Mount Macdonald Tunnel | |
Status: | Active |
Crosses: | Selkirk Mountains, below Rogers Pass |
Opened: | 1988 |
Traffic: | Railway |
Character: | Primarily freight service Some passenger service (Rocky Mountaineer) |
Length: | 9.11miles |
Height: | 25feet |
Width: | 17feet (straights) 18feet (curves) |
The Mount Macdonald Tunnel is in southeastern British Columbia, on the Revelstoke–Donald segment. This single-track 9.11adj=onNaNadj=on tunnel, which carries the Canadian Pacific Kansas City (CPKC) main line under Mount Macdonald in the Selkirk Mountains, handles most westbound traffic, whereas the Connaught Tunnel handles mostly eastbound. The tunnel was opened by the Canadian Pacific Railway (CP) in 1988.
By the 1970s, it was evident that the Connaught Tunnel alone could not meet the increasing traffic demands. The major growth opportunities were primarily in the bulk commodities of coal, sulphur, and potash.In 1980, the estimated construction cost of $300 million was almost 20% of CP's gross income for 1979. Furthermore, westbound grain transportation had been an ongoing liability for the railways. Consequently, CP was unwilling to proceed with a new tunnel unless the Crow Rate, which did not cover the variable cost of grain movement, was addressed. In response, the federal government gradually increased this rate from 1983, before abandoning rate regulation in 1993.
The need for pusher locomotives was another encumbrance. During the pusher station's existence, six engineers, six maintenance workers, and nine locomotives were based at Rogers. Five-unit engines were used on heavy trains carrying grain, coal, and potash. Four-unit engines were used on other freights.[1] A significant grade improvement would eliminate the need for pushers.
To enable the reintroduction of double tracks, three schemes required a 6adj=onNaNadj=on lowering of the Connaught Tunnel floor, complemented by a new approach to serve the east portal:
However, lowering the floor would be extremely difficult while maintaining traffic flow.
Three schemes offered a straight new tunnel at a lower elevation:
Mike Wakely, Regional Engineer, Special Projects, suggested the selected option, which provided a 1.0% grade from Rogers, and a west portal 3miles west of Glacier station. The budget, including approaches, was $600 million. In 1975, preparatory work began in earnest.[2]
The 21.6adj=onNaNadj=on route of surface track and tunnels, within a 100adj=onNaNadj=on wide right-of-way, uses continuous welded rail.
Macdonald Tunnel route | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
Mile | Location | Mile | Location | Mile | Location | |||||
68.3 | Fraine | 74.5 | Gully bridge | 78.6 | Connaught Creek bridge | |||||
68.6 | Cupola Creek bridge | 75.0 | Surprise Creek culvert | 79.3 | Bear Creek | |||||
69.4 | Alder Creek culvert | 75.0 | Wakely | 79.4 | Mt. Macdonald Tunnel (E. portal) | |||||
71.3 | Mountain Creek bridge | 76.5 | Stoney Creek bridge | 84.9 | Macdonald | |||||
73.7 | Cedar Creek culvert | 77.1 | John Fox viaduct | 88.5 | Mt. Macdonald Tunnel (W. portal) | |||||
74.2 | Raspberry Creek culvert | 78.0 | 89.9 | Ross Peak |
. Connaught Track and Macdonald Track diverge; named for former Pacific Region V.P.; previously called Rogers.[3]
. Length: 130adj=onNaNadj=on; two span; double track; Cana Construction[4] completed in July 1984.
. Connaught Track had to be moved 30feet into the mountainside along this section to accommodate the new lower track.
. Length: 315adj=onNaNadj=on; 2 × 250-ton spans. Height: about 145feet below Mountain Creek bridge on Connaught Track. Cana Construction completed in fall 1985.
. A 8800adj=onNaNadj=on siding;[5] named after Mike Wakely, a former chief construction engineer, who oversaw the years of preparatory work, but retired before the work was properly underway, and died soon after, never to see the completed project.
. Length: 700feet; seven spans. Height: about 500feet below Stoney Creek bridge on Connaught Track.
. Length: 4032feet; Pitts Engineering Construction began work in 1985; 45 × 89feet steel spans, each weighing 82 tonnes; brought from Calgary via the Crowsnest Pass, because too wide for the Spiral Tunnels, and unloaded at the south end of the new Stoney Creek bridge; supported on 44 custom-designed piers and two abutments; pier heights range from 15feet to 70feet; cut and fill not adopted because it would undermine Connaught Track above, and encroach on highway below; spans installed from early 1987 to that July; walkway on north side; named after John Fox.
. Length 1.14miles.
. Length 156feet; single span; comprises a pair of 70-ton deck plate girders, offloaded near the east portal of the Connaught Tunnel, and hauled up to the highway and down to the site; Cana Construction built.
. A railway point.
. A railway point.
CP built a substation in Revelstoke and from it constructed a 35 kV operating distribution line along the railway right-of-way; originally built using both 69 kV insulators and construction standards.[6]
On August 27, 1984, the Selkirk Construction joint venture (comprising S.A. Healey, Foundation Company of Canada, and Atlas Construction) began blasting from the east portal. By mid-October, sufficient room existed to install their 22feet, 60feet tunnel-boring machine (TBM). In December 1985, the tunnel passed 360feet below the Connaught one, almost directly beneath the mountain peak. On completion, Selkirk Construction had advanced 5.25miles westward.
On October 5, 1984, the Manning-Kumagai (MK) joint venture (comprising Manning Construction and Kumagai Gumi) began from the west portal. Using the drilling and blasting method, 30 men, rostered in 3 shifts, completed 3.6miles eastward. Meanwhile, the highway was temporarily relocated to construct a 880feet reinforced concrete box in a cut-and-cover trench. This structure carries both the highway and protects the portal from avalanches. In 1985, the words "Mount Macdonald Tunnel 1988" were stamped into the concrete cladding above the portal.[7] The eastern work camp was near the Mount Shaughnessy Tunnel, and the western one at Flat Creek. A third camp for summer surface workers existed near Rogers.
Breaking through on October 24, 1986, the approaching tunnels joined. Cementation Canada sank the 28feet, 1150feet ventilation shaft. MK drilled and blasted the gate chamber below, and air tunnels to, this shaft. After concrete lining, the tunnel height is 25feet, and the width is 17feet on the straights, and 18feet on the curves. In September 1988, the final track concrete was poured. The paved concrete track (PaCT) rests on a 7feet, 9inches reinforced concrete slab. The height clearance can accommodate any future electrification.
A fleet of 50 dump cars were built exclusively for the project. About 5,000 tons of material were removed daily from the western side. Parks Canada allowed some dumping about 2.8miles from the portal, creating a bed for track twinning. The remainder was dumped outside the park boundary at various proposed double-tracking sites between Golden and Revelstoke. The 660cuyd of rubble produced daily at the eastern end was dumped into a large depression to create the grade. Minus the 156adj=onNaNadj=on bridge, this fill covered the 4386adj=onNaNadj=on distance to the Mount Shaughnessy Tunnel.
Because of the tunnel's length and lack of electrification, it uses a ventilation system consisting of a series of huge fans which clear the tunnel of diesel exhaust left behind by the locomotives. The tunnel also has large doors at the portals and the mid-point which can open and close whenever the tunnel needs to be cleared out.
The purpose of the ventilation system is to prevent locomotives overheating and remove air pollutants. The opening and closing of the gates at the portals and mid-point assists the extraction process. The mid-tunnel gate structure stands inside a 82feet, 88feet, and 52feet cavern. In a power failure, counterweights return all gates to the up position. Each gate has a central wooden panel designed to break if struck by a train. Although monitored at the Revelstoke control centre, the ventilation system is computer controlled, and adjusts to the type and size of train. Standing at the top of the shaft, near the Rogers Pass highway summit, the ventilation building houses four fans, a standby 3800adj=onNaNadj=on diesel generator, and two elevators. Used by maintenance staff, each open cage takes minutes to slowly descend an open elevator shaft to tunnel level. A straight tunnel would have made the shaft location clearly visible from the summit monument. To hide the complex, a slight kink was made in the tunnel alignment.
On November 9, 1988, the first official train travelled the Macdonald Track westward. About 535m (1,755feet) west of the west portal, R.S Allison, CP president, connected the last track clip.[8] On December 12, 1988, the first revenue train, hauling coal, passed through the tunnel, and saved an hour on the journey. The official opening of the $422 million tunnel was in May 1989.[9] The crest at the west portal is 295feet lower than the Connaught crest. The 0.7% gradient westward eliminated the need for pusher locomotives. Nowadays, locomotives can climb the grade at 20mph. Loaded coal trains travel at 9to through the tunnel. To ensure frequency vibrations do not cause damage to the track structure, the speed limit for all traffic is 30mph.[10]
CP repairs 50to of PaCT each year. Drain holes cored down to a longitudinal collector drain under the tunnel reduce failures from excessive surface water. Slab cracking, owing to insufficient lateral and longitudinal reinforcing in the PaCT slab, can be repaired with epoxy resin in minor cases. Injecting the resin restores structural integrity. Slab removal and replacement is needed in serious cases. From 1993 to 2020, a total of 378feet of PaCT were replaced in the two tunnels.
The hardware for power, communications, and signalling is obsolete. The slow ventilation systems can take 45 minutes to purge the air after each train. In 2019, consultants were advising on possible improvements, but it will probably take 5 to 10 years to modernize the tunnel.[11]
Twelfth longest railway tunnel when opened:
Seikan Tunnel (1988) (Japan) 53.852NaN2
Daishimizu Tunnel (1982) (Japan) 22.22NaN2
Simplon Tunnel (1906) (Switzerland) 19.82NaN2
Shin Kanmon Tunnel (1975) (Japan) 18.712NaN2
Apennine Base Tunnel (1934) (Italy) 18.512NaN2
Rokkō Tunnel (1972) 16.252NaN2
Furka Base Tunnel (1982) (Switzerland) 15.442NaN2
Haruna (1982) 15.352NaN2
Monte Santomarco Tunnel (1987) (Italy) 15.042NaN2
Gotthard Tunnel (1882) (Switzerland) 152NaN2
Nakayama (1982) 14.862NaN2
Mount Macdonald Tunnel (1988) 14.66km (09.11miles)
However, it took the title from the Cascade Tunnel (1929) 12.6km (07.8miles) as the longest railway tunnel in the North America. The project was the largest CP expansion of capacity since the building of the transcontinental in the early 1880s. In 2016, the tunnel was inducted into the North America Railway Hall of Fame.[12] Tunnel 4 of the Cuajone–El Sargento line in Peru is of similar length, and which is the longer of the two is disputed.
2005: While clearing ice in the tunnel, an employee died when struck by a falling 225kg (496lb) chunk.[13]
2019: An avalanche descending upon a stopped train at Wakely derailed seven container-carrying flatcars.[14]