North–South MRT line explained

Box Width:width:12em;

North–South Line
Native Name:Laluan MRT Utara Selatan
Chinese: 南北地铁线
Tamil: வடக்கு தெற்கு எம்ஆர்டி வழி
Type:Rapid transit
System:Mass Rapid Transit (Singapore)
Status:Operational
Locale:Singapore
Start:Jurong East
End:Marina South Pier
Stations:29 (27 in operation, 2 under planning)
Routes:2
Daily Ridership:456,323 (July 2020)[1]
Open: (First section)
(Initial line complete)
(Woodlands extension)

Planopen:
Mid-2030s
Owner:Land Transport Authority
Operator:SMRT Trains (SMRT Corporation)
Character:Elevated (Jurong EastAng Mo Kio)
Ground-level (Bishan)
Underground (BraddellMarina South Pier)
Stock:Kawasaki Heavy Industries C151 (KHI)
Siemens C651 (SIE)
Kawasaki–Nippon Sharyo C751B (KNS)
Kawasaki–Sifang C151A (KSF)
Kawasaki–Sifang C151B (KSF)
Kawasaki–Sifang C151C (KSF)
Alstom Movia R151 (ALS)
Linelength:45km (28miles)
Tracks:2; 3 (Ang Mo Kio)
Speed:limit of 80km/h
Map State:hide
Depot:Bishan
Ulu Pandan
Map Name:Route diagram

The North–South Line (NSL) is a high-capacity Mass Rapid Transit (MRT) line in Singapore, operated by SMRT Corporation. Coloured red on the Singapore rail map, the line is 45km (28miles) long and serves 27 stations,[2] 11 of which, between the Bishan and Marina South Pier stations, are underground. It runs from Jurong East station, located in Western Singapore, to Marina South Pier station in the Central Area, via Woodlands station in northern Singapore. The line operates for almost 20 hours a day (from the first departure 5:07 am to approximately 1 am the next day), with headways of up to 1 to 2 minutes during peak hours and 5 to 8 minutes during off-peak hours. All the trains on the North–South Line run with a six-car formation.

It was the first MRT line to be built in Singapore, with the first section from Yio Chu Kang station to Toa Payoh station beginning service on 7 November 1987, followed by an extension southwards to Raffles Place station on 12 December the same year and northwards to Yishun station on 20 December 1988. After the southern extension to Marina Bay station opened on 4 November 1989, the North–South Line was formed and split from the East–West Line. In the 1990s, the line extended to the north and west connecting to the Branch line via Woodlands through the Woodlands line extension.

Since the 2010s, due to the ageing infrastructure of the North–South Line (being the oldest and heavily utilised MRT line), significant improvements have been made on this line, such as the replacement of sleepers, third rail replacement and the introduction of new rolling stocks (the C151B, C151C and R151) to replace the older rolling stocks and increase passenger capacity. The North–South Line is also the first line to have undergone a major re-signalling project, converting it from semi-automatic to fully automated operations in 2019. Other recent developments of the line include a new extension to Marina South Pier station on 23 November 2014 and a new infill station, Canberra station, on 2 November 2019. Two more infill stations (Brickland and Sungei Kadut stations) on the line are being planned and are set to be opened in the 2030s.

History

Initial developments

See main article: History of the Mass Rapid Transit (Singapore). The Mass Rapid Transit (MRT) originated from a forecast in 1967 by the planners of the State and City Planning Project,[3] which stated the need for a rail-based urban transport system in Singapore by 1992.[4] [5] [6] Following a debate on whether a bus-only system would be more cost-effective, then-Minister for Communications Ong Teng Cheong came to the conclusion that an all-bus system would be inadequate, as it would have to compete for road space in the land-scarce country.[7] [8]

After deciding on a rail-based system, the construction of Phase I of the MRT system,[9] which will be the North–South Line, was given priority as the line passes through areas having a higher demand for public transport, such as the densely populated housing estates of Toa Payoh and Ang Mo Kio and the Central Area. The line was expected to relieve the traffic congestion on the Thomson–Sembawang road corridor.[10] [11] Construction of the MRT line (and also the MRT system itself) started on 22 October 1983,[12] and the first section from Yio Chu Kang station to Toa Payoh station opened on 7 November 1987.[13] [14] At the inauguration ceremony, Ong Teng Cheong, who backed and commissioned the planning of the MRT system, attended the ceremony as a special Guest of Honour. Dr Yeo Ning Hong, the Minister For Communications and Information, inaugurated the start of MRT operations and announced it to be the "beginning" of the MRT system.[15]

Nine more stations from Novena station to Outram Park station via Raffles Place opened on 12 December that year.[16] The line was extended northward to Yishun station on 20 December 1988 as part of phase 2B[17] and it began independent operations on 4 November 1989 as the North–South Line when the extension to Marina Bay station was opened.[18] [19]

Woodlands extension

After the Branch line (from the Jurong East to Choa Chu Kang stations) opened in 1990, the Woodlands MRT line was envisioned so as to close the gap between Yishun and Choa Chu Kang stations.[20] [21] [22] Numerous changes were made to the number of stations for the extension mainly to accommodate the 1991 Concept Plan by the Urban Redevelopment Authority,[23] which aimed to make Woodlands a regional centre for northern Singapore.[24]

During the initial planning of the line, Sembawang station was only intended as a provisional station, to be built at a later date due to the underdevelopment of Sembawang, and construction began on 19 November 1992.[25] Sembawang station[26] and Kranji station[27] were later included in the construction after the second round of planning (construction began at the same time on 19 November 1992) and Sungei Kadut station was then omitted. Sungei Kadut will be built later if the town's population justifies the necessity for the station.[28]

During the construction, a total of 19 new trains were purchased for almost S$259 million for the new MRT line, designed by German company Siemens Aktiengesellschaft, to complement the 66 first-generation C151 trains. There was also a need to level the land covered in thick vegetation in Kadut, Woodlands and Sembawang for the MRT line.[29]

With the official opening of the Woodlands extension on 10 February 1996 by then Prime Minister Goh Chok Tong, the Branch line was incorporated into the North–South Line. The extension was built at a cost of $1.2 billion.[30]

Subsequent developments

See main article: Marina South Pier MRT station and Canberra MRT station. The NSL platforms of the Bishan station underwent major alterations to increase the passenger capacity of the station from 1,250 to 2,020. A new air-conditioned platform to serve southbound trains to Marina South Pier was constructed and opened for service on 27 July 2008, connected to Junction 8 via Exit E. The station was expanded to handle increased passenger traffic when the CCL station opens.[31] As the original platform, now serving northbound trains to Jurong East, remained in service, upgrading works for the platform (Platform A) was hindered and took about a year to complete. While the re-tiling of the platform was done during the day, the Platform Screen Doors (PSDs) were installed in sections through the night. An air-conditioning system was also installed as part of the upgrade. Upgrading works for the platform were fully completed on 23 May 2009.[32]

Under the Land Transport Master Plan 2008, the Jurong East Modification Project entailed the construction of a new platform and the addition of a fourth track to Jurong East station to reduce waiting times and crowding at the station during peak hours.[33] The modification project was completed on 27 May 2011.[34] The track and platform was initially opened during morning peak hours only, but since December 2011, they also operate during the evening peak hours.[35]

In the 2008 Land Transport Master Plan, the 11NaN1 North–South Line extension was announced as one of the upcoming projects rolled out by the Land Transport Authority to expand Singapore's rail network.[36] The one kilometre extension from Marina Bay to Marina South Pier station was opened on 23 November 2014.[37] [38] This extension serves the Marina South Pier, the Marina Bay Cruise Centre Singapore, and future developments in the Marina Bay Downtown area.[39]

On 17 January 2013, the Land Transport Authority (LTA) announced that a feasibility study was conducted to construct Canberra MRT station.[40] [41] The feasibility study was completed in 2014 and LTA announced Canberra as a new station.[42] Construction of Canberra station commenced on 26 March 2016.[43] The station, which is an infill station with side platforms, was built along an operational section of the line between Sembawang and Yishun. The station cost S$90 million to build,[44] and is meant to serve upcoming developments at the vicinity. Canberra station opened on 2 November 2019.[45]

Incidents

On 3 March 2003, a 23-year-old man lost control of his vehicle along Lentor Avenue, crashed through the fence, and landed on a stretch of track between Yio Chu Kang and Khatib stations. The incident forced a train carrying hundreds of commuters to come to a screeching halt, but not before flattening the front of the car. The accident disrupted train services for more than three hours and cost SMRT between S$100,000 and $150,000 in damages and lost revenue.[46]

On 15 December 2011, train services between Bishan and Marina Bay stations were disrupted due to damage sustained on the power rail between City Hall and Dhoby Ghaut. Trains along this stretch were stalled and caused a service disruption until 11:40pm on that day.[47] [48] Two days later, a similar problem caused a seven-hour disruption between Ang Mo Kio and Marina Bay.[49] [50] According to SMRT, the disruption was caused by damage to the third rail and the trains' collector shoes. Seven trains were damaged in this incident.[51] These two service disruptions on the North–South line were both related to damaged rail, and became one of the worst disruption since SMRT's inception in 1987.[52]

On 7 July 2015, train services on the North–South and East–West lines were temporarily disrupted due to massive power trips detected along both lines. A cause of the disruption was due to damaged insulators which caused a failure to properly supply power.[53] [54] [55] [56] For this disruption that brought inconvenience to 413,000 commuters, LTA imposed a 'record' fine of S$5.4 million on SMRT.[57]

On 7 October 2017, a 20-hour long disruption of services started due to flooding in the tunnels between Braddell station and Bishan station due to a faulty drainage system, resulting in disruption of train services between Ang Mo Kio and Marina South Pier stations in both directions for several hours. A trackside fire between Raffles Place and Marina Bay stations further exacerbated the disruption. Train services between Marina South Pier and Newton resumed at about 9:20pm on the same day, followed by Newton and Ang Mo Kio at around 2pm the following day.[58] Although no injuries or casualties were reported, SMRT fired a total of eight employees from the maintenance crew, and incurred a S$2 million fine, following the incident.[59]

On 14 October 2020, train services from Jurong East to Woodlands stations were disrupted for more than three and a half hours, owing to a faulty power cable, which affected the East–West Line and Circle Line too. The power fault began at 7pm and by 7:30pm, commuters were stuck in the trains. Free bus bridging services were activated at all affected stations, and bus operators increased the frequency of regular services serving these areas. Service resumed at all stations along the North–South and East–West Lines at 10:35pm.[60] A total of 36 stations were affected by the power fault.[61] The incident led to a replacement of 150km of power cables for the Tuas West Extension and two SMRT staff being suspended.

On 27 October 2023, trains skipped Novena MRT station for about 2 hours during the evening travel peak, after an air-conditioning unit filled the underground station with smoke. Free bus bridging services were provided between Newton MRT station and Toa Payoh MRT station, and ended shortly after the station was reopened at around 7.29pm. [62]

On 3 June 2024, around 5.50pm, a lightning strike caused traction power to trip, as well as a small fire breaking out in a power control box next to the train track located about 20 meters from the platform of Kranji MRT station. No injuries were reported. This resulted in train services to be suspended between Choa Chu Kang and Woodlands stations for more than two hours. According to the Singapore Civil Defence Force, the fire had burned itself out before its officers arrived. Train services were progressively restored at 8.10pm.[63]

Future plans

See main article: Brickland MRT station and Sungei Kadut MRT station.

In the Land Transport Master Plan 2040 (LTMP2040), two new infill stations are projected to be built along the existing North–South Line. Brickland station will be built between Bukit Gombak and Choa Chu Kang stations, while Sungei Kadut station will be built between Yew Tee and Kranji stations and provide an additional interchange with the Downtown Line. Both stations are expected to be completed before mid-2030s.[64] [65] [66] [67]

Network and operations

Services

Train services on the North–South Line operates from approximately 5:30am to around midnight daily. In general, during peak hours, train frequency is 2 to 3 minutes while during non-peak hours the frequency is reduced to 5 minutes throughout the entire route.[68] Each day, the first train begins service at the following timings:

Extra downroute trips were added to start from Newton, Bishan or Kranji. Kranji is the best example because of the huge number of workers from Malaysia to Singapore. From 11pm onwards, selected trains from Jurong East station will terminate at either Ang Mo Kio, Toa Payoh or Yew Tee stations [69] Selected trains departing from Marina South Pier station will also terminate at Kranji, Yishun or Ang Mo Kio station in the late evenings. There are no express services.[70]

Train services on the North–South Line are also subjected to maintenance and renewal works, usually on selected Fridays, Saturdays or Sundays. Shuttle bus services may be provided throughout the duration of the early closures and late openings for affected commuters.[71] Operations of the North–South Line are affected by the COVID-19 pandemic, leading to the drop of ridership.[72] [73]

Route

The North–South line forms an incomplete loop from Jurong East in the West Region of Singapore, north to Woodlands and Sembawang, and south to the Central Area. It is 45km (28miles) long and is predominantly double-tracked, but certain short sections at the Woodlands, Yishun and Ang Mo Kio stations widen to three tracks,[74] [75] [76] and four tracks at Jurong East station.[77] The line begins above ground at Jurong East station[78] [79] from where it continues north on a set of elevated viaducts, with the exception of a short tunnel between the Bukit Batok and Bukit Gombak stations,[80] and a surface section of track between the Bukit Gombak and Choa Chu Kang stations.[81] The line curves from the Yew Tee to Kranji stations and continues eastwards, paralleling Woodlands Avenue 3 (which the line briefly cuts underneath between Kranji and Marsiling stations)[82] and Avenue 7 main roads.[83]

After Sembawang station, the line follows the route of Canberra Link and Yishun Avenue 2, curving southwards. Between Khatib and Yio Chu Kang stations parallel to Lentor Avenue, the line continues at surface level; this section is the longest distance between any two MRT stations in Singapore.[84] The line continues above ground for the Yio Chu Kang and Ang Mo Kio stations, then it goes back to surface level for Bishan station, the MRT system's only at-grade station. A branch line to Bishan Depot exists between the Ang Mo Kio and Bishan stations.[85] After Bishan, the line goes underground through the Central Area. The North–South Line runs parallel to the East–West Line at the City Hall and Raffles Place stations, which are also cross-platform interchanges to the East–West Line. The line ends at Marina South Pier station.[79]

Stations

The line serves 28 mrt stations across 45km (28miles) of track, and station codes for the line are red, corresponding to the line's colour on the system map.[86] [87] 11 stations, from Braddell to Marina South Pier are underground, with the rest being ground-level or elevated.[88] With the exception of Bishan, Braddell and Canberra stations, the other stations have island platforms.

North–South Line Stations Timeline! Date !! Project !! Description
7 November 1987 Phase 1
12 December 1987 Toa PayohOutram Park (Direct train service to Outram Park via Raffles Place)
12 March 1988 Phase 1A Outram ParkClementi (Now part of the East–West Line)
5 November 1988 Phase 2B ClementiLakeside (Now part of the East–West Line)
20 December 1988
4 November 1989 Phase 2A Raffles PlaceMarina Bay (Separation of the North–South Line & East–West Line)
10 March 1990 Phase 2B Jurong EastChoa Chu Kang (Operates as a branch line from Jurong East)
10 February 1996 Woodlands Extension Choa Chu KangYishun
23 November 2014 North–South Line Extension Marina BayMarina South Pier
2 November 2019 Canberra Station Canberra station between Sembawang and Yishun
2034 Future infill stations between existing stations Brickland station between Bukit Gombak and Choa Chu Kang
Mid-2030s Sungei Kadut station between Yew Tee and Kranji

Legend

List

Depots

NumberDepot name;
Lines
LocationImagesLine-specific
stabling capacity
CostOpening
  59 trains S$300 million
 
 
45 trains S$130 million

Infrastructure

Rolling stock

Electric Multiple Unit (EMU) trains on the North–South Line operate in a six-car formation, based out of Bishan Depot and Ulu Pandan Depot, which provide train maintenance, inspection and overhaul facilities.[93] [94] [95] Similar rolling stock is used on the East–West Line, with an electrification of 750 V DC powered by a third rail. With the exception of the C651 and R151 trains, the current rolling stock was manufactured by Kawasaki Heavy Industries, in a joint venture with CRRC Qingdao Sifang for the subsequent rolling stocks of the C151A, C151B and C151C trains.[96] When the initial line opened, the rolling stock of the North–South Line consisted of 66 first-generation C151 trains only. The 19 second-generation C651 trains were introduced during the Woodlands extension to complement the existing 66 first-generation C151 trains.[97] The 21 third-generation C751B trains were introduced during the Changi Airport extension to complement the existing 66 first-generation C151 trains and 19 second-generation C651 trains.[98] [99] In 2011, the fourth-generation C151A trains were introduced, increasing the passenger capacity of both the North–South and East–West lines by 15%.[100] [101] [102] The C151A trains were the first successful joint venture between Kawasaki Heavy Industries and CSR Qingdao Sifang in the international market.[103]

As part of efforts to further increase passenger capacity on the line, newer C151B and C151C trains were subsequently delivered in 2017 and 2018 respectively.[104] [105] The introduction of the C151B trains saw the introduction of STARiS 2.0, which is also seen in subsequent rolling stocks.[106] The C151C trains are also the first MRT rolling stock on the NSEWL to be fitted with tip-up seats, in addition to the current features of the C151B trains.[107] [108]

Another generation of rolling stock, the R151 trains, will be delivered from 2022 to 2026, to replace all 66 first-generation C151, all 19 second-generation C651 and all 21 third-generation C751B trains which will be retired. The R151 trains will be the first rolling stock on the North–South Line to be manufactured by Bombardier (Bought by Alstom in 2021), which has also supplied trains for the Downtown Line.[109] [110] [111]

Signalling

Initially, the North–South line used a semi-automatic signalling system consisting of the Westinghouse fixed block signalling system with automatic train control under automatic train operation Grades of Automation (GoA) 2.[112] [113] However, the ageing system had undermined the rail reliability on the line, requiring the NSL to upgrade its signalling system.[114] Since 2019, the North–South Line is fully equipped with Thales SelTrac Communications-based train control moving block signalling system with automatic train control under automatic train operation (ATO) GoA 4.[115] [116] The subsystems consist of automatic train protection to govern train speed, NetTrac MT Automatic Train Supervision (ATS) to track and schedule trains and a Computer-based interlocking system that prevents incorrect signal and track points to be set.[117]

A new moving-block signalling system, supplied by Thales, replaced the ageing fixed-block signalling system on the North–South Line. The upgrading works were completed in phases from 2016. With the upgraded signalling system, trains are now able to run closer to each other.[118] [119] The new system was tested on the evening of 28 March 2017. Train services were paused for ten minutes as the old signalling system was being changed to the new system.[120] From 16 April 2017, the new system commenced full-day testing on Sundays for two months. The new C151B rolling stock were first introduced to the line on these testing days.[121] Since 28 May 2017, the new signalling system has been operating full-day on the North–South Line.[122] The old signalling system then ceased operations on 2 January 2019.

Platform screen doors

When the line was first opened, full-height platform screen doors supplied by Westinghouse were installed at underground stations. These doors serve to prevent suicides, enable climate control within the station, better security control by restricting access to the tunnels and tracks and for overall passenger safety considerations.[123] The authorities initially rejected calls for platform screen doors to be installed at elevated stations by casting doubts over functionality and concerns about the high installation costs.[124] Nevertheless, the LTA reversed its decision and made plans to install half-height platform screen doors on elevated stations on 25 January 2008.[125] [126] The first platform screen doors by ST Electronics were installed at Pasir Ris, Jurong East and Yishun stations in 2009 as trial runs.[127] Subsequently, installation began in May 2011 at Ang Mo Kio station. On 14 March 2012, platform screen doors became operational at all elevated stations on the North–South Line.[128]

Rail

The NSL was built with wooden sleepers, which needed to be replaced when they neared the end of their lifespan of 15 to 25 years. The replacement sleepers, made out of concrete, have a significantly longer lifespan and enable smoother and safer rides.[129] Since 2014, train services on the line have ended earlier for critical maintenance works, with the exception of a break between September 2016 and December 2016.[130]

Trains on the NSL are powered via a third rail. However, constant contact between the train's Current Collector Devices (CCD) and the line saw the need for replacement works on the third rail, which were completed in August 2017.[129] [131] The new third rail replaced its 30-year-old predecessor, which was used since the opening of the line. The new electrical system is expected to make train services more reliable.[132]

External links

Notes and References

  1. Web site: Land Transport DataMall . mytransport.sg . 20 August 2020 . 21 August 2020 . https://web.archive.org/web/20200821123230/https://www.mytransport.sg/content/mytransport/home/dataMall.html . live .
  2. Web site: LTA North–South Line . 16 October 2022 . www.lta.gov.sg . 1 November 2019 . https://web.archive.org/web/20191101093902/https://www.lta.gov.sg/content/ltagov/en/getting_around/public_transport/rail_network/north_south_line.html#:~:text=The%20North-South%20Line:%20Singapore%27s%20first%20MRT%20line&text=The%2027%20stations%20along%20the,East%20to%20Marina%20South%20Pier. . live .
  3. News: . 'Unique nation State' plan . 20 September 1967 . . 6 . . 14 April 2020 . https://web.archive.org/web/20191115204019/http://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19670920-1.2.22 . 15 November 2019 . live .
  4. Book: Seah C. M.. Southeast Asian Affairs.. 1981. Singapore: Institute of Southeast Asian Studies. 293. 14 April 2020. 19 September 2020. https://web.archive.org/web/20200919041256/https://eservice.nlb.gov.sg/item_holding.aspx?bid=4183690. live.
  5. Book: Sharp, Ilsa . sharp2005 . The Journey — Singapore's Land Transport Story . SNP:Editions . 2005 . 978-981-248-101-6.
  6. 10.1.1.119.9246 . Fwa Tien Fang . Sustainable Urban Transportation Planning and Development — Issues and Challenges for Singapore . 4 September 2004 . Department of Civil Engineering, National University of Singapore.
  7. Web site: 1982 – The Year Work Began . Land Transport Authority . 16 November 2013 . https://web.archive.org/web/20130929173053/http://www.lta.gov.sg/content/ltaweb/en/about-lta/our-history/1980s.html . 29 September 2013 . live .
  8. News: Lee Siew Hoon . Chandra Mohan . amp . In Memoriam — Ong Teng Cheong: A Profile . https://web.archive.org/web/20020223222029/http://www.channelnewsasia.com/cna/obituaries/ongtengcheong/special2.htm . 23 February 2002 . . Singapore . 26 November 2007.
  9. News: Project to go on line in three stages . The Straits Times . 8 July 1986 . 8 . 8 March 2021 . 12 April 2022 . https://web.archive.org/web/20220412214257/https://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19860708-1.2.54.13.2 . live .
  10. Book: Annual report / Provisional Mass Rapid Transit Authority, Republic of Singapore.. Singapore: Provisional Mass Rapid Transit Authority. 1983. 5.
  11. News: North–south line off first . The Straits Times . 29 August 1982 . 19 December 2020 . 19 December 2020 . https://web.archive.org/web/20201219051543/https://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19820829-1.2.2 . live .
  12. News: Work begins on the first part of MRT system . The Straits Times . 29 October 1983 . 19 December 2020 . 19 December 2020 . https://web.archive.org/web/20201219051544/https://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19831029-1.2.70.8 . live .
  13. News: All aboard for the Subway Age. The Straits Times. 8 November 1987. 3 February 2020. https://web.archive.org/web/20170912145237/http://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19871108-1.2.2. 12 September 2017. live.
  14. Web site: MRT system begins operations – Singapore History. eresources.nlb.gov.sg. 8 April 2020. https://web.archive.org/web/20200212134059/http://eresources.nlb.gov.sg/history/events/e926e24f-9c14-482b-b278-d582b535deb6. 12 February 2020. live.
  15. Web site: Speech by Dr Yeo Ning Hong, Minister For Communications and Information And Second Minister For Defence (Policy), at the inauguration of public service of the MRT system at the Toa Payoh Station on Saturday, 7 November 1987 at 9.00 am . nas.gov.sg . 7 November 1987 . 19 December 2020 . 19 July 2019 . https://web.archive.org/web/20190719034357/http://www.nas.gov.sg/archivesonline/data/pdfdoc/ynh19871107s.pdf . live .
  16. News: Shopping for Xmas the MRT way.... Rav. Dhaliwal. 12 December 1987. Straits Times. 19 September 2017. eResources. https://web.archive.org/web/20180124011005/http://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19871212-1.2.3. 24 January 2018. live.
  17. News: MRT Yishun opens, two-thirds of system now complete. The New Paper. 20 December 1988. NewspaperSG. 8. en. 3 February 2020. https://web.archive.org/web/20171007221657/http://eresources.nlb.gov.sg/newspapers/Digitised/Article/newpaper19881220-1.2.11.2. 7 October 2017. live.
  18. News: New names for eight stations . Singapore Monitor . 30 November 1982.
  19. News: Dhaliwal. Rav. East-enders get ticket to ride as MRT opens line. The Straits Times. 21 April 2020. 19 September 2020. https://web.archive.org/web/20200919041254/https://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19891104-1.2.33.1. live.
  20. News: 11 March 1988. MRTC considering extending line to Woodlands. The Straits Times. 19 September 2020. https://web.archive.org/web/20200919041253/https://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19880311-1.2.5. live.
  21. Web site: Woodlands MRT line Infopedia. National Library Board. eresources.nlb.gov.sg. 19 September 2017. https://web.archive.org/web/20180101140912/http://eresources.nlb.gov.sg/infopedia/articles/SIP_364_2005-01-28.html. 1 January 2018. live.
  22. News: Work on Woodlands MRT line to begin later this year. Leong. C. T.. 26 February 1991. The Straits Times.
  23. Web site: Past Concept Plans. www.ura.gov.sg. 30 January 2020. https://web.archive.org/web/20200130132455/https://www.ura.gov.sg/Corporate/Planning/Concept-Plan/Past-Concept-Plans. 30 January 2020. live.
  24. Book: Living the next lap: towards a tropical city of excellence.. Urban Redevelopment Authority. 1991. 14.
  25. News: Better layouts for six new MRT stations. 19 November 1992. The Straits Times.
  26. News: Another station added to Woodlands MRT line. 19 November 1992. The Straits Times.
  27. Web site: Kranji MRT station . National Library Board Singapore . 11 November 2003 . 3 February 2012 . Thulaja, Naidu Ratnala . dead . https://web.archive.org/web/20131231050129/http://infopedia.nl.sg/articles/SIP_365_2005-01-28.html . 31 December 2013 .
  28. News: Station names for Woodlands line have ties to surroundings . The Straits Times . 20 November 1991 . 3 . Sembawang will be in the proposed town centre of Sembawang New Town, while Kadut station will be in Sungei Kadut Industrial Estate, earmarked for redevelopment into a new town.
  29. News: Woodlands MRT closer. 4 October 1994. The Straits Times.
  30. Web site: Speech by Prime Minister Goh Chok Tong at the opening of Woodlands MRT line on Saturday, 10 February 1996 at 10.00 am. 10 February 1996. live. https://web.archive.org/web/20190714093300/http://www.nas.gov.sg/archivesonline/data/pdfdoc/19960210_0001.pdf. 14 July 2019.
  31. News: New Platform at Bishan Station ready. 26 July 2008. The Straits Times.
  32. News: Bishan MRT station ready for Circle crowds . The Straits Times . 22 May 2009. 49.
  33. Web site: Jurong East Modification Project. 31 January 2012 . dead . https://web.archive.org/web/20120212162757/http://app.lta.gov.sg/corp_press_content.asp?start=1964 . 12 February 2012 .
  34. Web site: New Platform At Jurong East Station To Open On 27 May . Land Transport Authority of Singapore . 16 May 2011 . 22 November 2014 . https://web.archive.org/web/20141220064357/http://www.lta.gov.sg/apps/news/page.aspx?c=2&id=9h18aw9i6asknrt367xu15fsk5yfn42ppgtynwhh6ob20585f8 . 20 December 2014 . live .
  35. Web site: New Platform At Jurong East Station To Open On 27 May Press Room Land Transport Authority. www.lta.gov.sg. en. 23 September 2017. https://web.archive.org/web/20170923145050/https://www.lta.gov.sg/apps/news/page.aspx?c=2&id=9h18aw9i6asknrt367xu15fsk5yfn42ppgtynwhh6ob20585f8. 23 September 2017. live.
  36. Web site: Land Transport Master Plan 2008 (Pg 34). February 2008. www.lta.gov.sg. live. https://web.archive.org/web/20121111133443/http://www.lta.gov.sg/content/dam/ltaweb/corp/PublicationsResearch/files/ReportNewsletter/LTMP-Report.pdf. 11 November 2012. 8 November 2019.
  37. Web site: Marina South Pier MRT Station on North–South Line to open on Sunday. 22 November 2014. The Straits Times. en. live. https://web.archive.org/web/20180224163243/http://www.straitstimes.com/singapore/transport/marina-south-pier-mrt-station-on-north-south-line-to-open-on-sunday. 24 February 2018. 8 November 2019.
  38. Web site: Marina South Pier Station to Open on 23 November. 17 November 2014. lta.gov.sg. live. https://web.archive.org/web/20150307081123/http://www.lta.gov.sg/apps/news/page.aspx?c=2&id=4518c4b9-a674-42a4-9f27-81d9325bb983. 7 March 2015. 8 November 2019.
  39. Web site: North–South Line Extension Projects Public Transport Land Transport Authority. www.lta.gov.sg. en. 19 September 2017. https://web.archive.org/web/20120930005359/http://www.lta.gov.sg/content/ltaweb/en/public-transport/projects/north-south-line-extension.html. 30 September 2012. live.
  40. Web site: Speech by Mr Lui Tuck Yew at visit to DTL1 Chinatown Station on 17 January 2013 . MOT . 19 September 2019 . 17 January 2013 . https://web.archive.org/web/20200226205104/https://www.mot.gov.sg/news-centre/news/Detail/Speech%20by%20Mr%20Lui%20Tuck%20Yew%20at%20visit%20to%20DTL1%20Chinatown%20Station%20on%2017%20January%202013/ . 26 February 2020 . live .
  41. Web site: Two New Rail Lines And Three New Extensions To Expand Rail Network By 2030 . Land Transport Authority . 17 January 2013 . 1 August 2014 . dead . https://web.archive.org/web/20140706170425/http://app.lta.gov.sg/apps/news/page.aspx?c=2&id=38dc4ca3-5e70-4bf8-97bc-87f78e6303e7 . 6 July 2014 .
  42. Web site: New MRT station for North–South Line: Canberra . The Straits Times . 27 June 2014 . 1 August 2014 . https://web.archive.org/web/20140808063321/http://www.straitstimes.com/news/singapore/transport/story/new-mrt-station-north-south-line-canberra-20140627 . 8 August 2014 . live .
  43. Web site: Work Starts for Canberra MRT Station on North–South Line. 26 March 2016. LTA. https://web.archive.org/web/20171011181151/https://www.lta.gov.sg/apps/news/page.aspx?c=2&id=7de0099c-4e9d-4a67-bb3f-217885a85fe3. 11 October 2017. dead. 11 October 2017.
  44. Web site: Work starts on Canberra MRT station. Channel NewsAsia. 3 March 2016. https://web.archive.org/web/20160306190102/http://www.channelnewsasia.com/news/singapore/work-starts-on-canberra/1809560.html. 6 March 2016. live.
  45. Web site: Canberra MRT station to open on Nov 2 . CNA . 20 May 2019 . 20 May 2019 . https://web.archive.org/web/20190520150011/https://www.channelnewsasia.com/news/singapore/canberra-mrt-station-open-nov-2-lta-11548606 . 20 May 2019 . live .
  46. News: Car accident on the MRT track . RIMAS . March 2003 . 3 February 2020 . https://web.archive.org/web/20120208072834/http://www.rimas.org.sg/files/Article%20-%20An%20MRT%20Accident.doc . 8 February 2012 . dead .
  47. News: North–South MRT line breakdown hits thousands. Channel News Asia. 15 December 2011. 17 March 2012. https://web.archive.org/web/20120329170737/http://www.channelnewsasia.com/stories/singaporelocalnews/view/1171573/1/.html. 29 March 2012. live.
  48. Web site: 2nd Update – SMRT statement: Service disruption on North–South Line (Northbound): Marina Bay Station to Bishan Station. dead. https://web.archive.org/web/20120414224606/http://www.smrt.com.sg/Upload/2011121610464247486.pdf. 14 April 2012.
  49. News: MRT breaks down again . Channel NewsAsia . 17 December 2011 . 17 December 2011 . https://web.archive.org/web/20120107150702/http://www.channelnewsasia.com/stories/singaporelocalnews/view/1171888/1/.html . 7 January 2012 . live .
  50. News: North–South Line service resumes after 7-hour disruption . Channel NewsAsia . 17 December 2011 . 17 December 2011 . https://web.archive.org/web/20120107185109/http://www.channelnewsasia.com/stories/singaporelocalnews/view/1171914/1/.html . 7 January 2012 . live .
  51. Web site: Service disruption on North–South Line on 17 Dec 2011 . dead . https://web.archive.org/web/20120414224614/http://www.smrt.com.sg/Upload/2011121715425352588.pdf . 14 April 2012 .
  52. News: Minister Updates Parliament on MRT Disruptions . Ministry Of Transport . 9 January 2012 . dead . https://web.archive.org/web/20120702205320/http://app.mot.gov.sg/News_Centre/Perspective/VID/68B1100028F13900/Minister_Updates_Parliament_on_MRT_Disruptions.aspx . 2 July 2012 . dmy-all .
  53. Web site: Power trip on MRT network due to power fault on NSEWL. LTA. https://web.archive.org/web/20160427123605/http://www.channelnewsasia.com/news/singapore/power-trip-on-mrt-network/2733272.html. 27 April 2016. dead.
  54. Web site: Tan . Christopher . Full train service resumes; no suspension of North–South line at 11am . The Straits Times . 7 July 2015 . 23 August 2020 . 23 August 2020 . https://web.archive.org/web/20200823131752/https://www.straitstimes.com/singapore/transport/full-train-service-resumes-no-suspension-of-north-south-line-at-11am . live .
  55. News: MRT breakdown: North–South, East–West lines down for hours. Tang. Louisa. Today. Singapore. Mediacorp. 7 July 2015. 23 August 2020. 23 August 2020. https://web.archive.org/web/20200823131710/https://www.todayonline.com/singapore/train-services-down-north-south-and-east-west-lines. live.
  56. News: Cause of massive NSEWL train disruption in July identified, says SMRT. CNA. Singapore. Mediacorp. 22 August 2015. Malinda, Kyle. 3 March 2016. 6 March 2016. https://web.archive.org/web/20160306190436/http://www.channelnewsasia.com/news/singapore/cause-of-massive-nsewl/2014794.html. live.
  57. News: SMRT to be fined a record S$5.4m for July 7 MRT breakdown . Channel NewsAsia . Singapore . 23 September 2015 . 3 March 2016 . 17 January 2016 . https://web.archive.org/web/20160117124430/http://www.channelnewsasia.com/news/singapore/smrt-to-be-fined-a-record/2146104.html . live .
  58. News: NSL disruption: No train services between Ang Mo Kio, Newton 'till further notice', says SMRT. Channel NewsAsia. 8 October 2017. en-SG. https://web.archive.org/web/20171008044136/http://www.channelnewsasia.com/news/singapore/nsl-disruption-flooded-mrt-tunnel-sunday-9290220?view=DEFAULT. 8 October 2017. live.
  59. News: NSL disruption: Malfunctioning water pumping system resulted in flooded MRT tunnel, says LTA. Channel NewsAsia. 8 October 2017. en-GB. https://web.archive.org/web/20171008181159/http://www.channelnewsasia.com/news/singapore/lta-on-flooded-mrt-tunnel-9290804. 8 October 2017. live.
  60. Web site: hermesauto. 14 October 2020. Train services restored on North–South, East–West, Circle lines after disruption due to power fault. 15 October 2020. The Straits Times. en. 15 October 2020. https://web.archive.org/web/20201015023308/https://www.straitstimes.com/singapore/transport/power-fault-on-north-south-line-east-west-line-results-in-extra-train-travel. live.
  61. Web site: Oct 14 MRT breakdown: Manufacturer to replace power cables along Tuas West Extension, 2 SMRT staff suspended . 1 April 2022 . TODAY . en . 1 April 2022 . https://web.archive.org/web/20220401023420/https://www.todayonline.com/singapore/oct-14-train-breakdown-all-power-cables-trip-coils-along-tuas-west-extension-be-replaced . live .
  62. News: Hamzah . Aqil . 2023-10-27 . Novena MRT station reopens after closure caused by smoke from air-con unit . en . The Straits Times . 2023-11-16 . 0585-3923.
  63. News: Ang . Qing . 2024-06-03 . Lightning strike sparks power trip that disrupted MRT services on NSL for over 2 hours . 2024-06-03 . The Straits Times . en . 0585-3923.
  64. News: New Sungei Kadut MRT station linking North–South and Downtown lines could shorten trips by 30 mins. The Straits Times. 25 May 2019 . 25 May 2019. https://web.archive.org/web/20190525105557/https://www.straitstimes.com/singapore/transport/new-sungei-kadut-mrt-station-linking-north-south-and-downtown-lines-could. 25 May 2019. live.
  65. Web site: Land Transport Master Plan 2040. www.mot.gov.sg. 11 December 2019. https://web.archive.org/web/20190713174806/https://www.mot.gov.sg/ltmp2040/. 13 July 2019. live.
  66. Web site: Land Transport Master Plan 2040: Bringing Singapore Together Press Room Land Transport Authority . Land Transport Authority . 26 May 2019 . https://web.archive.org/web/20190823063103/https://www.lta.gov.sg/apps/news/page.aspx?c=2&id=de83f659-4b0d-4609-840e-3deb3ac9b4b9 . 23 August 2019 . live .
  67. Web site: At a glance: Key updates to MRT, bus network and more for 2040 master plan . TODAYonline . 25 May 2019 . 28 May 2019 . https://web.archive.org/web/20190525141717/https://www.todayonline.com/singapore/at-a-glance-key-updates-to-mrt-bus-network-and-more-2040-master-plan . 25 May 2019 . live .
  68. Web site: LTA Getting Around Public Transport Rail Network. www.lta.gov.sg. 5 April 2020. https://web.archive.org/web/20191101093543/https://www.lta.gov.sg/content/ltagov/en/getting_around/public_transport/rail_network.html. 1 November 2019. live.
  69. Web site: SMRT Journeys. journey.smrt.com.sg. 5 April 2020. https://web.archive.org/web/20190904072806/http://journey.smrt.com.sg/journey/station_info/jurong-east/first-and-last-train. 4 September 2019. live.
  70. Web site: SMRT Journeys. journey.smrt.com.sg. 5 April 2020. 19 September 2020. https://web.archive.org/web/20200919041252/http://journey.smrt.com.sg/journey/station_info/marina-south-pier/first-and-last-train/. live.
  71. Web site: Early Closure of Selected North–South Line Stations from January to March 2020. www.smrt.com.sg. 5 April 2020. https://web.archive.org/web/20191229171330/http://www.smrt.com.sg/Announcements/articleid/1220. 29 December 2019. live.
  72. Web site: Last train services for MRT and LRT (Annex B) . LTA . 15 April 2020 . https://web.archive.org/web/20200417141415/https://www.lta.gov.sg/content/dam/ltagov/news/press/2020/20200414_Last%20train%20service%20for%20MRT%20and%20LRT_AnnexB.pdf . 17 April 2020 . live .
  73. Web site: Changes to Public Bus and Train Operating Hours and Frequency. www.lta.gov.sg. 15 April 2020. https://web.archive.org/web/20200417141400/https://www.lta.gov.sg/content/ltagov/en/newsroom/2020/april/news-releases/Changes_to_public_bus_and_train_operating_hours.html. 17 April 2020. live.
  74. OpenStreetMap contributors . 28 March 2020 . Woodlands MRT station . https://www.openstreetmap.org/#map=19/1.43542/103.78297 . OpenStreetMap . 28 March 2020 .
  75. OpenStreetMap contributors . 28 March 2020 . Yishun MRT station . https://www.openstreetmap.org/#map=19/1.43453/103.83434 . OpenStreetMap . 28 March 2020 .
  76. OpenStreetMap contributors . 28 March 2020 . Ang Mo Kio MRT station . https://www.openstreetmap.org/node/1839603981#map=17/1.37008/103.84953 . OpenStreetMap . 28 March 2020.
  77. OpenStreetMap contributors . 28 March 2020 . Jurong East MRT station . https://www.openstreetmap.org/node/209451066#map=17/1.33348/103.74369 . OpenStreetMap . 28 March 2020 .
  78. Web site: OneMap. OneMap. 24 April 2020. 18 April 2020. https://web.archive.org/web/20200418055059/https://www.onemap.sg/main/v2/. live.
  79. Web site: MRT System Map. LTA. 21 August 2020. https://web.archive.org/web/20200821064838/https://www.lta.gov.sg/content/dam/ltagov/getting_around/public_transport/rail_network/pdf/sm-20-03-en-exp.pdf. live.
  80. OpenStreetMap contributors . 28 March 2020 . Tunnel between Bukit Batok and Bukit Gombak . https://www.openstreetmap.org/#map=19/1.35209/103.75176. OpenStreetMap . 28 March 2020 .
  81. OpenStreetMap contributors . 28 March 2020 . Surface section of track between Bukit Gombak and Choa Chu Kang . https://www.openstreetmap.org/#map=18/1.37540/103.74391. OpenStreetMap . 28 March 2020 .
  82. OpenStreetMap contributors . 28 March 2020 . Tunnel underneath Woodlands Avenue 3 . https://www.openstreetmap.org/#map=18/1.42887/103.76629. OpenStreetMap . 28 March 2020 .
  83. OpenStreetMap contributors . 31 March 2020 . NSL along Avenue 7 . https://www.openstreetmap.org/#map=17/1.43929/103.79270. OpenStreetMap . 28 March 2020 .
  84. OpenStreetMap contributors . 28 March 2020 . Surface section of track between Khatib and Yio Chu Kang . https://www.openstreetmap.org/#map=17/1.39679/103.83200. OpenStreetMap . 28 March 2020 .
  85. OpenStreetMap contributors . 31 March 2020 . Bishan Depot . https://www.openstreetmap.org/way/633298871. OpenStreetMap . 28 March 2020 .
  86. Web site: North–South Line. 24 December 2015. Land Transport Authority. https://web.archive.org/web/20170107085131/https://www.lta.gov.sg/content/ltaweb/en/public-transport/projects/north-south-line.html. 7 January 2017. live.
  87. Web site: North–South Line Extension. LTA. https://web.archive.org/web/20120930005359/http://www.lta.gov.sg/content/ltaweb/en/public-transport/projects/north-south-line-extension.html. 30 September 2012. dead. 11 October 2017.
  88. Book: . Singapore Bilingual Street Directory . Mighty Minds Publishing Pte Ltd . fold out map . 2017 . 9789812501189.
  89. Web site: Woodlands MRT line. 10 October 2019. 1 January 2018. https://web.archive.org/web/20180101140912/http://eresources.nlb.gov.sg/infopedia/articles/SIP_364_2005-01-28.html. live.
  90. Web site: Woodlands MRT line. 10 October 2019. 1 January 2018. https://web.archive.org/web/20180101140912/http://eresources.nlb.gov.sg/infopedia/articles/SIP_364_2005-01-28.html. live.
  91. Web site: Revenue & Expenditure Estimates. www.singaporebudget.gov.sg. en-US. 17 April 2018. 18 April 2018. https://web.archive.org/web/20180418092803/http://www.singaporebudget.gov.sg/budget_2018/BudgetSpeech/RevenueExpenditure/RevenueExpenditureEstimates.aspx. live.
  92. Web site: Projects . Land Transport Authority . 3 May 2010 . 14 June 2022 . 5 June 2011 . https://web.archive.org/web/20110605124529/http://www.lta.gov.sg/projects/proj_maps_rail_l.htm . live .
  93. News: 10 shortlisted for Bishan Depot deal. 10 June 1984. The Straits Times. 11 October 2017. https://web.archive.org/web/20171011182744/http://eresources.nlb.gov.sg/newspapers/Digitised/Article/straitstimes19840610-1.2.36. 11 October 2017. live.
  94. News: Building the MRT's third depot. 17 October 1986. The Straits Times. 11 October 2017. https://web.archive.org/web/20171011183249/http://eresources.nlb.gov.sg/newspapers/Digitised/Article/biztimes19861017-1.2.10.14. 11 October 2017. live.
  95. News: North–South Line signalling system to take up to 6 months to stabilise. Channel NewsAsia. 11 October 2017. en-US. https://web.archive.org/web/20171119100248/http://www.channelnewsasia.com/news/singapore/north-south-line-signalling-system-to-take-up-to-6-months-to-9031560. 19 November 2017. live.
  96. Web site: 海外向け車両 鉄道車両. 川崎重工業株式会社. ja. 8 April 2020. https://web.archive.org/web/20190922082314/http://www.khi.co.jp/mobility/rail/export.html. 22 September 2019. live.
  97. News: $290 million contracts for Woodlands MRT line. 16 August 1992. The Straits Times.
  98. Web site: EMU Trains for the Singapore Land Transport Authority . Kawasaki Heavy Industries . 5 November 2012 . https://web.archive.org/web/20121231070440/http://www.khi.co.jp/english/rs/product/detail/pro_singapore.html . 31 December 2012 . live .
  99. Web site: Rapid Transit Kawasaki Heavy Industries. global.kawasaki.com. 8 April 2020. https://web.archive.org/web/20200408010932/https://global.kawasaki.com/en/mobility/rail/rapid_transit/index.html. 8 April 2020. live.
  100. Web site: Extra metro trains for Singapore . . 7 May 2009 . dead . https://web.archive.org/web/20091113051116/http://www.railwaygazette.com/news/single-view/view/extra-metro-trains-for-singapore.html . 13 November 2009 .
  101. Web site: Five new trains added to boost capacity of North–South and East–West Lines . . 16 May 2011 . dead . https://web.archive.org/web/20110927090934/http://www.smrt.com.sg/Upload/20115161592799442.pdf . 27 September 2011 .
  102. Web site: Train capacity to rise by up to 50% in 4 years. 8 April 2020. https://web.archive.org/web/20120229180453/http://www.straitstimes.com/BreakingNews/Singapore/Story/STIStory_733460.html. 29 February 2012. live.
  103. Web site: CSR Sifang and Kawasaki Heavy Industries Won the Bid in the Subway Vehicle Project of Singapore . https://archive.today/20120723075002/http://www.csrgc.com.cn/ens/xwzx/2009-05-13/1277.shtml . dead . 23 July 2012 . 13 May 2009 . 8 February 2012 .
  104. Web site: New signalling system trials extended to full day every Sunday: SMRT, LTA . Channel NewsAsia . 12 April 2017 . 8 April 2020 . https://web.archive.org/web/20170415202840/http://www.channelnewsasia.com/news/singapore/new-signalling-system-trials-extended-to-full-day-every-sunday/3671664.html . 15 April 2017 . live .
  105. Web site: LTA Singapore Orders 12 MRT Trains (72 cars) for North–South/East–West Lines Kawasaki Heavy Industries, Ltd.. 29 April 2016. 8 June 2017. https://web.archive.org/web/20160429033133/http://global.kawasaki.com/en/corp/newsroom/news/detail/?f=20150922_0034. 29 April 2016.
  106. Web site: SMRT Boosts Service Excellence Efforts with first Customer Experience Innovation Conference . SMRT Corporation . 21 January 2016 . 8 April 2020 . 19 September 2020 . https://web.archive.org/web/20200919041330/http://www.smrt.com.sg/News-Room/Announcements-News-Releases/articleid/733/%20News%20Releases/parentId/180/year/2016?category=Announcements+ . live .
  107. News: Tan. Christopher. SMRT adding 12 trains to two most heavily used lines. 14 August 2018. The Straits Times. live. https://web.archive.org/web/20200408010247/https://www.straitstimes.com/singapore/transport/smrt-adding-12-trains-to-two-most-heavily-used-lines. 8 April 2020.
  108. Web site: LTA News Room News Releases 12 More Trains to Boost Capacity of North–South and East–West Lines. www.lta.gov.sg. 15 April 2020. https://web.archive.org/web/20191227140330/https://www.lta.gov.sg/content/ltagov/en/newsroom/2015/9/2/12-more-trains-to-boost-capacity-of-north-south-and-east-west-lines.html. 27 December 2019. live.
  109. Web site: LTA News Room News Releases Bombardier to Supply 66 New Trains for North–South and East–West Lines. www.lta.gov.sg. 8 February 2020. 15 November 2019. https://web.archive.org/web/20191115185341/https://www.lta.gov.sg/content/ltagov/en/newsroom/2018/7/2/bombardier-to-supply-66-new-trains-for-north-south-and-east-west-lines.html. live.
  110. News: New fleet to replace 66 oldest MRT trains from 2021. Channel NewsAsia. 25 July 2018. en-US. 25 July 2018. https://web.archive.org/web/20180725183703/https://www.channelnewsasia.com/news/singapore/new-fleet-to-replace-66-oldest-mrt-trains-from-2021-10561652. live.
  111. News: Bombardier awarded $1.2 billion contract to replace 66 oldest MRT trains. hermesauto. 25 July 2018. The Straits Times. 25 July 2018. en. 18 December 2019. https://web.archive.org/web/20191218205005/https://www.straitstimes.com/singapore/transport/bombardier-awarded-12-billion-contract-to-replace-66-oldest-mrt-trains. live.
  112. Web site: Woodland. Daniel. August 2004. Optimisation of Automatic Train Protection Systemstion Systems. Appendix C Page 32 to Page 33. live. https://web.archive.org/web/20200615155037/http://etheses.whiterose.ac.uk/14543/1/531116.pdf. 15 June 2020. 15 June 2020.
  113. Web site: Oral Reply by Minister for Transport Khaw Boon Wan to Parliamentary Question on North–South Line Resignalling. www.mot.gov.sg. en. 25 April 2020. 16 June 2020. https://web.archive.org/web/20200616000115/https://www.mot.gov.sg/news-centre/news/Detail/%20Oral%20Reply%20by%20Minister%20for%20Transport%20Khaw%20Boon%20Wan%20to%20Parliamentary%20Question%20on%20North-South%20Line%20Resignalling(1)/. live.
  114. Web site: Speech by Minister Khaw Boon Wan at the Fourth Joint Forum on Infrastructure Maintenance. www.mot.gov.sg. en. 25 April 2020. 19 September 2020. https://web.archive.org/web/20200919041330/https://www.mot.gov.sg/news-centre/news/Detail/Speech%20by%20Minister%20Khaw%20Boon%20Wan%20at%20the%20Fourth%20Joint%20Forum%20on%20Infrastructure%20Maintenance/. live.
  115. Web site: Thales awarded signalling contracts for Singapore North–South, East–West lines and Tuas West Extension. www.thalesgroup.com. en. 4 July 2017. https://web.archive.org/web/20170820160452/https://www.thalesgroup.com/en/press-release/thales-awarded-signalling-contracts-singapore-north-south-east-west-lines-and-tuas. 20 August 2017. dead.
  116. Web site: Metro automation facts, figures and trends. International Association of Public Transport. live. https://web.archive.org/web/20160501034433/http://www.uitp.org/sites/default/files/Metro%20automation%20-%20facts%20and%20figures.pdf. 1 May 2016.
  117. Web site: Thales awarded signalling contracts for Singapore North–South, East–West lines and Tuas West Extension . 6 February 2012 . Thales Group . dead . https://web.archive.org/web/20150630183155/https://www.thalesgroup.com/en/content/thales-awarded-signalling-contracts-singapore-north-south-east-west-lines-and-tuas-west . 30 June 2015 . dmy-all .
  118. Web site: THALES Urban Rail Signalling Singapore – North–South / East-West Lines. live. https://web.archive.org/web/20200615163959/http://tda-armements.com/sites/default/files/asset/document/seltracr_in_singapore.pdf. 15 June 2020. 16 June 2020.
  119. Web site: LTA Website. North–South Line Signal Upgrade. Land Transport Authority. 21 April 2017. https://web.archive.org/web/20180617192724/https://www.lta.gov.sg/content/ltaweb/en/public-transport/projects/north-south-line.html. 17 June 2018. live.
  120. Web site: Joint Media Release by the Land Transport Authority (LTA) & SMRT – New Signalling System Trial on North–South Line Begins on 28 March 2017 . LTA . 28 March 2017 . 22 April 2020 . 19 September 2020 . https://web.archive.org/web/20200919041330/https://www.lta.gov.sg/content/ltagov/en/newsroom/2017/3/2/joint-media-release-by-the-land-transport-authority-lta-smrt---new-signalling-system-trial-on-north-south-line-begins-o.html . live .
  121. Web site: Factsheet by the Land Transport Authority (LTA) & SMRT: Full-day Sunday Trial of New Signalling System for North–South Line from 16 April 2017 . LTA . 16 April 2017 . 22 April 2020 . 19 September 2020 . https://web.archive.org/web/20200919041330/https://www.lta.gov.sg/content/ltagov/en/newsroom/2017/4/2/factsheet-by-the-land-transport-authority-lta-smrt-full-day-sunday-trial-of-new-signalling-system-for-north-south-line-.html . live .
  122. Web site: 7 Questions about SMRT Trains' New Signalling System – SMRT Blog. blog.smrt.com.sg. 6 June 2017 . en-GB. 11 October 2017. https://web.archive.org/web/20171011182458/http://blog.smrt.com.sg/7-questions-about-smrt-trains-new-signalling-system/. 11 October 2017. live.
  123. http://www.platformscreendoors.com/psd/projects/massrapid.php Westinghouse Platform Screen Doors – Completed Projects
  124. Safety at MRT and LRT Stations — Respect The Yellow line . Land Transport Authority . 20 November 2005 . dead . https://web.archive.org/web/20070927182635/http://app.lta.gov.sg/corp_press_content.asp?start=1090 . 27 September 2007 .
  125. News: The Straits Times . Platform screen doors for all above-ground MRT stations by 2012 . 25 January 2008 . https://web.archive.org/web/20080128072930/http://www.straitstimes.com/Latest+News/Singapore/STIStory_199958.html. 28 January 2008.
  126. Speech by Mr Raymond Lim, Minister for Transport, at the Visit to Kim Chuan Depot, 25 January 2008, 9.00am. Ministry of Transport. 25 January 2008. 11 January 2015. https://web.archive.org/web/20150112142646/http://www.mot.gov.sg/News-Centre/News/2008/Speech-By-Mr-Raymond-Lim-At-The-Visit-To-Kim-Chuan-Depot-on-25-January-2008/. 12 January 2015. dead.
  127. News: Platform doors for elevated MRT stations . Yeo Ghim Lay . 3 September 2008 . The Straits Times . 26. https://web.archive.org/web/20090816160221/http://www.straitstimes.com/Breaking+News/Singapore/Story/STIStory_416017.html . 16 August 2009. dead.
  128. News: LTA completes installing elevated MRT station screen doors early. Channel NewsAsia. 23 September 2017. en-US. https://web.archive.org/web/20170924001503/http://www.channelnewsasia.com/news/singapore/lta-completes-installing-elevated-mrt-station-screen-doors-early-8443586. 24 September 2017. live.
  129. Web site: SMRT Rail Improvements – Updates – SMRT Blog. blog.smrt.com.sg. 17 October 2016 . en-GB. 19 September 2017. https://web.archive.org/web/20170923144948/http://blog.smrt.com.sg/smrt-rail-improvements/. 23 September 2017. live.
  130. News: Project to replace MRT sleepers done. The Straits Times . 25 December 2016 . https://web.archive.org/web/20170329142812/http://www.straitstimes.com/singapore/project-to-replace-mrt-sleepers-done. 29 March 2017. live.
  131. Web site: Factsheet on Power Rail Replacement Programme for the North–South and East–West Lines (NSEWL). https://web.archive.org/web/20170923144946/https://www.smrt.com.sg/Portals/0/Factsheet_%20Power%20Rail%20Replacement_vF_1.pdf. 23 September 2017. dead.
  132. Web site: Third Rail Replacement on North South and East West Line. https://web.archive.org/web/20170216050249/http://blog.smrt.com.sg/third-rail-replacement-of-the-north-south-east-west-line/. 16 February 2017. live.