-31.949°N 115.855°WPerth City Link is an urban renewal and redevelopment project in Perth, Western Australia.

The projectbounded by the Mitchell Freeway, Wellington Street, the Horseshoe Bridge and Roe Street is on land that was once the Perth/City railway yard and dedicated railway property west of Perth railway station. The land was used by the railways and reserved for their use, from the 1880s until the late 1990s. At the time of early proposals, much of the space was no longer required by the railway.

The foundation project, involved sinking a small section of the Fremantle railway line, between the City and Northbridge and demolishing the old Wellington Street Bus Station. Underground rail, refurbishment and extension of Perth station and a new bus station, is allowing for redevelopment of the of surface land that has been reclaimed.[1] The rail works were completed in December 2013 and the Perth Busport opened in 2016.

Transport

Rail

The $360 million rail project was the first stage of the Perth City Link. The scope of works included:

Work commenced in 2010 with the project initially scheduled for completion in mid-2014. By early 2013 the project was running six months ahead of schedule.[2] [3]

Tunneling commenced on 31 January 2012, with Premier Colin Barnett, Transport Minister Troy Buswell, Lord Mayor Lisa Scaffidi and Senator Louise Pratt (representing Federal Infrastructure Minister Anthony Albanese) taking part in a ceremony in which several documents were placed in a time capsule and buried at the station, to be unearthed in 2031.[4]

After a six-day shutdown, trains began running through the new tunnel on 18 July 2013.[5]

The final part of the project, the pedestrian underpass, was officially opened on 19 December 2013, signaling the completion of the rail project, six months ahead of schedule.[6]

Bus

The $249 million Perth Busport was the second stage of the Perth City Link. It involved the demolition of the Wellington Street Bus Station, which opened in 1973, and the construction of Australia's first dynamic stand allocation underground bus station at the same location. It opened on 17 July 2016.[7]

Precincts

The Arena

Located at the western end of the site, this precinct centres around the Perth Arena.

King Square

In late January 2014 Leighton Properties started construction on the King Square precinct on the former Perth Entertainment Centre site. Four office buildings were constructed with Shell Australia, John Holland Group, P&N Bank and HBF as tenants.[8] [9] In May 2013, three of the buildings were sold to the Dexus Property Group.[10] The buildings (along with the precinct) were completed in December 2015 and tenanted by early 2016.[11]

Yagan Square

Yagan Square, named after the Aboriginal warrior Yagan, is a 1ha public space located between the arms of the Horseshoe Bridge.

Previous proposal

In 1967 the government invited private developers, three internationally based, and one domestic group to submit proposals to place the railway underground, releasing 52acres for redevelopment. Financing issues and community opposition saw the project abandoned.[12] In 1972 the government announced further plans to sink the railway,[13] however this never eventuated.

External links

Notes and References

  1. Web site: Perth City Link: Reconnecting the City. 2012-06-28. Metropolitan Redevelopment Authority.
  2. News: Peter . Kerr. City Link on time and budget. 2013-03-25 . . 10 April 2013.
  3. Web site: April 2013 works update. 2013-04-10. Perth City Link Rail Alliance . https://web.archive.org/web/20130508071309/http://www.pta.wa.gov.au/perthcitylink/Article/tabid/514/ArticleID/63/April-2013-works-update.aspx . live. 8 May 2013 .
  4. News: Work begins on $360m city link project. 2012-01-31 . PerthNow . 10 April 2013.
  5. http://www.abc.net.au/news/2013-07-18/train-services-back-to-normal/4827522 Perth and Fremantle train services return to normal after shutdown
  6. http://www.pta.wa.gov.au/perthcitylink/article/articleid/81/december-2013-works-update December 2013 works update
  7. Web site: Opening of Perth Busport and changes across the bus network. Transperth. 19 July 2016.
  8. http://kingssquare.com.au/commercial/ Experience a Different Side to the City
  9. http://www.propertyobserver.com.au/finding/commercial-investment/office/31630-shell-australia-expands-floor-space-in-perth-s-ks2.html Shell Australia expands floor space in Perth's KS2
  10. http://www.leightonproperties.com.au/news/kings-square-buildings-sold.html King Square Buildings Sold
  11. http://www.johnholland.com.au/who-we-are/latest-news/kings-square-1-now-complete/ Kings Square 1 now complete
  12. Public Transport Authority (March, 2010) Perth City Link Master Plan: Lowering the Fremantle Railway in Perth
  13. News: Thomas. Athol. 25 March 1972. Perth Transport Plan. The Canberra Times.