Main Street Bridge (Columbus, Ohio) Explained

Main Street Bridge
Image Upright:1.3
Coordinates:39.9561°N -83.0066°W
Carries:
Crosses:Scioto River
Locale:Columbus, Ohio
Maint:Ohio Department of Transportation
Id:2503220
Design:inclined arch
Length:700feet
Width:about 65feet
Mainspan:400feet
Lanes:2 eastbound, 1 westbound,
1 pedestrian
Begin:2006
Complete:July 2010
Open:July 30, 2010
Mapframe-Custom:
Type:shape
Zoom:15
Point:none
Stroke-Color:
  1. 424242
Stroke-Width:1
Id:Q6736096
Mapframe-Caption:Interactive map outlining the Main Street Bridge

The Main Street Bridge in Columbus, Ohio is a, three-span, inclined tied arch bridge over the Scioto River. The bridge is the first in North America and the fifth in the world to use an inclined single-rib-tied arch superstructure.[1] [2] The final cost for the bridge was $60.1 million.[3] It carries Main Street (U.S. Route 62 and Ohio State Route 3) northwest from Downtown Columbus into Franklinton, splitting into Rich and Starling Streets just west of the bridge.

History

The original Main Street bridge was a Whipple through truss bridge built in 1890 over the Scioto River. It was lengthened in 1917 using two spans salvaged from a railroad bridge a short distance downstream of the bridge.[4] In the 1930s, it was replaced with a multiple-span, art-deco open-spandrel concrete deck arch bridge, built in 1937. After years of degradation due to weather and traffic, the bridge was deemed unfit for use and closed in 2002.[2] The 1937 bridge was part of the Scioto River Bridge Group, listed on the Columbus Register of Historic Properties in 1983 and proposed as part of the Columbus Civic Center Historic District, nominated to the National Register of Historic Places in 1988.[5]

Wanting an iconic structure to replace the old bridge, the city of Columbus contracted Dr. Spiro Pollalis, professor of design technology and management at the Harvard University Graduate School of Design to design the bridge. His design, altered slightly for budget reasons, opened for traffic on July 30, 2010.[3]

When the former bridge closed, engineers estimated that a replacement would cost approximately $19.5 million. However, by 2004, estimates climbed $29.5 million. When planners received construction bids in 2006, the lowest was $44.1 million. Cost overruns, design changes and inspections added another $10 million to the structure's final cost.[6]

Design

Arch

The original concept of the Main Street bridge was far more complex and costly than the final design. Initially, the bridge called for a very shallow 10:1 span-to-rise ratio for the main arch, creating significant axial and bending forces. To accommodate the excess forces, the design called for expensive, high-strength concrete and steel to support the bridge. Because of the high cost of materials and construction of such a span, the design of the arch was revised to a 6.6:1 span-to-rise ratio, making the main arch taller and decreasing its length from 480feet to 400feet. This design change was expected to allow for cheaper materials and save over 60000lb of steel while keeping the ten-degree incline that makes the bridge unique.[7]

Bridge deck

The bridge surface is composed of two separate decks, a 35feet wide vehicular deck carrying two lanes of eastbound traffic, one lane of westbound traffic, and a 18feet wide pedestrian deck on the opposite side of the arch from the vehicular deck and slightly elevated. While the redesign of the original concept altered the deck supports, the actual construction of the decks changed only slightly to accommodate the new design.

L-struts

The Main Street bridge also calls for thirteen L-struts, which would attach the arch to the bridge deck. Their original design used tapering geometries which were different for each strut. Creating, designing and testing thirteen distinct struts would have been cost-prohibitive, so engineers simplified the designs to reduce costs. While the aesthetics of the original design changed because of the more uniform strut design, they are similarly appealing and reduce the components' weight by over 400000lb.

Piers

The final redesign of the Main street bridge was of the piers. The original design called for two 'V-piers', formed by the convergence of the main arch and the secondary arches on either side. This design proved to be nearly impossible to make structurally sound forcing engineers to simplify the piers. To do so they created a 'crescent pier' shape, which removes the two smaller arches on either end and creates a larger pier to provide better support.

External links

Notes and References

  1. Web site: McConnell. Mollie. January 5, 2014. Main Street bridge's arch makes it unique. The Columbus Dispatch. The Dispatch Printing Company. 14 December 2014.
  2. Web site: Main Street Bridge. 2012-05-01. DowntownColumbus.com. https://web.archive.org/web/20120509154758/http://downtowncolumbus.com/home/moving-forward/main-street-bridge. 2012-05-09. dead.
  3. News: Potthoff. Gina. July 30, 2010. Main Street bridge opened to traffic. 2012-05-01 . The Columbus Dispatch. dispatch.com.
  4. Web site: Main Street Bridge (Old Truss Bridge) . Bridgehunter.com.
  5. Web site: Main Street Dam Removal & Scioto Greenways Feasibility Study. Stantec. 14-15. 2012. December 16, 2022.
  6. News: NBC 4 Digs Into Over-Budget Main Street Bridge. nbc4i. WCMH-TV. 20 May 2009. 2012-05-01. https://archive.today/20130129154814/http://www2.nbc4i.com/news/2009/may/20/nbc_4_digs_into_over-budget_main_street_bridge-ar-13643/. 29 January 2013. dead.