Opuyo–Moroto High Voltage Power Line Explained

Opuyo–Moroto High Voltage Power Line
Coordinates:1.6775°N 33.6769°W
Direction:South to North
Start:Opuyo, Uganda
Through:Katakwi, Napak
Partners:Islamic Development Bank
Operator:Uganda Electricity Transmission Company Limited
Contractors:Nanjing Paji Steel Power Manufacturing Company Limited of China
Construction:2017
Est:June 2021
Current Type:AC
Length:160
Ac Voltage:132kV
Circuits No:2

The Opuyo–Moroto High Voltage Power Line is a high voltage electricity power line, connecting the high voltage substation at Opuyo, a southern suburb of the city of Soroti, in the Eastern Region to another high voltage substation at Moroto, in the Northern Region of Uganda.[1] The power line was energized in June 2021.[2]

Location

The 132 kilo Volt power line starts at the Uganda Electricity Transmission Company Limited (UETCL) 132kV substation at Opuyo, Soroti District, in Uganda's Eastern Region, approximately 7km (04miles), by road, south-east of Soroti, the largest urban center in the Teso sub-region. The power line travels in a general north-easterly direction to end at another 132kV substation, also owned by UETCL, located at Moroto City, in Moroto District, a total distance of about 160km (100miles). The road distance between Opuyo and Moroto is about 176km (109miles), but the power line is a little shorter, because it does not always follow the road.

Overview

The power line was developed as part of plans to improve grid power delivery and reliability to the districts that constitute the Karamoja sub-region. Using US$80 million, borrowed from the Islamic Development Bank, the government of Uganda funded the construction of this power line, including a new substation at Moroto. Grid electricity was introduced in Karamoja in 2013, but distribution remains sparse.[1]

Associated power lines

Each of the five districts in the Karamoja sub-region is expected to receive a feeder line off this power line, to bring grid electricity closer to the people who need it.[1] [3]

Project Engineering and work supervision

Supervision of works contract was awarded to Ghods Niroo Engineering Company .[1]

Construction

Nanjing Daji Steel Tower Manufacturing Company Limited of China, is the main contractor on this project. Construction began in July 2017[1] and was concluded in 2021, with commercial commissioning in June 2021.[2]

See also

External links

1.6775°N 33.6769°W

Notes and References

  1. Web site: Karamoja to Get High Voltage Power Line . 13 July 2013 . . 23 December 2018 . Edward Eninu . Kampala.
  2. Web site: Kampala Post . 2 August 2021 . In Figures: A Look at Uganda's Energy Sector - By Ruth Nankabirwa Sentamu . 3 August 2021.
  3. Web site: Uganda Electricity Transmission Company Limited: Projects Under Implementation . . Uganda Electricity Transmission Company Limited . 2017 . 23 December 2018.