MRT Line 10 explained

MRT Line 10
Status:Proposed
Locale:Quezon City, Pasig, Makati, Taguig
Start:Commonwealth Avenue
End:Ninoy Aquino International Airport
Stations:18
Linelength Km:22.5

The C5 Metro Rail Transit Line 10, also known as MRT Line 10 or MRT-10, is a proposed rapid transit line in the Philippines. When completed, the line will be approximately 22.5sp=usNaNsp=us long, with 16 stations. The line would run along Circumferential Road 5, with a terminus at Ninoy Aquino International Airport, and another terminus in Commonwealth Avenue with a possible interchange with MRT-7 at Tandang Sora Station. The line would then run from Commonwealth Avenue through Katipunan Avenue, where there may be a possible interchange with LRT Line 2 at the Aurora Station in Katipunan Avenue. The line would then continue to NAIA along the aforementioned Circumferential Road 5. The planned location of the Line's Train Depot would be on UP Diliman Property in Diliman, Quezon City.[1] [2]

The project is expected to cost 92.58 billion, and is currently waiting approval of the relevant approving bodies.[3]

Stations

Line 10 would have 18 stations. The known stations are as follows:[4]

NameStructure TypeTransfersLocation
ElevatedQuezon City
Pasig
Taguig
[5] Pasay

Notes and References

  1. Web site: C5 MRT 10 Project PPP Center. 2021-01-01. ppp.gov.ph. en.
  2. Web site: Vera. Ben O. de. 2019-11-18. Tycoons' unsolicited PPP projects bolster 'Build, Build, Build'. 2021-01-01. INQUIRER.net. en.
  3. Web site: Ordinario. Cai. 2018-10-01. Neda reviews proposal for MRT 10, 2 other infrastructure projects Cai Ordinario. 2021-01-01. BusinessMirror. en-US.
  4. 49th PBC&E Day 2. Philippine Chamber of Commerce and Industry. Facebook Live. 2023-10-25. 2023-10-28.
  5. Web site: 6 subway stations to rise on gov't properties. 2021-01-01. www.pna.gov.ph. en.