Mahinerangi Wind Farm Explained

Mahinerangi Wind Farm
Coordinates:-45.7606°N 169.905°W
Country:New Zealand
Location:north of Lake Mahinerangi, Otago
Status:O
Construction Began:September 2010
Cost:NZ$75 million
Owner:Mercury NZ Ltd
Ps Units Operational:12
Ps Units Manu Model:Vestas

V90-3MW

Wind Rotor Diameter:900NaN0
Wind Rated Speed:150NaN0
Wind Farm Type:Onshore
Ps Site Elevation:600-
Wind Site Usage:Farming
Ps Site Area:17.232NaN2
Ps Electrical Capacity:36 MW
Planned: 200 MW
Ps Annual Generation:101 GWh (stage 1)

The Mahinerangi Wind Farm is a wind farm on the north side of Lake Mahinerangi, around 50 km west of Dunedin, in Otago, New Zealand. Stage one of the wind farm, generating 36 MW, was commissioned in March 2011, and an additional 160 MW is consented to be commissioned in further stages.

The wind farm is owned and operated by Mercury NZ Ltd. It was the second major wind farm to be built in the South Island.

History

Resource consent was granted in 2007[1] and later confirmed after an appeal to the Environment Court.[2]

Construction of stage 1 of the wind farm, consisting of twelve turbines, began in September 2010.[3] Vestas V90-3MW turbines were chosen for the wind farm, having previously been used for stage 3 of Tararua Wind Farm in 2007. Turbines were shipped to Port Chalmers, and trucked through Dunedin to their final site.

The wind farm generated its first electricity on 21 February 2011, with the first two turbines being commissioned.[4] All twelve stage one turbines were completed and generating electricity by the end of March 2011.[5] [6]

Location

The wind farm will be contained within 17.23km2 of land at an elevation of 600 to 730 metres above sea level and about 50 kilometres west of Dunedin.[7] Most of the land in the proposed site is pasture grazed by sheep and cattle.[8]

Stage 2

Stage 2 at Mahinerangi is proposed for up to 100 wind turbines producing 160MW and an annual output of over 600GWh. Resource consents were granted in 2009.[9]

Transmission

Electricity generated from Stage 1 turbines is injected into the nearby Deep Stream and Waipori hydro schemes. This utilised the existing 33kV transmission line and avoided the cost of additional transmission infrastructure. Electricity from Stage 1 and the hydro schemes is then injected into either Dunedin's local distribution network, or into Transpower's Halfway Bush-Balclutha-Gore 110 kV line at Berwick.

Stage 2 and beyond is too large to inject into the Waipori/Deep Stream system. Instead, it will inject into Transpower's Halfway Bush-Roxburgh 110 kV line, which passes a short distance south of the wind farm.

See also

External links

Notes and References

  1. News: TrustPower Welcomes Mahinerangi Wind Farm Decision. 2007-10-01. Scoop.
  2. News: Mahinerangi wind farm passes court hurdle . 22 December 2008 . . . 19 October 2011.
  3. Web site: Mahinerangi Wind Farm Project Community Meeting Progress Booklet . 15 December 2010. 2011-01-23.
  4. Web site: Mahinerangi Windfarm up and in action . Channel 9 Dunedin. 21 February 2011. 21 February 2011.
  5. Web site: DUNEDIN'S NEWEST WIND FARM OPEN TO THE PUBLIC . TrustPower . 5 April 2011.
  6. Web site: Mahinerangi Wind Farm Stage 1. Tilt Renewables. 24 June 2018.
  7. http://trustpower.co.nz/Content/Generation/WindFarms/Mahinerangi.aspx TrustPower
  8. http://trustpower.co.nz/Content/Generation/WindFarms/VolumeI.aspx TrustPower
  9. Web site: Mahinerangi Wind Farm Stage 2. Tilt Renewables. 24 June 2018.