Nuclear Power Plants Authority (Egypt) Explained

NPPA: is an Egyptian public economic authority of a special nature, affiliated to the Ministry of Electricity and Renewable Energy

Establishment

NPPA was established pursuant to Law No. (13) of 1976, as amended by Law No. (210) of 2017, as a public economic authority of a special nature, affiliated to the Ministry of Electricity and Renewable Energy, and is the only authority competent to establish, operate and manage nuclear power plants in the Arab Republic of Egypt. The main headquarters of NPPA is located in Cairo. NPPA possesses national capabilities, including with respect to the scientific qualifications and accumulated expertise necessary for achieving the duties assigned to it  in relation to the management, operation and maintenance of nuclear power plants in the Arab Republic of Egypt (ARE).

Mission

NPPA is competent to carry out the following duties:

The Importance of The Egyptian Nuclear Program

Egypt was one of the first countries that became cognizant of the importance of using nuclear energy in electricity generation and sea water desalination  in the early fifties of the last century, so as to contribute to optimising the benefits of Egypt's primary energy and fresh water resources as follows:

El-Dabaa Nuclear Power Plant Project

The substantial efforts made by Egypt and its governments throughout many years in seeking to enter the nuclear field resulted in signaling  the commencement of the construction of the El-Dabaa NPP. It is planned to build four Russian VVER reactors with a capacity of 1200 MW each (AES-2006). It is worth mentioning that this reactor belongs to the category of pressurized water reactors (advanced third generation reactors GEN 3+), which are currently among the most advanced reactors in the world.

The project is currently being implemented at the El-Dabaa site which is located 150 km west of Alexandria on the Mediterranean coast, in the north of the Arab Republic of Egypt (ARE). Multiple contracts have been concluded between the NPPA and Rosatom as the main contractor for the project, including the Engineering, Procurement and Construction contract, Nuclear Fuel Supply contract, Operation Support and Maintenance contract, as well as the Spent Nuclear Fuel contract.

Stages of Implementation of the El-Dabaa NPP

First Stage

The preparatory stage began in December 2017 and lasted about two and a half years, aimed at preparing the site for the construction works.

It is worth noting that the El-Dabaa NPP project was chosen as one of the best 3 nuclear projects in terms of launching, on the sidelines of the eleventh edition of “Rosatom Expo 2019”, the largest nuclear conference and exhibition in the world which was held in Sochi. and marked the first time that a nuclear project in the Middle East was granted this award.

Second Stage

The construction stage, which is the current project stage and which commenced following the obtainment of the construction permit for unit 1 from the Egyptian Nuclear and Radiological Regulatory Authority (ENRRA).on 29 June 2022, and includes all works related to building, constructing, training NPPA personnel, and preparing to carry out operational tests.

Third Stage

This is the final stage after obtaining the pre-commissioning testing permit, and includes commissioning works and the commencement of  actual operation until the provisional take-over of the first unit and the issuance of the operating license.

The progress of the project implementation is contingent upon  the issuance of licenses, as their issuance confirms the compliance with all requirements related to the safety and security of the nuclear power plant.

Accordingly, NPPA is keen to obtain all required licenses and permits related to the site, the reactor design, the construction, commissioning testing and commercial operation.

Milestones

The Arab Republic of Egypt has undertaken many actions, procedures and activities to enhance and prepare its nuclear infrastructure to be able implement and operat NPP projects efficiently, safely and reliably. The following table shows the milestones achieved with respect the Egyptian nuclear program  in order to establish a NPP

1955Establishment of the Atomic Energy committee
1957Establishment of the Atomic Energy Authority
1957Egypt is a founding of the International Atomic Energy Agency (IAEA), and in laying the foundation upon which the IAEA mandate is established as well as supporting the peaceful uses of nuclear energy.
1958Establishment of the first research nuclear reactor, under the name of Experimental Research and Training Reactor (ETRR-1), which was supplied by the Soviet Union; and inaugurated in Anshas in 1958.
1963Establishment of the Nuclear Engineering Department at Alexandria University
1964Launching an international tender for the construction of a nuclear power plant with a capacity of 15 MW for electricity generation and seawater desalination in Sidi Kerir.
1966Issuance of a letter of intent to the first bidder.
1967The war of June 1967 and suspension of the project.
1974Launching a restricted tender among American companies to construct a nuclear power plant with a capacity of 600 MW in Sidi Kerir.
1976Establishment of the NPPA.
1976Establishment of the Supreme Council of Energy.
1977Establishment of the Nuclear Materials Authority.
1978Suspension of the project due to the accident of the Three Mile Island reactor in the USA.
1980Selection of the El-Dabaa site for the construction of the Egyptian NPP.
1981Ratification of the Nuclear Non-Proliferation Treaty by the Arab Republic of Egypt.
1981Issuance of the presidential decree allocating the El-Dabaa site for the establishment of the NPP project.
1981The Supreme Council of Energy approves the Egyptian nuclear program.
1981Establishing a fund to support alternative energy projects.
1983Invitation to an international tender for the construction of a NPP with a capacity of 1000 MW.
1986Suspension of the project following the Chernobyl accident in Ukraine.
1998Operation of the second Egyptian experimental reactor with a capacity of 22 MW at Anshas.
2006Initiating a national dialogue to study the use of nuclear power in electricity generation.
2006Restructuring  the Supreme Council of Energy chaired by the Prime Minister.
2007Announcing Egypt's strategic decision to build a number of reactors for electricity generation.
2007Establishment of the Supreme Council for the Peaceful Use of Nuclear Energy headed by the President of the Republic.
2009"Worley Parsons" chosen as a consultant for the project.
2010Preparing and submitting the documents related to licensing the El-Dabaa site for the construction of the first NPP  to ENRRA.
2010Promulgation of Law No. 7 of 2010 Regulating Nuclear and Radiological Activities.
2011Completion of the technical specifications and tender documents preparation.
2012Establishment of the ENRRA, which is affiliated to the Prime Minister and undertakes regulatory

and supervisory works for all activities related to the peaceful use of nuclear energy.

2015The Arab Republic of Egypt received three technical and financing offers from Russia, China and South Korea.

The Russian offer  was deemed to be the most suitable offer.

On November 19, 2015, an inter-governmental agreement was signed between the Government of the Arab Republic of Egypt, and the Government of the Russian Federation, .

2016/2017Negotiations with the Russian party for the construction and operation of a nuclear plant, the supply of fuel and the storage of spent fuel. The NPP consists of four VVER reactor units with a capacity of 1200 MW per unit.
December 2016The engineering, procurement and construction contract was signed (EPC Contract).
25 February 2017On February 25, 2017, as part of the efforts to promote public awareness and acceptance of the El-Dabaa Nuclear Power Plant project, a public ceremony was held as part of the project community dialogue in the presence of. Dr. Mohamed Shaker, Minister of Electricity and Renewable Energy and the Governor of Matrouh, with the participation of El-Dabaa residents and all local stakeholders.
December 2017The project contracts entered into force and the preparatory stage of the project commenced.
March 2019Issuance of the El-Dabaa Site Approval Permit (SAP) by ENRRA.
November 2019The IAEA team of experts completed the Integrated Nuclear Infrastructure Review mission to assist the Arab Republic of Egypt in assessing the status of nuclear infrastructure.
2019The Egyptian nuclear project was granted an award upon its recognition as one of the top 3 project launches.
2020Commencement of the docking facility for the purpose of delivering the equipment of the El-Dabaa NPP.
August 2021Commencement of manufacturing of long lead equipment, including the core catcher.
September 2021Commencement of the training of the Egyptian personnel with respect to the operation and maintenance works.
October 2021NPPA’s Project Team responsible for oversseing the implementation of the El-Dabaa NPP Project, was granted the Best Team Award and the project was awarded the first place in the Egypt Governmental Excellence Award in its second edition.
June 2021Obtainment of the construction permit for the first unit of the El-Dabaa NPP.
July 2021Pouring of the first concrete for the first unit of the El-Dabaa NPP.
October 2021Obtainment of the construction permit for the second unit of the El-Dabaa NPP.
November 2022Pouring of the first concrete for the second unit at the El-Dabaa NPP
March 2023The website of the Nuclear Power Plants Authority is among the best distinguished government websites in the Egypt Government Excellence Competition for the year 2023
May 2023Pouring of the first concrete for the third unit at the El-Dabaa NPP

Choosing Rosatom [1]

The Russian Federation is currently one of the largest exporters of nuclear reactors and currently has nuclear power plant projects under construction in Bangladesh, Belarus, Hungary, China, India and Turkey. Rosatom has also has accumulated experience in the field of nuclear power plant construction and operation, as it has supplied many nuclear power plants currently in operation, totaling to (96) reactors of various Russian models which operate efficiently in (14) countries.

Impact of the El-Dabaa Nuclear Power Plant Project

The implementation of the nuclear power project has many positive effects on the following:

The i construction, operation and maintenance of nuclear power plants will require thousands of highly skilled personnel at different professional levels, which will contribute to reducing the unemployment rate, in addition to the following key advantages

Achievements[2]

The El-Dabaa NPP project was chosen as one of the 3 best nuclear projects in terms of launch in the eleventh edition  of the largest nuclear conference and exhibition in the world «Rosatom Expo», which was held in Sochi, Russia. This award is the first of its kind to be awarded to a nuclear project located in the Middle East.

The award commemorates Egypt's efforts to agree the best technical specifications and conditions upon which the contracts were concluded with the Russian partner implementing the nuclear power plant project in El-Dabaa.

As part of the continuous outstanding achievements of the NPPA  under the leadership of its Board Chairman,

Prof. Dr. Amgad El-Wakeel, the El-Dabaa Nuclear Power Plant project team won the Government Excellence Award for the best  national team . The award was received by Eng. Mohamed Ramadan, Vice Board Chairman for Operation and Maintenance.[3]

See also

References

  1. Web site: Egypt and Russia to sign contract for Dabaa nuclear power station. 2020-11-20. Ahram Online. en.
  2. Web site: الضبعة أفضل ثاني مشروع نووي بمعرض "إكسبو" في روسيا. 2021-01-02. مصراوي.كوم.
  3. Web site: 'الضبعة' تفوز بجائزة 'روساتوم'.. ووزير الطاقة يشكر العاملين. 2021-01-02. جريدة الدستور. 14 May 2019 .