MV Glen Sannox (2017) explained

MV Glen Sannox is a dual-fuel car and passenger ferry constructed at Ferguson Marine in Port Glasgow for CMAL to lease to Caledonian MacBrayne, planned to serve the Ardrossan to Brodick crossing. On 1 June 2017 her name was chosen from a shortlist by public ballot and recalls an earlier Arran ferry.[1]

The ship is to be the first of two Scottish ferries capable of operating on either marine gas oil or LNG, offering benefits of a marked reduction in carbon dioxide, sulphur and nitrous oxide emissions. Ferguson Marine was announced as preferred tenderer on 31 August 2015.[2] Initially expected to enter service in summer 2018, the ship only began its sea trials in February 2024.[3] [4] It has been the subject of continuing political scandal known as the "ferry fiasco" regarding increased costs and lengthy delays.[5] [6] [7]

Ferguson Marine (FMEL) was a new company, formed in September 2014 when Jim McColl rescued the shipyard from bankruptcy. The industry standard design and build fixed price contract required a bank-backed guarantee to protect interim payments, and give the builder an incentive to meet contract times and quality standards. When FMEL revealed that they could not provide this warranty, Scottish Government ministers decided to take the risks which were set out in a paper by CMAL. Defective work had to be redone, causing delays. In July 2017, FMEL claimed £17.5 million for additional costs. CMAL dismissed the claim as not valid, but delays and claims increased.The ship's launch was delayed to 21 November 2017, with it then expected to begin operation in late 2018 or early 2019.[8] The dispute escalated, in August 2019, FMEL went into administration, having been paid £83.25 million in contract payments, and £45 million in loan payments from the Scottish Government. The shipyard was then nationalised, and renamed Ferguson Marine (Port Glasgow) Ltd. Further delays were announced, some due to complications with the vessel's LNG powerplants,[9] [10] and as of August 2024 handover was expected to take place before the end of September 2024.[11]

History

See also: Ferry fiasco. The State-owned enterprise CalMac, originally Caledonian MacBrayne Ltd, was formed in 1973 as a vessel owner and operator providing most of the ferry services to the Firth of Clyde and the Hebridean islands off the west coast of Scotland. In 2006, its roles were split to satisfy EU competition rules. As Caledonian Maritime Assets (CMAL) it continued to own the Caledonian MacBrayne fleet and order new ships, while CalMac Ferries Ltd (CalMac) was created as a separate company which successfully bid in open competitive tender for the contract to operate the services. Many of CalMac's ferries had been built by Ferguson Shipbuilders, which five years earlier had employed 300 people, but it had struggled to compete and CalMac orders were won by the Remontowa shipyard in Gdańsk, Poland.[12] [13] In 2011 Fergusons successfully bid for two small ships for CMAL, funded by the Scottish Government's Low Emissions Hybrid Ferries project.[14]

Ferries Plan

The Scottish Government's Ferries Plan, which its executive agency Transport Scotland published in December 2012,[15] included indicative proposals for two new major vessels.[16] International emissions regulations tightened, and cleaner liquefied natural gas (LNG) fuel was adopted by ferry operators in Northern Europe,[17] particularly Norway. The Danish island of Samsø invited tenders for the first in the EU, and in June 2013 Remontowa was awarded the contract for this dual-fuel ferry, to be delivered in October 2014.[18] David MacBrayne Ltd bid to operate a ferry connecting Gotland in Sweden, with detailed proposals drawn up by CalMac, but in May 2014 this bid was reported unsuccessful.[19]

To prepare the Vessel Replacement and Deployment Plan (VRDP), Transport Scotland held tripartite monthly meetings with CMAL and CalMac, starting in October 2013. By agreement, CalMac led development of programmes for the major vessels.[20] In early July 2014 the Scottish Government, using CalMac's initial analytical work, authorised the procurement of two new major ferries, aiming to name the preferred bidder in nine months. CMAL's head of vessels said then that this timetable was a "hugely challenging". It left CalMac only three weeks to produce its Specification of Technical and Operational Requirements. They quickly adapted work done for the Gotland ferry bid, but made some errors such as including irrelevant description of passenger cabins. The exceptionally large and detailed specification now had to be made more concise as part of CMAL's tender documents.

Ferguson Shipbuilders had been struggling to get orders. Cash flow problems, and difficulties in arranging financial bonds (or refund guarantees) left it unable to bid for several major contracts. The workforce was reduced to 77, then on 15 August 2014, a month before the Scottish independence referendum, the yard went bankrupt,[21] [22] and the administrators KPMG immediately laid off 70 workers.[23] The First Minister of Scotland, Alex Salmond of the SNP, personally intervened and persuaded businessman Jim McColl, one of his Council of Economic Advisers, to buy out the shipyard.[24] McColl's Clyde Blowers Capital, previously deterred by the yard's debts, now took over its assets and business,[25] and formed Ferguson Marine Engineering Ltd. (FMEL) as a new subsidiary. On 30 September Deputy First Minister Nicola Sturgeon announced that FMEL had been given the order for a third hybrid ferry. Government ministers had given CMAL a letter of comfort allowing this contract to go ahead without a refund guarantee.[26]

CMAL's draft specification was disputed by CalMac, who said on 14 October that it only met 20% of their requirements. The compromise eventually specified in the tender documents meant wider ships which would need improvements to ports.

Vessel procurement process

The start of the vessel procurement process was publicly announced on 15 October 2014 by the Transport Minister Keith Brown. The pre-qualifying questionnaire (PQQ), issued by CMAL on 17 October,[27] invited shipbuilders to demonstrate their capability for detailed design, construction, testing, and delivery of two 100 metres long ROPAX ferries.[28] [29] The questionnaire emphasised the requirement for Bank Refund Guarantee bonds before work started, and requested evidence from a bank confirming its willingness to provide these guarantees.[30] [31] Following discussion with CMAL, FMEL said on 9 December that guarantees from its parent company Clyde Blowers Capital (CBC) would be inappropriate, so it intended to provide Bank Guarantees and would "endeavour to provide Guarantees to levels that provide the security you require."

Of the six shipbuilders shortlisted for the invitation to tender (ITT), only Remontowa had built a dual-fuel LNG engined ferry.[32] [33] The ITT included a 135-page "Specification of Operational and Technical Requirements" (SoR) for the vessels, which were to be dual-fuel LNG engined. Under the industry standard BIMCO design and build New Build Contract, shipyards bid a fixed price to take responsibility for designing and building ships to meet the specification, and the full risk for this remains with the builder throughout the construction period. Bidders were required to accept the terms of the draft contract included with the ITT, or provide comments and/or propose amendments to this draft.[34]

The ITT, issued on 10 December 2014, required refund guarantees on behalf of the Builder by "a first class international bank". FMEL wrote that they had no comment to make "at this time". When FMEL told local MSP Stuart McMillan that they could not provide these guarantees, he wrote to the deputy first minister John Swinney. In early February 2015 transport minister Derek Mackay responded; "While CMAL's board in line with standard industry practice has a preference for refund guarantees it has on occasion taken alternative approaches to ensure that ship yards, including Ferguson under its previous owners, were not excluded from bidding for those government contracts." This letter was taken by McColl as suggesting that "alternative approaches were acceptable. On this basis FMEL proceeded with the tender." CMAL say they had "no awareness of, or involvement in, these exchanges."[35] Tenders were submitted by 31 March 2015, then evaluated on cost and quality by CMAL with assistance of a consultant naval architect. CalMac gave technical input. The FMEL design was heavy, with large engines, and the two ship contracts totalled £109.8m. Their bid mentioned a lighter version, on 17 May the consultant asked for details, enabling FMEL to price each ship contract at £50.25m, eventually negotiated down to £48.5m each, a total of £97m.[36] The assessment placed the Remontowa bid second, FMEL's was "the highest quality bid received but also the highest price. Taken together, the FMEL tender achieved the highest overall evaluation score". On 20 August the Transport Scotland Ferries Unit wrote asking the transport minister to approve in principle award of the contracts by CMAL before the tenders expired on 31 August.

Transport Scotland (TS) told CMAL on 21 August that FMEL would be named as preferred bidder at the end of the month. Also on 21 August, FMEL's lawyers said that refund guarantees could not be arranged by CBC, and instead proposed guarantees from its subsidiary, the holding company Ferguson Marine Engineering (Holdings) Limited, but CMAL required independent refund guarantees as specified. Negotiations were far from concluded, and CMAL told TS that announcing the preferred bidder would "materially reduce their negotiating hand"; TS offered CMAL a letter of comfort if needed. On 31 August, First Minister Nicola Sturgeon visited the shipyard and named FMEL as preferred tenderer for the £97m contract, MacKay said it was for dual-fuel ferries, "allowing them to use cleaner fuel and future-proofing them for the advent of tighter regulations around sulphur emissions." Erik Østergaard, Chair of CMAL, said "Subject to agreement on all points, we hope to be in a position to finalise the award of the contract later in September."[37]

CMAL understood that government ministers wanted the ferries built in Scotland by FMEL, but on 25 September the CMAL board considered there were "too many risks involved around the refund guarantee matter which are still to be resolved and to that end the Board are not in a position to award the contract to FMEL at this stage." Next day, Østergaard emailed TS that CMAL could not recommend the level of unsecured risk, and proposed rejecting the deal; putting the project on hold, or "re-opening the contract negotiations with Remontowa (with whom we have a track record of doing business) or even a second yard in parallel while continuing negotiations with FMEL." Initially FMEL proposed an unusually small final milestone instalment, reducing their incentive to complete, but on 29 September they increased it to 25%, which with insurance backed guarantee coverage at 25% left CMAL at risk for around half of payments made pre-delivery. CMAL produced a paper setting out the risks. On 9 October TS confirmed that Scottish ministers had noted and accepted the risks and, as CMAL's sole shareholder, approved award of the contracts. Ministers approved £10.6m loan funding to CMAL, with special provisions to protect against the risks and repayments only due after completed ferries were in service. MacKay and Swinney signed off on the contract, and on 16 October contracts were signed between CMAL and FMEL, which MacKay publicly announced that day at the SNP's annual conference in Aberdeen.[38]

In its 2022 report, Audit Scotland said the Builder’s Refund Guarantee (BRG) is "an integral part of shipbuilding contract and is the main source of financial security for a ship buyer", giving the shipbuilder "a significant incentive to build a quality product as the buyer can cancel the contract and claim a full refund of all payments if the ship does not meet its required specification." The contract "places full responsibility and risk for the design and build of the vessels with the shipbuilder and does not allow the buyer to intervene in the running of the project." The lack of a full refund guarantee transferred some of the risk from FMEL to CMAL, so "the contract was not effective when problems emerged."

Construction – Ferguson Marine Engineering Ltd.

The build strategy of Ferguson Marine Engineering Ltd. (FMEL) was to construct vessels 801 (Glen Sannox) and 802 (Glen Rosa) concurrently until they were ready for launch, then complete work on 801 (for May 2018 delivery) before focussing on 802 (for July 2018 delivery). Their dates programme and schedule for payments, initially drafted on 21 August 2015, included 15 milestone events and payments for each vessel to aid their cash flow, rather than the usual five or six. CMAL agreed to this. The contract, signed on 16 October, required the shipbuilder to provide CMAL with detailed drawings and plans 30 days before construction started, and FMEL’s project plan allowed three months to design the relevant hull section, but the agreed milestone schedule had 15 December 2015 as the start of cutting steel. Around then, CMAL informed TS of delays by FMEL in organising work.[39] Catriona occupied the slipway until its launch on 11 December. A workshop bay was demolished, and the old brick office building was demolished before work on the new large prefabrication shed from May to August 2016. New offices were then built nearer the main road. CMAL reported that this redevelopment reduced the available space and hampered concurrent work on both vessels, but FMEL later attributed the delays to CMAL.

To mark the start of construction, the first steel for both vessels was cut on 16 February 2016 at a ceremony attended by transport minister Derek Mackay.[40] [41] Problems increased as FMEL did construction work "at risk", without approval of drawings by CMAL, and without regulation approvals required by the classification society (Lloyd's Register) and the Flag Authority (MCA). Delays built up as incorrect work had to be re-done. TS informed Scottish ministers that the vessels were likely to be late, CMAL said it had cash flow problems due to contract problems and was assisted by accelerated payments and a loan. The vessel's bulbous bow was rough rather than smooth, and condemned by Lloyd's as not fit for purpose, but left uncorrected at the time of the launch. Glen Sannox was launched on 21 November 2017 by the then First Minister Nicola Sturgeon, but was substantially incomplete at the time. The bridge (and other) windows were painted on, and the funnels were not operational, but only for show for the launch.[42] [43] [44]

In July, FMEL had claimed £17.5 million for additional costs, CMAL argued that the claim was not valid, but the amount claimed was increased. In August 2018, new Cabinet Secretary for Transport Michael Matheson said it had been confirmed that the ship was to be delivered in June 2019, followed by two months of crew familiarisation and sea trials.[45] CMAL took legal advice, and completely rejected the claim in March 2019, but FMEL did not contest this in court. The Scottish Government commissioned an independent view in May 2019, and concluded in June 2019 that there was no legal basis for CMAL to pay more than the £97 million fixed price for the contract. In August 2019, FMEL went into administration. By then, FMEL had been paid £83.25 million in contract payments, and £45 million in loan payments from the Scottish Government.

Construction – Ferguson Marine (Port Glasgow) Ltd.

On 16 August 2019 Derek Mackay, now the finance and economy secretary, announced a nationalisation plan to take the shipyard into public ownership.[46] [47] A commercial transaction nationalising the shipyard was completed on 2 December 2019, making it a new business named Ferguson Marine (Port Glasgow) Ltd., with marine engineer Tim Hair appointed as turnaround director.[48]

A report issued on 9 December 2019 estimated that, with good progress, Glen Sannox would be handed over to Caledonian Maritime Assets Ltd (CMAL) in the last quarter of 2021, and that completing the two ferries was likely to increase the total cost to over £207 million. In April 2020, Ferguson Marine (FMPG) contracted with International Contract Engineering, a marine design consultant, to revise the design and outfitting of Glen Sannox in advance of her eventual delivery.[49]

On 10 August 2020, tugs moved Glen Sannox to the Garvel dry dock in Greenock for remedial work including replacement of the bulbous bow, paintwork repair and removal of marine growth.[50] After additional work, the ship returned to the Fergusons shipyard in Port Glasgow on 9 September 2020.[51]

In October 2022, FMPG announced that Glen Sannox would initially operate only on marine gas oil, as vacuum sensors required for the LNG system were not available.[52]

Further delays to both ferries and increasing costs of £250 million, subsequently rising to £340 million by September 2022, have resulted in controversy surrounding the contract and the lack of transparency in the decision-making process.[53] [54] The Scottish Government announced that key documents relating to the decision-making process had gone missing.[55] In September 2023, a failed safety audit meant that MV Glen Sannox was further delayed: among other issues, the Maritime and Coastguard Agency (MCA) insisted on the installation of additional staircases as a condition of approving a safety audit. The work meant that planned sea trials of the Glen Sannox were delayed until the first quarter of 2024, raising doubts over whether the ship will be available for the start of the 2024 summer season.[56] Meeting MCA safety regulations ultimately meant that the passenger capacity of both ferries had to be cut from a planned 1,000 to 852. The ship began manufacturer's sea trials on 13 February 2024.[4] In June 2024 a delivery date of 19 August 2024 was announced,[10] however this was later put back, with handover now expected to take place before the end of September 2024.[11] On 18 July the Deputy First Minister of Scotland, Kate Forbes, visited the shipyard to announce plans for Ferguson Marine, and was shown round Glen Sannox at Inchgreen Quay.[57]

LNG and port infrastructure

Marine diesel oil is relatively cheap but very polluting, marine gas oil is cleaner but more expensive. Liquefied natural gas (LNG) is the cleanest burning fossil fuel, with around 20% lower emissions than marine gas oil.[58] LNG is currently shipped to the Grain LNG Terminal in Kent, then taken by road tankers to five off-grid networks in Scotland, including Stornoway, Oban and Campbelltown. In this way, LNG (from Qatar) is to be brought to Troon and Ardrossan for the ferries.[59] On 24 May 2023, CalMac awarded Molgas Energy UK Ltd the contract to supply and deliver the LNG to the new ferries.[60]

Service

Glen Sannox is being built for the Ardrossan to Brodick crossing. She was originally intended to serve as a running mate to on the Ardrossan–Brodick and the Ardrossan–Campbeltown crossings.[61] [62] In May 2023, it was announced that Glen Sannoxs sister vessel,, would also serve the Arran route.[63] However, the two new Arran ferries will initially be operating between Troon and Brodick for the first two or three years of their career, due to the planned upgrade works for Ardrossan harbour.[64]

Notes and References

  1. Web site: CMAL announces name of first LNG ferry . CMAL . 1 June 2017 . 24 June 2017.
  2. Web site: Caledonian Maritime Assets Limited- announces Scottish shipbuilder as preferred tenderer for two large ferries contract . CMAL . 31 August 2015 . 24 June 2017.
  3. Web site: New CalMac ferry sets sail in first sea trial after six year delay . STV News . 13 February 2024 . 15 February 2024.
  4. Web site: Long-delayed Ferguson ferry Glen Sannox begins sea trials . 13 February 2024 . BBC News . 13 February 2024.
  5. Web site: Costs double on delayed CalMac ferry contract . 18 December 2019 . BBC News . 14 January 2020.
  6. Web site: Ferguson Marine update . 18 December 2019 . Scottish Government . 14 January 2020.
  7. News: Completion of CalMac ferries delayed six months . BBC News . 25 August 2020.
  8. Web site: Ferry MV Glen Sannox ready for launch at Port Glasgow yard . Greenock Telegraph . 19 November 2017 . 23 November 2017.
  9. Web site: Update to NZET Committee 19 April 2024 . 2024-04-20 . Ferguson Marine . en.
  10. Web site: Ferry delivery faces short delay but latest costs on track . 2024-06-28 . BBC News . en.
  11. Web site: New Delivery Delay for CalMac Ferry Glen Sannox. BBC News. 2 August 2024. 5 August 2024.
  12. Web site: Ten things we learned about Scotland's ferry fiasco . BBC News . 27 September 2022 . 7 April 2024.
  13. Web site: Shipbuilder clinches £17m contract . BBC News . 5 October 2000 . 16 March 2020.
  14. Web site: Low Emissions Hybrid Ferries project . SAFETY4SEA . 4 November 2011 . 8 April 2024.
  15. Web site: Scottish Ferry Services: Ferries Plan (2013-2022) . Transport Scotland . 26 March 2024 . 12 April 2024.
  16. Web site: Ferguson Marine: key documents . gov.scot . 18 December 2019 . 12 April 2024.
    20 August 2015 email from: Transport Scotland Ferries Unit, re Minister for Transport and Islands.
  17. Web site: Ferry deal set to create new jobs . CMAL Caledonian Maritime Assets Ltd . 31 August 2015 . 16 April 2024.
  18. Web site: Denmark soon to get its very first LNG-fuelled domestic ferry . Skipsrevyen forsiden . 27 June 2013 . nb . 12 April 2024.
  19. Web site: Ross . David . CalMac bid to run European ferries . The Herald . 3 May 2014 . 12 April 2024.
  20. Web site: Vessel Replacement and Deployment Plan 2014 report (VRDP). Transport Scotland . 2 October 2015 . 14 April 2024.
  21. Web site: Monaghan . Angela . Scotland's last commercial shipyard Ferguson Shipbuilders set to close . the Guardian . 15 August 2014 . 3 May 2024.
  22. Web site: Harrison . Jody . Threatened shipyard wins ferry contract after buyout . The Herald . 30 September 2014 . 3 May 2024.
  23. Web site: Ferguson shipbuilder in Port Glasgow goes into administration . BBC News . 15 August 2014 . 17 May 2024.
  24. Web site: Watson . Calum . Ferguson ferries deal awarded without financial safeguards . BBC News . 23 March 2022 . 3 May 2024.
  25. Web site: McConnell . Ian . Ferguson: Jim McColl named as preferred bidder to save shipyard . The Herald . 25 August 2014 . 3 May 2024.
  26. Web site: Williams . Martin . Revealed: Ministers intervened to give another contract to ferry fiasco firm Ferguson Marine in new 'rigging' row . The Herald . 2 October 2022 . 12 May 2024.
  27. Web site: New Vessels for the Clyde and Hebrides Submission CMAL – Response on behalf of CMAL to the Public Audit Committee . Scottish Parliament Website . 12 August 2022 . 15 May 2024.
  28. Web site: View Notice, CMAL0060 Design and Build of 100 metre Vessels, ref. OCT189406 . Public Contracts Scotland . 15 October 2014 . 23 June 2024.
  29. Web site: Supplier Development Programme, Standard Pre-Qualifying Questionnaire . 15 May 2024. Buyers use a PQQ to assess the resources and capability of suppliers who express interest in a contract opportunity ... The intention of this stage of the procurement process is to identify the suppliers who are most capable of performing the contract..
  30. Web site: Statement from CMAL in response to BBC Disclosure programme . CMAL Caledonian Maritime Assets Ltd . 27 September 2022 . 15 May 2024.
  31. Web site: Lawyer's Scottish ferries deal report finds no evidence of fraud . BBC News . 18 October 2023 . 12 May 2024.
  32. Web site: Watson . Calum . Were Scotland's new gas-powered ferries a bad choice? . BBC News . 19 April 2024 . 3 July 2024.
  33. Web site: Landowski . Grzegorz . The first LNG fuelled ferry sails domestic route within EU . Poland at Sea, maritime economy portal . 15 February 2015 . 2 July 2024.
    Web site: Princess Isabella Baptises Ferry in Samsø . The Royal Forums . 7 June 2015 . 2 July 2024.
    Web site: M/F Prinsesse Isabella . YouTube . 6 March 2024 . 2 July 2024.
  34. Web site: New vessels for the Clyde and Hebrides, Arrangements to deliver vessels 801 and 802 . . 23 March 2022 . 25 June 2024.
  35. Web site: Williams . Martin . Revealed: Transport minister told tycoon contract refund pledges were not essential in Scots ferry scandal . The Herald . 17 May 2022 . 12 May 2024.
  36. Web site: Disclosure . BBC . KC’s ferries report: What questions remain? . BBC News . 2 November 2023 . 17 May 2024.
  37. Web site: Swindon . Peter . Ferguson's shipyard wins £97m ferry contract . The Herald . 31 August 2015 . 8 June 2024.
  38. Web site: £97m contract for Ferguson's shipyard . BBC News . 16 October 2015 . 9 June 2024.
  39. Web site: Construction and procurement of ferry vessels in Scotland – Summary of conclusions and recommendations . Scottish Parliament Reports, Rural Economy and Connectivity Committee (RECC) . 9 December 2020 . 30 June 2024.
  40. Web site: MV Glen Sannox & MV Glen Rosa: 102m dual fuel ferries – updates. CMAL Caledonian Maritime Assets Ltd . 19 April 2024 . 30 June 2024.
  41. Web site: First steel cut in construction of new ferries on the Clyde . STV News . 16 February 2016 . 30 June 2024.
  42. Web site: In Pictures -- Launch Of Ferry Glen Sannox At Port Glasgow . Inverclyde Now . 21 November 2017 . 26 August 2020.
  43. Web site: Swindon . Peter . 8 September 2019 . First Minister launched new Arran ferry at Ferguson shipyard with painted-on 'windows' . 12 March 2021 . Sunday Post.
  44. Web site: Grossman . David . 6 August 2021 . Scotland's Ferry Fiasco: What went wrong? . 7 August 2021 . BBC Newsnight.
  45. Web site: Fisher . Paul . 15 August 2018 . New Arran Ferry set to launch next June - government confirms . 15 August 2018 . Ardrossan Herald.
  46. News: Fraser . Douglas . 18 August 2019 . Shipyard forecast: Sunshine becoming misty . BBC News . 20 August 2019.
  47. Web site: Fraser . Douglas . 24 June 2021 . Delivery date for overdue ferries slips again . 7 August 2021 . BBC News.
  48. Web site: Ferguson Marine update . gov.scot . 18 December 2019 . 22 August 2024.
  49. Web site: Charting a New Course for Scottish Ferry Project . The Motorship . 6 April 2020 . 11 April 2020.
  50. News: Clyde Shipping - Dry Dock Work For MV Glen Sannox Is 'Major Step' Forward . Inverclyde Now . 10 August 2020 . 11 August 2020.
  51. Web site: Ferry Returns To Shipyard After Dry Dock Work . Inverclyde Now . 9 September 2020 . 9 September 2020.
  52. News: New fault means environmentally friendly Scots fiasco ferry cannot initially run green . . 29 October 2022 . 30 October 2022.
  53. Web site: Nicola Sturgeon: Buck stops with me over ferry contract row . BBC News . 24 March 2022 . 25 April 2022.
  54. News: Cost to taxpayer of Scotland's ferry fiasco soars to nearly £340m . HeraldScotland . en.
  55. Web site: Bol . David . Sturgeon denies 'cover-up' over missing key ferries contract document . HeraldScotland . 22 April 2022 . 25 April 2022.
  56. News: Concern over whether Scots ferry fiasco vessel will set sail after safety audit fail . The Herald . 12 September 2023.
  57. Web site: Sullivan . Joe . Kate Forbes 'optimistic' about Ferguson Marine's future amid £14.2m cash injection . The National . 18 July 2024 . 16 August 2024.,
    Ship's bridge, outlook over Inchgreen Quay to Ladyburn Business Centre, Greenock.
  58. Web site: Liquefied natural gas (LNG) for vessels 801 and 802: FOI release . gov.scot . 11 January 2022 . 4 July 2024.
  59. Web site: Customer FAQs . CalMac Ferries . 4 July 2024.
  60. Web site: CalMac award of LNG supply tender . CalMac Ferries . 4 July 2024.
  61. Web site: Costs double on delayed CalMac ferry contract . 18 December 2019 . BBC News . 14 January 2020.
  62. Web site: Ferguson Marine update . 18 December 2019 . Scottish Government . 14 January 2020.
  63. Web site: Competition Launched to Name Dual Fuel Ferry . 2 August 2023 . 2 August 2023 . Caledonian Maritime Assets Ltd (CMAL).
  64. Web site: Ardrossan Harbour redevelopment. North Ayrshire Council. 1 September 2023.