North–South Line (Jakarta MRT) explained

Native Name:Lin Utara–Selatan
Type:Rapid transit
System:Jakarta MRT
Status:Operational (Phase 1)
Under Construction (Phase 2A)
Locale:Jakarta, Indonesia
Start:Lebak Bulus
End:Bundaran HI
Stations:13
Routes:1
Planopen:2028 (Phase 2A)
2032 (Phase 2B)
Open: (Phase 1)
Character:Elevated
Underground
Stock:16 six-car MRTJ 1000 series trainsets
Electrification:1,500 V DC overhead catenary
Speed:limit of 100km/h
Map State:collapsed
Depot:Lebak Bulus
Ancol Barat (future)

The North–South line is a rapid transit line of the Jakarta MRT. Coloured dark red on the map, the line is currently long and serves 13 stations. It is the first line and only operational line of the Jakarta MRT. The line is the second rail transit system to be operated in the country, after Palembang LRT.

History

Development

The developing of the first line of the Jakarta MRT began when President Susilo Bambang Yudhoyono designated the system as a national project. On 28 November 2006, the first loan agreement was signed with the Japan International Cooperation Agency (JICA, then Japan Bank for International Cooperation or JBIC) for the project. The agreement includes study funding and construction work funding for the first line of the system.[1] [2] [3]

Phase 1

A total of eight contracts were awarded.

On 1 June 2013, the first three civil contracts for the underground section were signed. Three civil engineering contracts for the elevated section were signed in the third quarter of 2013. Construction work began in October 2013.[4]

Tunnelling was completed on 23 February 2017, meeting the target completion date.[5] By October 2017, the construction of both elevated and underground line sections were completed.[6]

Ahead of its official opening, a limited public trial run was conducted from 12 March 2019 to 23 March 2019. The official opening ceremony was held on 24 March 2019 by President Joko Widodo.[7] [8]

Phase 2

A total of eight contracts were put up.

Groundbreaking for Phase 2 was initially planned to begin on 19 December 2018. However, due to land acquisition issues, it was pushed back to January 2019. On 30 January 2019, President Director of PT MRT Jakarta, William Sabandar announced that the groundbreaking ceremony is delayed again as the State Secretariat has yet to issue a land-use permit for the area near Medan Merdeka.[9] The groundbreaking ceremony for Phase 2 was finally held on 24 March 2019 and advanced works began in June 2019 near the future Monas station.[10]

Site works for contract CP201 were originally planned to begin in March 2020. However, due to the COVID-19 pandemic, it was pushed back three months, to June 2020.[11] Site works for contract CP203 began in September 2021.[12] Site works for CP202 began in August 2022, after multiple delays in securing a bidder.[13] Phase 2A will commence operations in 2028, and Phase 2B will follow suit four years later.[14]

Funding

The Phase 1 was funded through soft loans by the JBIC, which now has merged to JICA. The loan tenor is 30 years and a grace period of 10 years. The first payment is made 10 years after signing the agreement. Payments last up to 30 years afterward with an interest rate of 0.25% per annum.[15]

Meanwhile, phase II is funded by a loan with a similar scheme by JICA but with a tenor of 40 years. The first payment is made 10 years after signing the agreement. The interest charged is 0.1% on the first stage of payment. This funding also includes part of the funding for phase I due to budget shortfalls, one of which is used to implement updated government regulations on preventing the impact of earthquakes. The debt payment burden is divided into 49% by the Jakarta Provincial Government and 51% by the Directorate General of Railways.[16]

Network

Route

The North–South line connects the Lebak Bulus region in South Jakarta with Ancol in North Jakarta. For now, only the section between Lebak Bulus Station and Bundaran Hotel Indonesia Station is operational. This line serves at least 13 stations with seven elevated stations and six underground stations. The elevated structure stretches for approximately from Lebak Bulus Station to ASEAN Station. The underground line stretches for approximately from Senayan Station to Bundaran HI Station. The transition between elevated and underground lines is located between ASEAN Station and Senayan Station. This line is planned to intersect with the East–West Line at Thamrin Station.[17]

Stations

The stations on the north–south line are generally uniformly designed. With the exception of Block M station, all stations have two tracks.[18]

The stations also have a number of supporting facilities, such as free WiFi and disabled-friendly toilets. In the concourse area, there are ATMs and various retail kiosks. In addition, there is also a nursing room and a prayer room.[19] [20] Each station is equipped with a flood barrier, so it is ensured that all stations on the north-south line are flood-free.[21]

It is also planned that each station will be connected to a transit-oriented development area. One of them is the Dukuh Atas Station, which is connected to the KRL Commuterline and Soekarno–Hatta Airport Rail Link through the Dukuh Atas TOD. In addition, there are transit-oriented areas at Istora Senayan Station, Blok M, ASEAN, Fatmawati, and Lebak Bulus. The development of the TODs can take the form of building public facilities and housing around the station, as well as improving access to other modes of transportation.[22] [23]

List of stations

RegionNumber Station NameTransfers/NotesElevation
Phase 2B (planned, operational by 2032)
North JakartaAncol Ancol (planned)Underground
Mangga Dua Kampung Bandan (planned) Mangga Dua (planned)
Phase 2A (under construction, operational by 2028)
West JakartaKotaFuture Phase 2A terminus Jakarta Kota (under construction)

Kota (under construction)

Underground
Glodok Glodok (under construction)
Mangga Besar Mangga Besar (under construction)
Central Jakarta Sawah Besar Sawah Besar (under construction)
Harmoni Harmoni (under construction)
Phase 2A (under construction, operational by 2027)
Central Jakarta Monas Monas (under construction)Underground
ThamrinPlanned interchange station to Kebon Sirih (under construction)
Phase 1
Central JakartaBundaran HIPhase 1 terminus Bundaran HI AstraUnderground
Dukuh Atas BNI Sudirman

BNI City

Dukuh Atas

Galunggung

Setiabudi Astra
Bendungan Hilir
Istora Mandiri Polda Metro Jaya
Senayan Mastercard Bundaran Senayan
South JakartaASEAN[24] Initially named 'Sisingamangaraja'

Masjid Agung

ASEAN

Kejaksaan Agung

CSW 1

Elevated
Blok M BCA Blok M

Blok M Bus Terminal (via short walk)

Blok A
Haji Nawi
Cipete Raya
Fatmawati IndomaretPlanned interchange station to
Lebak Bulus GrabTerminal station Lebak Bulus

Lebak Bulus Bus Terminal (via short walk)

Rolling stock

See main article: MRTJ 1000 series. The North–South line of the Jakarta MRT uses a fleet made by the Nippon Sharyo consortium from Japan which and known as "Ratangga".[25] [26] The fleet consists of 16 trains, each with six carriages. Each carriage has four doors on either side, except for the first and last carriages which have driver's cabins. Work on building the trains started in 2015 and they began to be delivered to Indonesia in 2018.[27] [28] The trains began to fully operate in conjunction with the inauguration of the line on March 24, 2019.

An additional fourteen sets (under Contract Package CP 206) will be added to the trains for the second phase leading to Ancol.

Incidents

Notes and References

  1. Web site: Engineering Services For Jakarta Mass Rapid Transit System Project .
  2. News: 28 November 2006 . Jepang Danai Mega Proyek MRT . 2021-02-21 . detikcom.
  3. News: 29 November 2006 . Jepang Beri Pinjaman Untuk Pembangunan MRT . 2021-02-21 . ANTARA News.
  4. Jakarta metro contracts signed . . 13 June 2013.
  5. Web site: Pengeboran Jalur "Underground" di MRT Fase I Sudah Selesai . 14 March 2017.
  6. News: MRT Jakarta focuses on constructing stations, depot. The Jakarta Post. 1 December 2017.
  7. News: The News We've All Been Waiting For: Jakarta MRT Open for Public in March. 22 February 2019. Jakarta Globe.
  8. News: Operasional MRT Diresmikan Jokowi 24 Maret. 18 March 2019. CNN Indonesia.
  9. Web site: Groundbreaking MRT Fase II Molor (Lagi). 30 January 2019.
  10. News: MRT Jakarta decides on Ancol as site of depot in Phase II construction. The Jakarta Post. 20 June 2019.
  11. News: Imbas Corona, Proyek MRT Jakarta Fase 2 Diundur ke Juni 2020. 29 April 2020. Kompas.
  12. News: Akhir 2021, Konstruksi MRT Mangga Besar-Kota Dimulai . Investor ID. 14 September 2021.
  13. News: Banyak Kendala, MRT Jakarta Fase 2A Nembus Perut Bumi 27 M . CNBC Indonesia . 18 August 2022 . id.
  14. Web site: Arini . Shafira Cendra . MRT Jakarta Fase 2 Ditargetkan Kelar 2032, Jalur Ancol Bakal Digarap . 2024-08-10 . detikfinance . id-ID.
  15. Web site: Mediatama . Grahanusa . 2012-08-30 . Foke: Pembangunan fisik MRT harus kelar tahun 2016 . 2022-10-31 . kontan.co.id . id.
  16. Web site: Simorangkir . Eduardo . Mengintip Skema Pembayaran Utang Pembangunan MRT Jakarta . 2022-10-31 . detikfinance . id-ID.
  17. Web site: Indraini . Anisa . Mengintip Desain 'Wah' 2 Stasiun Baru MRT Jakarta . 2022-10-31 . detikfinance . id-ID.
  18. Web site: Stasiun Blok M BCA MRT Jakarta . 2022-10-31 . jakartamrt.co.id.
  19. Web site: Melihat Kecanggihan Fasilitas di Stasiun MRT . 2022-10-31 . kumparan . id-ID.
  20. Web site: Liputan6.com . 2019-03-01 . Selain Wifi Gratis, Ini Beragam Fasilitas yang Ditawarkan MRT Jakarta . 2022-10-31 . liputan6.com . id.
  21. Web site: developer . mediaindonesia com . 2020-01-31 . Antisipasi Banjir, MRT Jakarta Siapkan Flood Gate . 2022-10-31 . mediaindonesia.com . id.
  22. Web site: MRT Jakarta Siapkan 5 Kawasan TOD . 2022-10-31 . kumparan . id-ID.
  23. Web site: 2020-07-02 . Serius Bangun Kawasan Trasit Terpadu, MRT Jakarta Bentuk Anak Usaha ITJ . 2022-10-31 . Bisnis.com . id.
  24. Web site: Menjajal Ratangga, MRT Jakarta yang Diuji Coba Hari Ini. 12 March 2019.
  25. Web site: 2015-03-03 . PROYEK MRT JAKARTA: Sumitomo Corporation Menangkan Tender Kereta Listrik . 2022-10-31 . Bisnis.com . id.
  26. Web site: Sugiharto . Jobpie . 2017-12-11 . Melihat Kereta MRT Jakarta Diproduksi: Tak Lagi Mirip Jangkrik . 2022-10-31 . Tempo . en.
  27. Web site: Mutmainah . Hesti Rika & Dinda Audriene . Dua Rangkaian Kereta MRT Datang, Siap Uji Coba Agustus . 2022-10-31 . ekonomi . id-ID.
  28. Web site: Yasmin . Puti Aini . Gerbong MRT Tiba, Menhub Cek Langsung ke Tanjung Priok . 2022-10-31 . detikfinance . id-ID.
  29. Web site: BeritaSatu.com . 2017-11-04 . Dinding Pembatas MRT Jatuh Menimpa Pengendara Motor . 2022-10-31 . beritasatu.com . id.
  30. Web site: 2017-11-05 . Dinding Beton Jatuh, PT MRT Jakarta Beberkan Hasil Investigasi . 2022-10-31 . Bisnis.com . id.
  31. Web site: Media . Kompas Cyber . 2024-05-30 . Operasional MRT Jakarta Dihentikan Sementara Imbas Besi Crane Jatuh ke Rel . 2024-05-30 . KOMPAS.com . id.
  32. Web site: Media . Kompas Cyber . 2024-05-31 . Hutama Karya: Jatuhnya Besi Konstruksi di Jalur MRT Dipicu Induksi Elektromagnetik . 2024-05-31 . KOMPAS.com . id.