Olkaria II Geothermal Power Station explained

Olkaria II Geothermal Power Station
Location Map Caption:Map of Kenya showing the location of Olkaria II Geothermal Power Station
Location:Olkaria, Nakuru County, Kenya
Coordinates:-0.8642°N 36.2994°W
Owner:KenGen
Status:O
Ps Units Operational:3 (@ 35MW)
Commissioned:2003 and 2010

The Olkaria II Geothermal Power Station also known as Olkaria II Geothermal Power Plant is a geothermal power plant in Kenya, with installed electric generating capacity of [1]

Location

The facility is located in the Olkaria area, adjacent to Hell's Gate National Park, on the eastern edge of the Eastern Rift Valley, approximately 113km (70miles), southeast of the city of Nakuru, where the county headquarters re located.[2] Olkaria lies approximately 122km (76miles), by road, northwest of Nairobi.[3] The coordinates of Olkaria are:0°51'49.0"S, 36°18'00.0"E (Latitude:-0.8636; Longitude:36.3000).

History

Olkaria II went on-stream in 2003 when Kenya Electricity Generating Company (KenGen) commissioned two 35 MW units manufactured and installed by Mitsubishi Heavy Industries (MHI). In 2010, a third unit of 35 MW capacity was installed, at a cost of approximately US$100 million, bringing the total capacity to 105 Megawatts.[4] The expansion was financed by (a) the European Investment Bank, which lent US$40.8 million (KSh303 billion), the International Development Association, which lent US$27.6 million (KSh2.2 billion), the French Development Agency, which lent US$20 million (KSh1.6 billion) and KenGen, which contributed the balance.[5] The Olkaria II power plant is one of six geothermal stations either planned or already operational in the Olkaria area in Nakuru County.[6]

Ownership

Olkaria II Power Station is owned by KenGen, a public company, whose stock is traded on the Nairobi Stock Exchange, and in which the government of Kenya maintains 70 percent shareholding, the remaining 30 percent being held by private individual and institutional investors.[6] [7]

See also

External links

Notes and References

  1. Web site: 28 September 2017 . 28 December 2010 . The Big List: 2010's Biggest Renewable Energy Projects: Geothermal . Renewable Energy World Network (REWN) . Nashua, NH, USA . REWN Editors.
  2. Web site: GFC . Distance between Nakuru, Nakuru County, Kenya and Olkaria, Nakuru County, Kenya . Globefeed.com (GFC) . 28 September 2017 . 28 September 2017.
  3. Web site: Globefeed.com (GFC) . GFC . Distance between Nairobi Central, Nairobi, Nairobi County, Kenya and Olkaria, Nakuru County, Kenya . 28 September 2017 . 28 September 2017.
  4. Web site: Kenya Electricity Generating Company: Olkaria II Expansion . Power Technology (PTech) . PTech . 2009 . 28 September 2017.
  5. Web site: 28 September 2017 . KenGen adds 35MW geothermal power at Olkaria II . 23 June 2010 . Alexander . Richter . Think GeoEnergy.
  6. Web site: 26 September 2017 . 27 September 2012 . . KenGen invites bids for 560MW geothermal plants.
  7. Web site: Victor . Juma . Nairobi . KenGen sells five per cent stake to South Africans for Sh2.3 billion . 23 February 2017 . 28 September 2017 . Business Daily Africa.