant is a geothermal power plant in Datong Township, Yilan County, Taiwan.

History

In 2017, Fabulous Power Co. won the right to use the land where the plant stands today.[1] The construction of the power plant was completed in September 2021 and was approved to be commissioned on 27 October the same year.[2] It was then commissioned on 23 November 2021.[3]

Technical specifications

The power plant has an installed generation capacity of 4.2 MW. The temperature of the geothermal reservoir is around 180°C with a depth of 1,200–2,100 meters. It has an hourly power generation capacity of 3,150 kWh.[4]

Finance

The power plant was constructed with a cost of NT$765 million. Yiyuan, the company that invested into the power plant, was granted the permit to operate the power purchase agreement for 20 years, in which it will pay the government NT$2 million annually.[2]

See also

Notes and References

  1. News: Oung. Angelica. 22 September 2021. Geothermal plant in Yilan to come online this month. Taipei Times. 1 November 2021.
  2. News: Huang. Tzu-li. 16 November 2021. Taiwan to see its first geothermal power plant in 3 decades. Taiwan News. 25 November 2021.
  3. Web site: Richter. Alexander. 16 November 2021. Start of new 4.2 MW geothermal plant in Taiwan set for Nov. 23, 2021. Think Geoenergy. 17 November 2021.
  4. Web site: Richter. Alexander. 22 September 2021. Start of 4.2 MW Quingshui geothermal plant imminent in Taiwan. Think Geoenergy. 1 November 2021.