Muyembe–Nakapiripirit Road Explained

Country:UGA
Muyembe–Nakapiripirit Road
Length Mi:92
History:Designated in 2016
Construction expected to start in 2020
Completion expected in 2023.
Direction A:South
Terminus A:Muyembe
Direction B:North
Terminus B:Nakapiripirit

Muyembe–Nakapiripirit Road is a road in the Eastern and Northern regions of Uganda. The road connects the towns of Muyembe in Bulambuli District, to the town of Nakapiripirit in Nakapiripirit District.[1]

Location

The road starts at Muyembe, approximately 35km (22miles) northeast of Mbale, the largest city in Eastern Uganda.[2] The road continues north to end at Nakapiripirit, a total distance of approximately . The coordinates of the road near Tabagonyi are 1°28'45.0"N, 34°24'56.0"E (Latitude:1.479179; Longitude:34.415548).

Upgrade to bitumen

Plans are underway to upgrade this gravel road to class II bitumen surface with road width of 7m (23feet), shoulders of 1.5m (04.9feet), with drainage channels and culverts. In December 2014, this road was listed as "At project preparation".[3]

In March 2015, the Ugandan Parliament, authorized the borrowing of US$110 million, representing 86 percent of the cost, from the Islamic Development Bank (IDB). The government of Uganda will fund the remaining 14 percent, amounting to about US$18 million or local currency equivalent.[4]

In December 2015, Uganda National Roads Authority advertised for construction companies to tender bids for the construction works, comprising 92km (57miles) of main roads and an additional 25km (16miles) of side roads and connectors, totaling 117km (73miles). Following the evaluation of those bids, a preferred contractor will be selected and a construction contract will be executed between the parties concerned.

The construction contract was awarded to a Turkish construction company, Polat Yol Yapi Sanayi ve Ticaret A.S. On 7 November 2019, the construction contract was signed between UNRA, represented by Allen Kagina, the agency's executive director and Emre Polat, representing the contractor. Work is expected to start in 2021 and conclude in 2023.[5] In November 2020, the New Vision newspaper reported that construction would begin in 2021 and last three years.[6]

In March 2022, the Nile Post, a Ugandan online publication, reported that works were ongoing, but were behind schedule. Work which began on 30 March 2020, is contractually expected to end on 30 March 2023, and then followed by one year of "defects liability period".[7]

Financing

In November 2018, the Daily Monitor newspaper reported that the Islamic Development Bank (IsDB) had committed to lend US$114.12 million while the government of Uganda will contribute $18 million in counter-funding, of which US$5 million will go towards land compensation. Construction is expected to start in 2019 and last 3 years.[1] In November 2019, it was reported that the Ugandan government had borrowed USh399 billion (US$109 million) from the IsDB to fund the upgrade of his road.[5]

See also

External links

1.4792°N 34.4156°W

Notes and References

  1. Web site: Work on Muyembe–Nakapiripirit road expected to start next year . 6 November 2018 . 6 November 2018 . . Nelson . Wesonga . Kampala.
  2. Web site: The Population of The Regions of the Republic of Uganda And All Cities And Towns of More Than 15,000 Inhabitants . 27 August 2014 . UBOS . Citypopulation.de Quoting Uganda Bureau of Statistics (UBOS) . 8 January 2016.
  3. Web site: Showbizuganda.com . 31 December 2014 . UNRA Releases 2015 Road & Bridge Projects . Denzel . Shantel . 8 January 2016 . Kampala.
  4. Web site: 8 January 2016. Kampala . Parliament Okays Shs330billion Loan for Nakapiripirit Road. 11 March 2015. Olive. Nakatudde. Uganda Radio Networ.
  5. Web site: UNRA Signs Contract For Upgrading 92km Muyembe–Nakapiripirit Road . 7 November 2019 . SofPower Uganda . 10 November 2019 . Paul Ampurire . Kampala.
  6. Web site: 26 November 2020 . Museveni Launches Muyembe–Nakapiripirit Road Construction . . Conan Businge . 30 November 2020 . Kampala.
  7. Web site: 1 March 2022 . Uganda: Works At Muyembe-Nakapiripirit Road Behind Schedule . Nile Post Uganda . Hakim Kanyere . 2 March 2022 . Kampala, Uganda . via AllAfric.com.