Pickering Nuclear Generating Station Explained

Pickering Nuclear Generating Station
Coordinates:43.8117°N -79.0658°W
Country:Canada
Location:Pickering, Durham Region, Ontario
Status:O
Construction Began:Unit 1: June 1, 1966
Unit 2: September 1, 1966
Unit 3: December 1, 1967
Unit 4: May 1, 1968
Unit 5: November 1, 1974
Unit 6: October 1, 1975
Unit 7: March 1, 1976
Unit 8: September 1, 1976
Commissioned:Unit 1: July 29, 1971
Unit 2: December 30, 1971
Unit 3: June 1, 1972
Unit 4 June 17, 1973
Unit 5: May 10, 1983
Unit 6: February 1, 1984
Unit 7: January 1, 1985
Unit 8: February 28, 1986[1]
Decommissioned:28 May 2007 (A2)
31 Oct 2008 (A3)
Cost:$716 million CAD (A station)
$3.84 billion CAD (B station)
Owner:Ontario Power Generation (OPG)
Operator:Ontario Power Generation (OPG)
Employees:3000+
Np Reactor Type:CANDU-500
Np Reactor Supplier:AECL
Ps Cooling Source:Lake Ontario
Ps Units Operational:2 × 515 MWe (NET A 1–4)
2 × 516 MWe (NET B 6–8)
1 × 522 MWe (NET B 7)
1 x 530 MWe (NET B 5)
Ps Units Manu Model:2 × CANDU 500A
4 × CANDU 500B
Ps Units Decommissioned:2 × 515 MW
Ps Thermal Capacity:6 × 1744 MWth
Ps Electrical Capacity:3114
Ps Electrical Cap Fac:73.85% (lifetime)
87.07% (2019)
Ps Annual Generation:23,600 GW·h (2019) [2]
972,252 GW·h (lifetime)
Website:Pickering Nuclear

Pickering Nuclear Generating Station is a Canadian nuclear power station located on the north shore of Lake Ontario in Pickering, Ontario. It is one of the oldest nuclear power stations in the world and Canada's third-largest, with eight CANDU reactors. Since 2003, two of these units have been defuelled and deactivated. The remaining six produce about 16% of Ontario's power and employ 3,000 workers.[3]

A single 1.8 MWe wind turbine, named the OPG 7 commemorative turbine, was installed on the site of the generating station until October 2019, when it was dismantled.[4]

Reactor codification

The reactors can be classified as follows:

PICKERING A

PICKERING B

Construction

The site was once Squires Beach located west of Duffins Creek. The facility was constructed in stages between 1965 and 1986[5] by the provincial Crown corporation, Ontario Hydro, with significant completion of Station A scheduled for 1971.[6] In April 1999, Ontario Hydro was split into five component Crown corporations with Ontario Power Generation (OPG) taking over all electricity generating stations.[7] OPG continues to operate the Pickering station.[8]

Operation

The Pickering station is a large multi-unit nuclear facility, comprising six operating CANDU nuclear reactors with a total output of 3,114 MW when all units are on line, and two non-operating units with a total output of 1,030 MW currently shut down in safe storage.[8] The facility is connected to the North American power grid via numerous 230 kV and 500 kV transmission lines.[9]

The facility was operated as two distinct stations, Pickering A (Units 1 to 4) and Pickering B (Units 5 to 8) until 2011.[10] While primarily administrative in nature, the division was not wholly artificial, as there are some distinct differences in design between the two groups of stations. (Example: The Pickering A units employ a moderator dump as a shutdown mechanism,[11] a feature not found in Pickering B, which instead uses what is called an over-poisoned reaction guaranteed shutdown.[12]) There are, however, a number of systems and structures in common between the two stations; the most notable of these is the shared vacuum building, a negative pressure containment system.[13] The operation of Pickering A and B was unified in 2010,[14] to reduce costs now that Pickering A Units 2 and 3 are shut down in safe storage.

Partial shutdown

On December 31, 1997 the four Pickering A reactors, along with the remaining three units at Bruce A, were shut down by Ontario Hydro for safety reasons[15] and placed in lay-up. Specific to Pickering A, four years earlier the AECB had required mandatory upgrades to the safe shutdown system be completed by the end of 1997,[16] which differed from that at the other three plants. Pickering A featured a moderator dump as its 2nd shutdown system,[17] and this was deemed too slow compared to the poison injection system that later plants used, including Pickering B. Ontario Hydro committed to the refit and restart project, but it underwent long delays and large cost over-runs.

Safety System Refit

Often called a refurbishment, the return to service of Pickering A units 1 and 4 did not involve refurbishing the reactor cores, which involves replacing the calandria tubes, pressure tubes, feeders and end fittings. The main scope of work was the upgrading of the secondary safe shutdown system as well as some maintenance. Instead of retrofitting the poison injection found at the other plants, the least cost option was to add more shutdown rods and then split them into separate, independent groups. This was deemed sufficient by the AECB, despite acknowledging that this does not in fact constitute a fully independent fast acting secondary safe shutdown system.[18]

Return to service

Premier Mike Harris asked former federal energy Minister Jake Epp to study and make recommendations on the problems with the Pickering restart. The review panel was established in May 2003.

Unit 4 was refitted and then restarted in Sept. 2003. The election of the Ontario Liberal Party in October 2003 delayed action on the Epp report. In late 2003, the new government fired the top three executives of OPG for botching the Unit 4 restoration, which was years late and millions of dollars over budget.[19]

Mr. Epp and the Pickering A Review Panel released their report in December 2003,[20] which acknowledged the large cost over-runs and delays, attributing blame to bad management. The Epp Review estimated the cost of restarting the remaining three reactors at $3 – 4 billion and supported the continuation of the project.

The government of Dalton McGuinty appointed Epp to the Ontario Power Generation Review headed by John Manley to examine the future role of Ontario Power Generation (OPG) in the province's electricity market, examine its corporate and management structure, and decide whether the public utility should proceed with refurbishing three more nuclear reactors at the Pickering nuclear power plant. The report recommended proceeding with the restart of Pickering “A” reactors 1, 2, and 3, sequentially. The report argued that the restart of units 2 and 3 would be contingent on whether “OPG will be able to succeed at the Unit 1 project."[21]

The McGuinty government accepted the OPG Review Committee's recommendation and allowed the refit and restart of reactor 1.

The anti-nuclear group Sierra Club of Canada criticized the 2004 OPG Review Committee report for not attributing any blame to the problems of nuclear technology, noting that there were no energy or environmental experts appointed to the panel.[22]

Numerous changes in executive-level staff and project management strategy were made for the follow-on project to refit Unit 1. The experience with the return to service of Pickering A Unit 1 was significantly different from Unit 4, with a much tighter adherence to schedule and budget.[23] In August 2005, the OPG Board of Directors announced that Units 2 and 3 would not be returned to service due to specific technical and cost risks surrounding the material condition of these two units. Unit 1 was returned to service in November 2005.[24]

Electrical Output

The graph represents the annual electricity generation at the site (A and B combined) in GWh.ImageSize = width:621 height:430PlotArea = left:45 right:5 top:25 bottom:30TimeAxis = orientation:vertical AlignBars = lateColors = id:linegrey2 value:gray(0.9) id:linegrey value:gray(0.7) id:cobar value:rgb(0.2,0.7,0.8) id:cobar2 value:rgb(0.6,0.9,0.6)DateFormat = yyyyPeriod = from:0 till:25000ScaleMajor = unit:year increment:1000 start:0 gridcolor:linegreyScaleMinor = unit:year increment:500 start:0 gridcolor:linegrey2PlotData = color:cobar width:19 align:left bar:2001 from:0 till:13121 bar:2002 from:0 till:14490 bar:2003 from:0 till:13119 bar:2004 from:0 till:15813 bar:2005 from:0 till:17370 bar:2006 from:0 till:19919 bar:2007 from:0 till:17005 bar:2008 from:0 till:19248 bar:2009 from:0 till:20708 bar:2010 from:0 till:19217 bar:2011 from:0 till:19629 bar:2012 from:0 till:20761 bar:2013 from:0 till:19734 bar:2014 from:0 till:20154 bar:2015 from:0 till:21297 bar:2016 from:0 till:20017 bar:2017 from:0 till:21510 bar:2018 from:0 till:20911 bar:2019 from:0 till:23657 bar:2020 from:0 till:20629 bar:2021 from:0 till:21165 bar:2022 from:0 till:21464 bar:2023 from:0 till:21543TextData= fontsize:S pos:(20,20) text: Pickering Nuclear Generating StationAs of the end of 2023, the total lifetime output of the facility was 972,252 GWh.

Costs

Construction Costs

Ontario Hydro estimated the construction cost for the four Pickering "A" units at $508 million in 1965. Actual cost was $716 million (in 1973 dollars).[25] Adjusted for inflation, the $508 million estimate in 1973 dollars is $698 million, a 2.6% overrun.

The 1974 estimated cost for the four Pickering "B" units was $1.585 billion. Final cost was $3.846 billion (1986 dollars).[26] Adjusted for inflation, the $1.585 billion estimate in 1986 dollars is $4.082 billion, putting Pickering B under budget.

Safety Refit Costs

According to Ontario's FAO, the cost for refitting and restarting the Pickering A units deviated significantly from projections.[27]
- Pickering Unit 4 was slated to cost $460 million and ultimately ended up costing $1.25 billion.
- Pickering Unit 1 was slated to cost $210 million and ultimately ended up costing $1.00 billion.

However, the figure presented by the FAO for Unit 1 doesn't align with that provided by Ontario Energy Minister, Dwight Duncan, who indicated that Pickering Unit 1 would cost $900 million, putting the completed project much closer to budget.[28] This is supported by OPG stating that the project was completed on time and on budget.[23]

Waste

The used nuclear fuel and some refurbishment waste generated by the plant sits on-site at the Pickering Waste Management Facility. All operational low and intermediate-level waste is transported to OPG's Western Waste Management Facility at the Bruce nuclear site near Kincardine, Ontario. OPG has proposed the construction and operation of a deep geologic repository for the long-term storage of low and intermediate level waste on lands adjacent to the Western Waste Management Facility.[29] The Nuclear Waste Management Organization is currently seeking a site for a potential repository for the used fuel from all Canadian nuclear reactors.

Records

On October 7, 1994, Pickering Unit 7 set the world record for continuous runtime at 894 days, a record that stood for 22 years. It was surpassed by Heysham 2 unit 8 in 2016, a facility located in the UK, owned by EDF.[30] This was subsequently surpassed by OPG's Darlington plant with Unit 1 running 1,106 consecutive days.[31]
- In 2019, Pickering set a site capacity factor record of 87.07%, producing 23.6TWh and putting it roughly on-par with the much newer Darlington and Bruce facilities.[2]

Future

In January 2016, the Province of Ontario approved plans to pursue continued operation of the Pickering Nuclear Generating Station to 2024.[32] The extension was intended to ensure sufficient base load electricity was available during refurbishment of the Darlington Nuclear Generating Station and the initial Bruce Nuclear refurbishments.[33] By 2016, OPG had begun planning for the end of commercial operations at the generating station, including the potential repurposing of the Pickering site location.[34]

OPG will begin the longer term decommissioning process if refurbishment is not pursued. The first step in the long-term decommissioning process is to layup the reactors and place them into safe storage. Pickering staff will have future employment opportunities placing the Pickering units in a safe storage state, at the Darlington refurbishment and operations, or at the potential new build at Darlington.

In September 2022, the Province of Ontario announced that it supported an extension of Pickering's operation from 2024 to 2026. Simultaneously, it announced that it had requested OPG to update feasiblity studies on the potential refurbishment of the four units of Pickering B. In its announcement, the Province stated that continued operation of the station would reduce carbon dioxide emissions by 2.1 megatonnes in 2026, as well as increasing the North American supply of cobalt-60, a medical isotope.[35] [36]

In August 2023, the OPG Board of Directors agreed with and authorized the submission of the feasibility assessment for the refurbishment of the Pickering B plant to the province as well as to proceed with preliminary planning and preparation activities for the project.[37] This feasibility report was given to the Minister of Energy in January 2024 but was not released to the public because it could harm the "economic or other interests of Ontario.”[38]

On January 30, 2024, the Minister of Energy, Todd Smith, announced that the Government of Ontario would be investing in the refurbishment of the four Pickering B reactors that date back to the early 1980s.[39] The refurbishment is expected to be complete by the mid 2030's and should extend the life of the plant by at least another 30 years.[40]

Incidents

A serious incident occurred on 1 August 1983. Pressure tube G16 in the Pickering A Unit 2 reactor developed a 2 metre long split. The reactor was safely shut down and the damage investigated. The cause was found to be the mis-location of annulus gas spacer springs which allowed the hot pressure tube to sag and touch the inside of the cold calandria tube leading to hydrogen enrichment of the cooler areas. This created a series of small cracks which linked up and caused the long rupture. There was some local fuel damage and the reactor was safely shut down by the operators with no increase in radioactive emissions. The eventual resolution was Large Scale Fuel Channel Replacement and all the pressure tubes were replaced in all Pickering A reactors. The new pressure tubes were supported by an improved design of the annulus gas spacer springs. Since then, careful monitoring of the location of the annulus gas spacer rings has been a significant part of routine reactor inspections.[41]

On December 10, 1994 there was a loss of coolant accident. It is said to be the most serious accident in Canadian history (June 2001) by The Standing Senate Committee on Energy, the Environment and Natural Resources. The Emergency Core Cooling System was used to prevent a meltdown.[42] [43]

In 1995 and 1996, the AECB noted many safety concerns with the plant, and the generating station was shut in 1997 after peer reviews describing poor safety practices at the plant became public. An Independent, Integrated Performance Assessment report noted that Pickering stations A and B were cited for breaking regulation 15 times and having 13 fires for the year. "Also of concern was the high failure rate of persons being tested for positions as nuclear operators. At Pickering A only 65% of those taking the test passed, while at Pickering B the rate was just 56%."[44]

On March 14, 2011, there was a leak of 73 cubic metres of demineralized water into Lake Ontario from a failed pump seal. There was negligible risk to the public according to the Canadian Nuclear Safety Commission.[45]

2020 nuclear incident alert

On January 12, 2020 at 7:24 a.m. ET, an emergency alert was issued via Alert Ready on all radio stations, television stations, television providers, and wireless networks in the province of Ontario, containing an advisory of an unspecified "incident" that had been reported and was being addressed at the plant. The alert stated that no immediate action was required for those within 10km (10miles) of the plant. Approximately 40 minutes later, OPG issued a statement via Twitter that the alert had been sent in error, and a second emergency alert was issued at around 9:10 a.m. with a similar message cancelling the previous alert.[46] [47]

Solicitor General Sylvia Jones stated that the alert was accidentally issued during a "routine training exercise" by Ontario's emergency operations centre. The incident prompted criticism from government officials, including MPP Peter Tabuns, Pickering mayor Dave Ryan, and Toronto mayor John Tory.[48]

The false alarm also prompted renewed interest in preparedness for actual nuclear accidents: OPG reported a surge in the sales of potassium iodide kits via its "Prepare to Be Safe" website between January 12 and 13, increasing from its monthly average of 100 to 200, to over 32,000. The website is applicable for those who live within 50km (30miles) of the plant; per Canadian Nuclear Safety Commission (CNSC) requirements, OPG is required to distribute these pills to all residences within 10km (10miles) of a nuclear facility.[49] [50] [51]

See also

External links

Notes and References

  1. Web site: Preliminary Decommissioning Plan - Pickering Generating Stations A & B . 2020-09-09 . 2020-03-12 . https://web.archive.org/web/20200312101837/https://www.opg.com/document/preliminary-decommissioning-plan-for-pickering-generating-stations-a-b-pdf/ . dead .
  2. Web site: Our story > Pickering Nuclear celebrates record-setting year . OPG . 2020-01-30 . 2021-11-29 . 2020-06-09 . https://web.archive.org/web/20200609153356/https://www.opg.com/story/pickering-nuclear-celebrates-record-setting-year/ . live .
  3. News: Shah . Maryam . 2013-06-22 . Future of Pickering nuclear plant a hot topic in Durham Region . live . https://web.archive.org/web/20160816081332/http://www.torontosun.com/2013/06/22/future-of-pickering-nuclear-plant-a-hot-topic-in-durham-region . 2016-08-16 . 2014-07-02 . Toronto Sun.
  4. Web site: 2019-09-27 . Removal of Pickering wind turbine – Sept. 30 to Nov. 8, 2019 . live . https://web.archive.org/web/20200609230136/https://www.opg.com/news/removal-of-pickering-wind-turbine/ . 2020-06-09 . 2021-11-29 . OPG .
  5. Web site: October 2008 . Better Never than Late: The Climate Fall-Out of Ontario's Nuclear Electricity Plan . Greenpeace Canada.
  6. News: 1967-04-05 . it seems like only yesterday this was a farmer's field . 5 . Canadian Champion (Milton, ON) . live . https://web.archive.org/web/20200321133843/http://news.milton.halinet.on.ca/2497804/page/5?q=text%3A%28Gordon%20AND%20McIntosh%29&docid=OOI.2497804 . 2020-03-21.
  7. Web site: 2017-03-09 . A look at the long, complicated history of Ontario hydro . live . https://web.archive.org/web/20201112001708/https://www.yorkregion.com/news-story/7165441-a-look-at-the-long-complicated-history-of-ontario-hydro/ . 2020-11-12 . 2020-05-13 . YorkRegion.com.
  8. Web site: Pickering Nuclear Generating Station . live . https://web.archive.org/web/20210423045528/https://www.opg.com/powering-ontario/our-generation/nuclear/pickering-nuclear-generation-station/ . 2021-04-23 . 2021-11-29 . OPG .
  9. Web site: 2016-06-30 . Pickering-Ajax-Whitby Sub-region Integrated Regional Resource Plan - Appendices . live . https://web.archive.org/web/20190224050150/https://www.hydroone.com/abouthydroone/CorporateInformation/regionalplans/gtaeast/Documents/2016-Pickering-Ajax-Whitby-IRRP-Appendices.pdf . 2019-02-24.
  10. News: Ontario government supports OPG proposal to operate Pickering nuclear station past planned 2024 closing. The Globe and Mail. 16 January 2020. McClearn. Matthew. Baum. Kathryn Blaze. 13 May 2020. 18 January 2020. https://web.archive.org/web/20200118024000/https://www.theglobeandmail.com/canada/article-ontario-government-supports-opg-proposal-to-operate-pickering-nuclear/. live.
  11. Web site: 2016-04-08 . The Use of Rod-Based Guaranteed Shutdown State in CANDU Reactors . live . https://web.archive.org/web/20211120190029/https://www.nuclearsafety.gc.ca/eng/resources/research/technical-papers-and-articles/2016/Use-of-rod-based-guaranteed-shutdown-state-in-candu-reactors.cfm . 2021-11-20 . 2021-11-29 . Canadian Nuclear Safety Commission .
  12. Web site: Urjan . R. . 2010 . Rod-Based Guaranteed Shutdown States (RBGSS) implementation at Pickering B (IAEA-TECDOC--1650) . live . https://web.archive.org/web/20200609065617/https://inis.iaea.org/search/search.aspx?orig_q=RN%3A41126193 . 2020-06-09 . 2021-11-29 . International Atomic Energy Agency (IAEA) .
  13. Web site: 3 February 2014 . Pickering Nuclear Generating Station . live . https://web.archive.org/web/20211118171601/https://www.nuclearsafety.gc.ca/eng/reactors/power-plants/nuclear-facilities/pickering-nuclear-generating-station/index.cfm . 2021-11-18 . 2021-11-29 . Canadian Nuclear Safety Commission .
  14. Web site: 2014-11-20 . EB-2013-0321 - Decision with Reasons . live . https://web.archive.org/web/20201216055835/https://www.oeb.ca/oeb/_Documents/Decisions/dec_reasons_OPG_20141120.pdf . 2020-12-16 . Ontario Energy Board.
  15. Web site: CBC News . July 7, 2004 . Ontario to spend nearly $1 billion to restart nuclear reactor .
  16. Web site: June 7, 2001 . Canada's Nuclear Reactors: How much safety is enough? .
  17. Web site: CANDU Fundamentals - Reactivity mechanisms .
  18. Web site: June 7, 2001 . Canada's Nuclear Reactors: How much safety is enough? .
  19. News: OPG cancels Pickering repairs. The Globe and Mail. 12 August 2005. Luciw. Roma. 13 May 2020. 9 June 2020. https://web.archive.org/web/20200609065623/https://www.theglobeandmail.com/report-on-business/opg-cancels-pickering-repairs/article1121297/. live.
  20. Web site: December 2003 . Report Of The Pickering "A" Review Panel . live . https://web.archive.org/web/20200609065624/https://collections.ola.org/mon/7000/10317476.pdf . 2020-06-09.
  21. J. . Manley . J. . Epp . P.C. . Godsoe . 2004-03-15 . Transforming Ontario's Power Generation Company . The Ontario Power Generation Review Committee . English . 47 . INIS.
  22. Web site: 2004-03-17 . Manley Expected to Support Pickering Nuclear Boondoggle . dead . https://web.archive.org/web/20040416153146/http://www.sierraclub.ca/national/media/item.shtml?x=603 . 16 April 2004 . Sierra Club of Canada .
  23. Web site: 2010-02-16 . OPG Moves to Planning Phase of Darlington Refurbishment . 2022-06-08 . Cision Canada . en.
  24. Web site: Ontario Supports Plan to Safely Continue Operating the Pickering Nuclear Generating Station . Government of Ontario . April 24, 2024 . September 29, 2022.
  25. Web site: A Journalist's guide to Nuclear Power . 3 May 2023 . inis.iaea.org.
  26. Web site: Appendix 2 - Ontario's Nuclear Generating Facilities: A History and Estimate of Unit Lifetimes and Refurbishment Costs . dead . https://web.archive.org/web/20170404155726/https://www.pembinafoundation.org/reports/appendix2.pdf . 4 April 2017 . 19 April 2022 . www.pembinafoundation.org.
  27. Web site: Fall 2017 . Nuclear Refurbishment - An Assessment of the Financial Risks of the Nuclear Refurbishment Plan . live . https://web.archive.org/web/20210126122018/https://www.fao-on.org/web/default/files/publications/Nuc%20Refurb%20nov%202017/Nuclear-Refurb-EN.pdf . 2021-01-26 . FAO - Financial Accountability Office of Ontario.
  28. Web site: 2004-07-26 . Ontario government gives thumbs up to Pickering A1 restart . live . https://web.archive.org/web/20200905081806/https://www.neimagazine.com/news/newsontario-government-gives-thumbs-up-to-pickering-a1-restart . 2020-09-05 . 2022-06-08 . Nuclear Engineering International.
  29. Web site: Deep Geologic Repository . 2011-04-11 . OPG.
  30. Web site: Larson . Aaron . 2016-09-21 . New Record: Nuclear Power Plant Online for 940 Continuous Days . live . https://web.archive.org/web/20211009103210/https://www.powermag.com/new-record-nuclear-power-plant-online-for-940-continuous-days/ . 2021-10-09 . 2021-11-29 . PowerMagazine.
  31. Web site: 2021-02-05 . Darlington's Unit 1 heads into planned outage after record-breaking run . live . https://web.archive.org/web/20220113234448/https://www.opg.com/story/darlingtons-unit-1-heads-into-planned-outage-after-record-breaking-run/ . 2022-01-13 . 2022-01-13 . OPG.
  32. Web site: 2016-01-11 . Ontario Moving Forward with Nuclear Refurbishment at Darlington and Pursuing Continued Operations at Pickering to 2024 . dead . https://web.archive.org/web/20160414164800/https://news.ontario.ca/mei/en/2016/01/ontario-moving-forward-with-nuclear-refurbishment-at-darlington-and-pursuing-continued-operations-at.html . 2016-04-14 . news.ontario.ca.
  33. Web site: Ontario's Long-Term Energy Plan . dead . https://web.archive.org/web/20160709050743/http://www.energy.gov.on.ca/en/ltep/ . 2016-07-09 . 2016-06-28 . Canada's Ministry of Energy.
  34. Web site: Repurposing Pickering . dead . https://web.archive.org/web/20160718222607/http://www.opg.com/generating-power/nuclear/stations/pickering-nuclear/repurposingpickering/Pages/RepurposingPickering.aspx . 2016-07-18 . Ontario Power Generation.
  35. Web site: Ontario Newsroom . 2023-05-02 . news.ontario.ca.
  36. Web site: Jones . Allison . 2022-09-29 . Ontario plans to extend life of Pickering nuclear plant, eyes refurbishment . live . https://web.archive.org/web/20230102080729/https://www.cbc.ca/news/canada/toronto/picking-nuclear-extension-ontario-1.6600102 . 2023-01-02 . 2023-05-01 . CBC News.
  37. Web site: 2023-08-11 . OPG REPORTS 2023 SECOND QUARTER FINANCIAL RESULTS . live . https://web.archive.org/web/20230820210626/https://www.opg.com/documents/2023-second-quarter-financial-results-pdf . 2023-08-20 . 2023-08-20 . OPG.
  38. Web site: McClearn . Matthew . January 21, 2024 . Ontario is about to decide whether to overhaul Canada's oldest nuclear power plant. Does it deserve a second life? . January 30, 2024 . Globe and Mail.
  39. Web site: Crawley . Mike . January 30, 2024 . Doug Ford government to announce plans to refurbish Pickering nuclear plant . CBC News.
  40. Web site: 2024-01-30 . Pickering nuclear plant expected to be fully refurbished by mid-2030s . CBC News.
  41. Web site: EXAMINATION OF THE PRESSURE TUBE RUPTURE AT PICKERING NGS 'A' UNIT 2, FUEL CHANNEL G16 . 2013-07-21 . 2013-10-05 . https://web.archive.org/web/20131005004826/http://www.oocities.org/uoit_psgp/pro/tr.pdf . live .
  42. http://www.cnp.ca/issues/nuc-threat-mediterranean.pdf "Nuclear Threat in the Eastern Mediterranean" David H. Martin, June 2000, Page 10 (or page 17 of 106)
  43. Web site: "Pickering A Shutdown and Rehabilitation: A Brief History" page 4 (or page 11 of 51) . 2019-02-03 . 2019-02-03 . https://web.archive.org/web/20190203090911/https://sencanada.ca/content/sen/Committee/371/pdf/interim-enrg-e.pdf . live .
  44. Web site: Government of Canada . Public Services and Procurement Canada . 2002-07-01 . Nuclear power systems : their safety / Lynne C. Myers.: YM32-1/83-14-1999-11E-PDF - Government of Canada Publications - Canada.ca . 2024-01-31 . publications.gc.ca.
  45. Web site: Pickering Nuclear plant reports water leak, CBC News, March 16 2011 . 2012-04-25 . 2012-04-30 . https://web.archive.org/web/20120430052837/http://www.cbc.ca/news/canada/toronto/story/2011/03/16/pickering-nuclear-leak.html . live .
  46. News: Ontario government apologizes for alert about Pickering nuclear plant incident sent 'in error'. 2020-01-12. CBC News. 2020-01-12. 2020-01-12. https://web.archive.org/web/20200112125921/https://www.cbc.ca/news/canada/toronto/pickering-nuclear-generating-station-1.5424115. live.
  47. Web site: Pickering Nuclear Generating Station emergency alert issued in error, OPG says. Global News. en. 2020-01-12. 2020-01-12. https://web.archive.org/web/20200112124740/https://globalnews.ca/news/6400665/pickering-nuclear-generating-station-emergency-alert/. live.
  48. News: Ontario Warned of a Nuclear 'Emergency,' Then Said Never Mind. Austen. Ian. 2020-01-12. The New York Times. 2020-01-12. en-US. 0362-4331. 2020-01-12. https://web.archive.org/web/20200112165021/https://www.nytimes.com/2020/01/12/world/canada/ontario-nuclear-pickering.html. live.
  49. News: Iodide pills protect you in a nuclear disaster. So, why didn't more people have them before the Pickering scare?. Toronto Star. 20 January 2020. en. 2020-01-21. 2020-01-20. https://web.archive.org/web/20200120234507/https://www.thestar.com/life/health_wellness/opinion/2020/01/20/why-doesnt-everyone-have-ki-pills.html. live.
  50. News: Orders for potassium iodide pills surge after false alarm at Pickering nuclear power plant. Toronto Star. 14 January 2020. en. 2020-01-21. 2020-01-15. https://web.archive.org/web/20200115180420/https://www.thestar.com/news/gta/2020/01/14/orders-for-potassium-iodide-pills-surge-after-false-alarm-at-pickering-nuclear-power-plant.html. live.
  51. News: Over 32,000 potassium iodide pills ordered in 2 days after Pickering nuclear power plant alert error. January 14, 2020. CBC News. January 20, 2020. January 16, 2020. https://web.archive.org/web/20200116135515/https://www.cbc.ca/news/canada/toronto/potassium-iodide-pills-nuclear-power-plant-pickering-1.5426044. live.