National Route 39 (Costa Rica) Explained

Country:CRI
Type:Primary
Route:39
Alternate Name:Second Republic Drive
Spanish; Castilian: Paseo de la Segunda República
Loop Road
Spanish; Castilian: Carretera de Circunvalación
Map:CR RNP 39 map.svg
Map Notes:Dotted line depicts north arc under construction since 2017
Photo Alt:Pedestrian crossing over Route 39, in Hatillo district.
Length Km:14.910
Length Round:2
Established:1979
History:Opened in 1979
To be completed in May 2022[1]
Loop:San José
Junction:


(Under construction as of 2019)
Provinces:San José
Previous Type:RNP
Previous Route:36
Next Type:RNP
Next Route:1

National Primary Route 39, or just Route 39 (Spanish; Castilian: Ruta Nacional Primaria 39, or Spanish; Castilian: Ruta 39) is a National Road Route of Costa Rica, located in the San José province.[2] Its official name is Spanish; Castilian: Paseo de la Segunda República (Second Republic Drive), is also known as Spanish; Castilian: Carretera de Circunvalación (Loop Road), and is an incomplete ring road encircling the central districts of San José canton, the capital of the country.

Description

It is one of the main roads of the capital San José, its purpose is to avoid the congestion of the inner districts. Currently, it starts in Uruca, in Avenida 39, which then takes south and to the east, finishing in the Goicoechea junction to Route 108 and Route 100. It is designed as dual two-lane road. [3]

In San José province the route covers San José canton (Zapote, San Francisco de Dos Ríos, Uruca, Mata Redonda, Pavas, Hatillo, San Sebastián districts), Goicoechea canton (Guadalupe, Calle Blancos districts), Montes de Oca canton (San Pedro, Mercedes districts).

Initially, eight roundabouts were constructed, some of which have been modified to include elevated highways, or demolished and turned into a semaphore regulated junction.

Route and access

Starting in Uruca, the road goes through Pavas and allows the access to places like Pavas, Mata Redonda and Escazú. There are junctions with Route 1 and Route 27.

Then Hatillo district, Alajuelita canton, San Sebastián are covered by the south section of the road, with access possible to Paso Ancho and Desamparados.

The east section covers Zapote, San Pedro and Goicoechea, which allow access to Catedral district, San Francisco de Dos Ríos, Curridabat canton, Sabanilla, Guadalupe, Calle Blancos and Moravia. Access to the Route 2 is possible on this east section.

When the north arc section is finished, it will allow access to Route 32, while there is also a pending design and construction of a link to Heredia through Santo Domingo.

History

In the latter half of the 1950s, the Housing and Urbanism National Institute (INVU), together with the Ministry of Public Works and Transport (MOPT), proposed the construction of the ring road. It was designated as a public interest project. Twenty years later the project was stalled, and a foreign United States agency suggested to expand the ring to outer districts, away from the city center of San José and its central districts of Carmen, Merced, Hospital, Catedral, Zapote and Mata Redonda.

Construction started in 1979.

Roundabouts upgrades

Several of the ground level roundabouts that were originally part of this road, have been reconstructed, giving priority to the vehicular flow of the Route 39.

As of 2020 the following work is planned for the remaining roundabouts, it was designed as a single construction work by the United Nations Office for Project Services, which supervises the project:[6]

North arc

As of 2019, the ring road is incomplete, missing the 4.1-kilometer north arc between Uruca and Calle Blancos. In the first half of the 2000 decade, the MOPT expropriated some of the required residential areas, but no evictions were executed, later in 2019 a couple of industrial plots were expropriated.

The works are financed by the Central American Bank for Economic Integration and the concession was awarded to private contractor Hernán Solís–La Estrella.[10]

The construction project on the north section was split on five "functional unit" working sections, and construction started on September 11, 2017: [11]

Hatillo tunnels

In December 2018 and February 2019 was announced that the three semaphore-regulated junctions in the Hatillo district would be upgraded to tunnels for the transversal roads to improve the route flow of Route 39 which would be over the tunnels, these works are projected to be finished in 2020. These works together with the upgrade of the Guadalupe semaphore junction, and the Montes de Oca train crossing removal, would render the ring road free of any stops.[13] [14]

Train crossing in Montes de Oca

The train crossing in Montes de Oca canton, currently at ground level in Route 39, will be removed. Designs are in the planning stage

Notes and References

  1. News: Recio . Patricia . Obras para construir intersección a tres niveles en La Uruca se extenderán por 14 meses . 10 March 2020 . 10 March 2020.
  2. Web site: GeoPortal . Ministerio de Obras Públicas y Transporte de Costa Rica . 28 May 2020.
  3. Web site: Morales R . Rosa María . Carretera de Circunvalación: Antecedentes e Involucrados en el proyecto . https://web.archive.org/web/20160304105200/http://srvinternet.mopt.go.cr/centrodeinformacion/Digitalizados/Carretera-Circunvalaci%C3%B3n.pdf . dead . 4 March 2016 . MOPT . 11 September 2019.
  4. News: Recio . Patricia . Construcción de paso a desnivel en Garantías Sociales comenzaría el 14 de enero . 10 March 2020 . 19 December 2018.
  5. News: Canales . Danny . Abierto paso a desnivel en Garantías Sociales sin corte de cinta ni políticos . 14 April 2020 . 30 March 2020.
  6. Web site: Pasos a desnivel en Tres Rotondas (Garantías Sociales, La Bandera e Intersección Guadalupe) . es.
  7. News: Rojas . Pablo . ¡Adiós semáforos! Volverá la rotonda en Guadalupe . 14 April 2020 . 30 January 2020.
  8. News: Recio . Patricia . Paso a desnivel en Guadalupe costará $8 millones más . 26 April 2020.
  9. News: Cabezas . Yaslin . Así lucen los trabajos por el nuevo paso a desnivel de Guadalupe . 14 April 2020 . 14 April 2020.
  10. News: Arias . L. . Construction of northern section of Circunvalación route to begin next year . 11 September 2019.
  11. News: Inicia construcción de Circunvalación Norte. es. North loop construction started. 11 September 2017.
  12. News: Chinchilla . Daniel . Inauguran intersección de 3 niveles en La Uruca . 10 March 2020 . 10 March 2020.
  13. News: Sandí . Shirley . Desaparecerán semáforos de los Hatillos sobre la Circunvalación . 15 September 2019 . 14 February 2019.
  14. News: 3 túneles para eliminar semáforos en circunvalación . 15 September 2019 . 20 December 2018.