Parali Thermal Power Station | |
Country: | India |
Location: | Parali, Beed, Maharashtra |
Status: | O |
Operator: | Maharashtra State Power Generation Company (Mahagenco) |
Th Fuel Primary: | Coal |
Ps Units Operational: | 6 |
Ps Electrical Capacity: | 1380.00 MW |
Commissioned: | 1971 |
Coordinates: | 18.8688°N 76.5261°W |
Parali Thermal Power Plant is located at Parali Vaijnath in Beed district of Maharashtra. The power plant is one of the coal based power plants of Maharashtra State Power Generation Company (Mahagenco).[1]
Stage | Unit Number | Installed Capacity (MW) | Date of Commissioning | Status |
---|---|---|---|---|
Stage I | 1 | 30 | 1970 August | Abandoned |
Stage I | 2 | 30 | 1971 March | Abandoned. |
Stage II | 3 | 210 | 1979 April | Abandoned. |
Stage II | 4 | 210 | 1980 July | Abandoned. |
Stage II | 5 | 210 | 1981 January | Abandoned. |
Stage III | 6 | 250 | 2007 | Running. |
Stage III | 7 | 250 | 2010 | Running. |