NAIT/Blatchford Market station is an Edmonton LRT station in Edmonton, Alberta which serves as the northern terminus of the Metro Line.[1] The station is located north of Princess Elizabeth Avenue, on the west side of the Northern Alberta Institute of Technology and Brigadier James Curry Jefferson Armoury. The station was built after a long-term comprehensive land use plan of the Edmonton City Centre Airport lands were finalized.[2] [3] [4]

NAIT station opened in 2015 at a temporary location until it was renamed and relocated approximately 200 metres northwest, to its permanent location on January 20, 2024.

History

NAIT
Type:Former station
Style:Edmonton LRT
Structure:Surface
Platform:Centre platform
Tracks:2
Bicycle:Yes
Opened:September 6, 2015
Closed:January 20, 2024
Accessible:Yes
Owned:City of Edmonton
Map State:collapsed

Preliminary engineering of the line was completed July 2009 and construction of the phase from the MacEwan station to NAIT began in the summer of 2011. The station was supposed to open in 2014.[5] However, due to delays it opened on September 6, 2015.[6]

The station was closed for four months from April 28 to August 30, 2019 due to construction on the Capital Line which shares track with southern sections of the Metro Line.[7] Because of delays that the construction caused, Edmonton Transit operated five car trains on the Metro Line. Since the NAIT station island platform was only three cars long, these larger trains were unable to fit alongside the platform, hence the temporary closure.

The new station was constructed between 2020 and late 2023.[8] The original NAIT station closed on January 20, 2024, following the opening of NAIT/Blatchford Market station on the same day.[9]

Future

In the future, the Metro Line will be extended by one station and Blatchford Gate will replace NAIT/Blatchford Market as the northern terminus of the line.

The two new stations are being constructed in response to the planned community of Blatchford, which is being built on the land of the former Edmonton City Centre Airport. The redevelopment of the old airport caused the original plan of two stations to be delayed, which resulted in the creation of a temporary station to service NAIT.[10]

Station layout

NAIT/Blatchford Market station is an outdoors at-grade station. Unlike other stations on the high floor Edmonton LRT, NAIT/Blatchford Market station was built with side platforms instead of an island one.

Around the station

Communities

Notes and References

  1. Web site: North LRT to NAIT . City of Edmonton . February 6, 2010 . dead . https://web.archive.org/web/20110616184254/http://www.edmonton.ca/transportation/ets/lrt_projects/downtown-to-nait-lrt-study.aspx . June 16, 2011 . mdy-all .
  2. Web site: North LRT Fact Sheet . February 2012 . City of Edmonton . May 30, 2012 . https://web.archive.org/web/20120601013248/http://www.edmonton.ca/transportation/NLRT_Fact_Sheet_February_2012.pdf . June 1, 2012.
  3. Web site: North LRT Stations . City of Edmonton . October 20, 2010 . dead . https://web.archive.org/web/20110616151650/http://www.edmonton.ca/transportation/ets/lrt_projects/north-lrt-stations.aspx . June 16, 2011 . mdy-all .
  4. Web site: North LRT to NAIT . City of Edmonton . February 6, 2010 . dead . https://web.archive.org/web/20110616184254/http://www.edmonton.ca/transportation/ets/lrt_projects/downtown-to-nait-lrt-study.aspx . June 16, 2011 . mdy-all .
  5. Web site: Metro Line Delay FAQ . City of Edmonton . October 8, 2014 . October 8, 2014 . dead . https://web.archive.org/web/20141013181223/http://www.edmonton.ca/transportation/MetroLineDelayFAQOct92014.pdf . October 13, 2014 . mdy-all .
  6. Web site: Ramsay. Caley. After lengthy delay, Metro Line LRT opens to riders. Global News Edmonton. September 6, 2015. September 6, 2015.
  7. Web site: City of Edmonton to suspend LRT services to NAIT campus for 4 months . Global News . March 25, 2019 . March 25, 2019 . Heidenreich . Phil.
  8. Web site: Metro Line - Northwest Extension . 2023-12-31 . City of Edmonton . en.
  9. News: Siemens . Nicole . New NAIT LRT station ahead of schedule, opening of other Blatchford stop remains unclear . January 20, 2024 . . . January 16, 2024.
  10. Web site: Blatchford Edmonton . 2023-12-31 . Blatchford . en-US.