Owen Falls Explained

Owen Falls
Location:Border of Buikwe District and Jinja District, Uganda
Coords:0.4436°N 33.1847°W
Watercourse:Nile River
Type:Cataract
Height:31 meters (102 feet)

The Owen Falls was a waterfall on the White Nile in Uganda near the city of Jinja. The falls, together with the nearby Ripon Falls, were submerged in 1954 with the completion of the Nalubaale Hydroelectric Power Station. The dam that houses the power station was originally named Owen Falls Dam, but was later renamed Nalubaale Dam and the name of the power station was also changed, from Owen Falls Power Station to Nalubaale Power Station.[1]

Location

The waterfalls were located approximately 4km (02miles), north (downstream), of the point where the river leaves Lake Victoria. This is the location of Nalubaale Dam, previously called Owen Falls Dam.[1] [2] The geographical location of the former Owen Falls are:00°26'37.0"N, 33°11'05.0"E (Latitude:0.443611; Longitude:33.184722).

The power station

See main article: Nalubaale Hydroelectric Power Station. The original Owen Falls Power Station consisted of a concrete gravity dam with a close coupled intake powerhouse unit. It controls the Lake Victoria outflows through a series of ten turbines and six sluices in the dam. When fully opened, the six sluices provide a spill capacity of about1,200 cubic metres per second (cumecs).[3]

At the time of its commissioning by Queen Elizabeth II, in 1954, the power station had two units of 15 megawatts each, for generation capacity of 30 megawatts. The table below illustrates how generation capacity was gradually increased until all ten units were operational in 1968. That year, generation capacity at the power station reached 150 megawatts.[3]

History of Upgrade of Owen Falls Dam 1954 Until 1996! Rank !! Year !! Active Units!! Unit Capacity !! Total Capacity !!Notes
1 1954 2 15 Megawatts 30 Megawatts
2 1955 4 15 60
3 1957 6 15 90
4 1958 7 15105
5 1959 8 15 120
6 1966 9 15 135
7 1968 10 15 150
8 1996 10 18 180
Total 10 18.00 180.00

Operations and upgrade

According to agreements between the Colonial British government and the government of Egypt, signed in 1929 and amended in 1949, the power station is operated through the Agreed Curve, so that the outflow from Lake Victoria remains the same as it wasbefore the construction of the dam; when the outflow from the lake was naturally controlled by the rocky barrier of mukkibi falls.[1] [3]

Due to neglect and lack of maintenance from 1971 until 1986, generation capacity at Owen Falls Dam deteriorated to 60 megawatts by 1986. This required repairs and rehabilitation, including the increase of each turbine's capacity from 15 megawatts to 18 megawatts, to meet demand. The power station's generation capacity reached 180 megawatts in 1996.[1] [3]

Extension

The feasibility of increasing the power generating capacity of the Nile River at this location, was studied at the end of the 1980s by Acres International, which today is part of Hatch Ltd of Canada. The new project is a second powerhouse located about 1km (01miles) northeast of the Nalubaale Power Station. A new canal was cut to bring water from Lake Victoria to the new powerhouse. Major construction was completed in 1999. The first power from two units out of the installed five units, came online in 2000. The fifth and final turbine was installed in 2007. Each turbine has a capacity of 40 megawatts. The new power station is called Kiira Hydroelectric Power Station.[4]

See also

External links

Notes and References

  1. Web site: . Know Uganda: The Owen Falls Dam at 58 . 7 March 2012 . Dalton Wanyera . 20 April 2020 . Kampala.
  2. Web site: Owen Falls: Waterfall in Uganda . . 20 April 2020 . ((The Editors of Encyclopedia Britannica)) . 20 April 2020.
  3. Web site: . Owen Falls Dam: Powering Uganda For Five Decades . 3 February 2012 . Ibrahim Kasita . 20 April 2020 . Kampala.
  4. Web site: 20 April 2020 . Kiira Power Station, Formerly Known As Owen Falls Extension . https://web.archive.org/web/20150523012001/http://www.uegcl.com/kiira-Power.html . dead . 23 May 2015 . . 15 July 2013 . Uganda Electricity Generation Company Limited . Kampala . Archived from the original on 23 May 2015.