Pingshan II Power Station | |
Coordinates: | 33.8336°N 116.8308°W |
Location Map Caption: | Location of Pingshan Power station in China |
Country: | China |
Location: | Huaibei city, Anhui province, China |
Status: | O |
Construction Began: | November 2013 phase 1, April 2018 phase 2 |
Commissioned: | Phase 1 unit 1: December 2015, unit 2: March 2016 |
Cost: | $940, 000, 000 |
Owner: | Huaibei Shenergy Power Company (40%), Huaibei Mining Company (40%), Anhui Energy Group (20%) |
Operator: | As Owner |
Th Fuel Primary: | Coal |
Ps Units Operational: | 2 x 660 MWe 1 x 1,350 MWe |
Ps Electrical Capacity: | 2,670 MWe |
The Pingshan power station is a large modern coal-fired power station in China. The power station is divided into two phases with phase one consisting of two 660 MW units both with scrubbing systems and cooling towers. [1] Phase two has one ultra-supercritical secondary reheat unit with a 1350 MW capacity. This unit is one of the single largest coal units in the world, it also has the worlds largest cooling tower with a height of 210 m (689 ft).[2]
The engineering and design works for the power station were completed by East China Institute of Energy. The Phase 2 unit has coal consumption rate of 251g/kWh.[3]