Lunderskov–Esbjerg railway line explained

Lunderskov–Esbjerg railway line
Native Name:Lunderskov-Esbjerg-banen
Native Name Lang:da
Type:Heavy rail
System:Danish railway
Status:Operational
Locale:Southern Jutland
Stations:9
Owner:Banedanmark
Operator:Danish State Railways
GoCollective
Character:Passenger trains
Freight trains
Linelength Km:55.7
Linelength Mi:34.6
Tracks:Double track
Linenumber:29
Electrification:
Speed Km/H:180
Speed Mph:110
Map Name:The Lunderskov–Esbjerg railway line
Map State:uncollapsed

The Lunderskov-Esbjerg line is the railway between Lunderskov and Esbjerg in Southern Jutland. It was opened on 3 October 1874, along with the first part of the Esbjerg–Struer railway line to Varde.

History

The construction of the line was authorised by a law of 24 April, 1868, together with the West Jutland longitudinal line, the Vendsyssel line and the Silkeborg line. On the same date, a law concerning the construction of the port of Esbjerg was also passed. In 1909, the railway bridge over Snæum river was destroyed by a 3m (10feet) storm surge.[1]

Stations

Operation

From January 2003, the Esbjerg-Bramming section is operated by both Arriva and DSB, while the Bramming-Lunderskov section is only be operated by DSB with both Regional services to Aarhus and InterCity services to Copenhagen.

Electrification

In the wake of the delay in the delivery of the scandal-ridden IC4 trains, it was proposed several times through the late '00s and early '10s to electrify the main line of the Danish railway network in order to be able to buy proven standard equipment to remedy the growing shortage of train equipment.[2] However, this was rejected just as many times, as electrification of the railway network would require a simultaneous upgrading of the signaling system, which was already being replaced throughout the country by ERTMS 2. [3]

In this context, the Esbjerg-Lunderskov section was interesting, because in 1997 the section had already been almost completely upgraded in preparation for a forthcoming electrification, just before the electrification program was cancelled.[4] On 7 February 2012, the Social Democrats, the Radical Left, SF, Venstre, DF, Liberal Alliance and the Conservative People's Party therefore agreed to electrify the track, so it was ready for electric trains by the end of 2015. [5]  

The main idea behind the electrification was that it would allow for the rapid purchase of 15 new electric train sets, which could replace a similar number of IC3 train sets. [6] To further secure the track for the future, it was subsequently decided, on 12 March 2013, by the same conciliation group to electrify the track with a system rated for 200km/h. [7]  

Electrification was later postponed to 2016 due to economies of scale, as the contractors could thereby go directly from this section to the other sections that were to be electrified subsequently. [8] The electrification was begun on 6 August 2017, [9] but was later hit by operational problems and a complete shutdown for electric trains, due to problems with the Siemens Sicat SX overhead distribution system. After a replacement of the faulty rope wheels, the track was reopened for electric operation on 13 August 2018.

References

Bibliography

See also

External links

Notes and References

  1. Book: Munch-Petersen, J.. 1910. The Storm Flood on December 3-4, 1909. 68-70. April 1, 2021.
  2. Nicolai Østergaard . IC4 delay forces DSB to modernize ME locomotives. Ingeniøren. 2010 . 2013-08-10.
  3. Nicolai Østergaard . Social Democrats: Government Pickles Electrification . Ingeniøren. 2009 . 2013-08-10.
  4. Web site: "Modernization of the Railway Network in Western Denmark". 2010 . 2013-08-10.
  5. Web site: "Broad agreement on electrification of the railway, etc. - Ministry of Transport". . Trm.dk . 2012-02-07 . 2013-08-10.
  6. Nicolai Østergaard . "Here is the solitaire card that gives DSB's commuters 2,000 extra seats . Ingeniøren. 2013-06-27 . 2013-08-10.
  7. Web site: "The train will be speeding at 200 km/h . dr.dk . 2013-03-13 . 2013-08-10.
  8. Østergaard, Christian. ""The first electrification of the railway will be delayed by one year " Ingeniøren, 16 December 2014. Accessed: 16 December 2014.
  9. https://www.jv.dk/vejen/Elektrificering-af-jernbane-fejres-med-festdag-i-to-byer/artikel/2524720 Railway electrification is celebrated with a feast day in two cities | jv.dk