Old Dominion University maglev explained
Old Dominion University Maglev |
Color: | 202898 |
Color2: | 202898 |
Image Alt: | The Old Dominion University maglev train sitting on top of the metal track on a concrete elevated guideway |
Other Name: | ODU Maglev |
Type: | Maglev |
Status: | Demolished |
Locale: | Norfolk, Virginia |
Start: | Powhatan Avenue Residence Halls |
End: | Ted Constant Convocation Center Parking Garage |
Stations: | 3 (planned) |
Yearcommenced: | 2001 |
Planopen: | Around 2002 (not met) |
Close: | 2003 |
Owner: | Old Dominion University |
Character: | Fully elevated |
Stock: | 1 custom-built train |
Linelength Km: | 1 |
Linelength Mi: | 0.6 |
Tracks: | 1 |
Speed Mph: | 40 |
The Old Dominion University (ODU) maglev was a failed public transit maglev system for the campus, developed in 2001.[1] It was developed in partnership with the company American Maglev Technology (AMT) from Georgia and with funding coming from Dominion Virginia Power, Lockheed Martin, and the state.[2] The track spanned 1 kilometer (0.6 miles) from Powhatan Avenue to 46th Street in Norfolk, Virginia.[3] ODU claimed it would have been the first of its kind in America.[4] The guideway served as an important landmark for students.[5] The system has been completely torn down, with the only part remaining being a section of the concrete guideway that spans overtop Hampton Boulevard.[6]
History
Plans for the maglev were first announced in 1999, with it slated to begin groundbreaking in the spring of 2001. The maglev was given an initial budget of $14 million. A groundbreaking ceremony was held on August 2001[7] and by 2002, the concrete guideway and steel track had been completed.[8] The train was put on the track the same year. The vehicle was made from a modified railcar from a different system that had been decommissioned in Florida.[9]
Due to multiple technical issues that consumed the budget, the system was not open yet by 2003. AMT was also faced with lawsuits for not paying contractors working on the system, resulting in additional delays.[10] The vehicle failed to reach its proposed speed of 40 miles per hour, instead only roughly moving around 45 feet before coming to a stop[11] and it made bumping and rattling noises, in addition to vibrating.[12] ODU was granted another $2 million loan to continue development by the Federal Railroad Administration in 2003 due to these issues, although they estimated another $5 million would be needed to finish the stations. AMT departed from the contract around the same time. Due to these issues, it would be announced they would focus on researching maglev technology instead of aiming to get the system operational for public transport.[13]
In 2006, ODU reported that they had made improvements on the train and had successfully moved it from one end of the campus to another without major issues.[14] [15] In 2008, ODU announced a partnership with another company, MagneMotion Inc. from Massachusetts, to continue research and development of maglev technology using money from a federal Urban Maglev Program grant. The project would create a new vehicle but reuse the currently existing guideway. A 12 foot long bogie was successfully tested in 2009,[16] which led to plans to continue further development with MagneMotion using a new prototype vehicle built by the company.[17] Later on in 2010, a majority of the existing metal track except for a section near Powhatan Avenue was sold off for scrap money to continue research,[18] along with the demolition of what was built of one of the stations. It is unclear what happened to the original vehicle. A new 80 foot section of track was built on top of the concrete guideway to better interact with the prototype vehicle. A 2013 report on the MagneMotion vehicle published by the Federal Railroad Administration states that the prototype vehicle was successful but additional testing was needed to ensure its reliability for commercial usage.[19] This report also stated that MagneMotion was considering either using the rest of the track at ODU to finish testing or building a test facility in Devens, Massachusetts to complete the design.
After this phase, the guideway sat idle for many years with no further tests being seemingly being conducted. Students at Old Dominion University used it as a rain shelter and as a landmark in the meantime. It was eventually demolished in the summer of 2023, except for one segment that was kept over Hampton Boulevard.
Planned infrastructure
According to an ODU press report, the maglev system would have featured a singular train that ran in intervals of four minutes, with a planned top speed of 40 miles per hour and a capacity of 140. It would have been free of cost to ride and would have featured 3 stations - one at the residence halls, one at the 43rd street garage, and one at the convocation center parking garage. The train levitated around half an inch off of the track. The length of the track was 1 kilometer, or around 3,200 feet.
Criticism
The maglev system was criticized for remaining unfinished and for going through a high budget, with a couple sources calling it a $16 million flop and one calling it infamous. Old Dominion University students reportedly called it the "mag left" after it was reported the project would be left unfinished.[20] Students were also critical of it being demolished, wondering why they would build it if it was never used and sad that an ODU landmark was being taken down.
See also
External links
Notes and References
- Book: Bookman . Steve . Old Dominion University . Ritchie . Jessica . Arcadia Publishing . 2017 . 9781467127004 . Charleston, South Carolina . en-US.
- Web site: 2003-09-07 . ODU's $2 million to fix maglev . 2024-01-13 . The Washington Times . 2024-01-13 . https://web.archive.org/web/20240113022653/https://www.washingtontimes.com/news/2003/sep/7/20030907-105739-2867r/ . live .
- Web site: Bookman . Steve . 2017-10-26 . MAGLEV . 2024-01-12 . Old Dominion University History Wiki . en-US . 2024-01-13 . https://web.archive.org/web/20240113022654/https://sites.wp.odu.edu/oduwiki/2017/10/26/maglev/ . live .
- Web site: December 1999 . INNOVATIVE MAGLEV TRANSPORTATION SYSTEM -- FIRST OF ITS KIND IN THE COUNTRY -- TO BE BUILT ON OLD DOMINION CAMPUS . 2024-01-12 . Old Dominion University . en-us . 2022-10-10 . https://web.archive.org/web/20221010073416/https://www.odu.edu/news/news-archive/1999/12/INNOVATIVEMAGLEVT_8742 . live .
- Web site: Head . Leondra . 2023-06-06 . 'It's heartbreaking:' Demolition of failed maglev underway at ODU . 2024-01-13 . News 3 WTKR Norfolk . en . 2024-01-13 . https://web.archive.org/web/20240113022654/https://www.wtkr.com/news/its-heartbreaking-demolition-of-failed-maglev-underway-at-odu . live .
- Web site: Reese . Brian . 2023-05-10 . ODU's 'Maglev' in process of being removed . 2024-01-13 . WAVY.com . en-US . 2024-01-19 . https://web.archive.org/web/20240119084716/https://www.wavy.com/news/local-news/norfolk/odus-maglev-in-process-of-being-removed/ . live .
- Web site: August 2001 . GROUNDBREAKING FOR MAGLEV TRANSPORTATION SYSTEM TODAY . 2024-01-13 . Old Dominion University . en-us . 2022-10-10 . https://web.archive.org/web/20221010113445/https://www.odu.edu/news/news-archive/2001/08/GROUNDBREAKINGFORM_8862 . live .
- Web site: Patton . Zach . 2018-12-21 . Behind the Lens: A $16 Million Flop . 2024-01-13 . Governing . en . 2024-01-13 . https://web.archive.org/web/20240113022653/https://www.governing.com/archive/gov-maglev-train-old-dominion-university.html . live .
- Web site: Giusti . Michael . 2002-06-12 . Maglev train makes tracks to Va. . dead . https://web.archive.org/web/20110608160217/http://nl.newsbank.com/nl-search/we/Archives?p_product=NJ&p_theme=nj&p_action=search&p_maxdocs=200&p_topdoc=1&p_text_direct-0=0F420E16183164ED&p_field_direct-0=document_id&p_perpage=10&p_sort=YMD_date:D&s_trackval=GooglePM . 2011-06-08 . 2024-01-13 . The Daytona Beach News-Journal.
- "ODU's stop-and-start maglev project back on track ". Suffolk News-Herald. Vol. 75, no. 94. 2004-04-18. p. 13. Retrieved 2024-01-14.
- Web site: Witt . Will . 2022-11-15 . Twenty One Years Later, the Ghost of ODU's Monorail Remains . 2024-01-13 . Mace & Crown . 2024-01-13 . https://web.archive.org/web/20240113022654/https://maceandcrown.com/2924/news/twenty-one-years-later-the-ghost-of-odus-monorail-remains/ . live .
- Web site: Messina . Debbie . 2007-04-11 . Doesn't run in Fla. Stalled at ODU. Now maglev maven is in Georgia. . 2024-01-13 . The Virginian-Pilot . en-US . 2024-01-13 . https://web.archive.org/web/20240113022654/https://www.pilotonline.com/2007/04/11/doesnt-run-in-fla-stalled-at-odu-now-maglev-maven-is-in-georgia/ . live .
- Web site: Messina . Debbie . 2008-01-15 . ODU partners with Massachusetts company to test another maglev train . 2024-01-13 . The Virginian-Pilot . en-US . 2024-01-13 . https://web.archive.org/web/20240113022653/https://www.pilotonline.com/2008/01/15/odu-partners-with-massachusetts-company-to-test-another-maglev-train/ . live .
- Web site: November 2006 . MAGLEV PASSES NEW MILESTONE . 2024-01-13 . Old Dominion University . en-us . 2022-10-11 . https://web.archive.org/web/20221011072947/https://www.odu.edu/news/news-archive/2006/11/MAGLEVPASSESN_8766 . live .
- Web site: Debbie . Messina . 2006-08-14 . Trial run of ODU maglev gets it off the ground . 2024-01-13 . The Virginian-Pilot . en-US . 2024-01-13 . https://web.archive.org/web/20240113022653/https://www.pilotonline.com/2006/08/14/trial-run-of-odu-maglev-gets-it-off-the-ground/ . live .
- Web site: December 2009 . MAGLEV Passes Milestone TEST . 2024-01-13 . Old Dominion University . en-us . 2022-10-12 . https://web.archive.org/web/20221012001447/https://www.odu.edu/news/news-archive/2009/12/MAGLEVPassesM_19606 . live .
- Web site: Messina . Debbie . 2010-01-10 . ODU's stalled maglev gears up for next phase . 2024-01-13 . The Virginian-Pilot . en-US . 2024-01-13 . https://web.archive.org/web/20240113022653/https://www.pilotonline.com/2010/01/10/odus-stalled-maglev-gears-up-for-next-phase/ . live .
- Web site: Messina . Debbie . 2010-06-20 . ODU to sell unused material to keep maglev research on track . 2024-01-13 . The Virginian-Pilot . en-US . 2024-01-13 . https://web.archive.org/web/20240113022654/https://www.pilotonline.com/2010/06/20/odu-to-sell-unused-material-to-keep-maglev-research-on-track/ . live .
- Web site: Lanzilotti . Lisa . Alberts . Thomas . 2013 . MagneMotion Maglev Demonstration on ODU Guideway . 2024-01-13 . University of Washington . Federal Railroad Administration . 2024-01-13 . https://web.archive.org/web/20240113022654/https://faculty.washington.edu/jbs/itrans/ODU%20MM%20demo%20final%20report.pdf . live .
- Web site: Vogel . Mike . 2015-05-27 . Still hovering: Tony Morris pushes 'maglev' trains . 2024-01-15 . Florida Trend . 2024-01-14 . https://web.archive.org/web/20240114222129/https://www.floridatrend.com/article/18516/still-hovering-tony-morris-pushes-maglev-trains . live .